Question

In: Mechanical Engineering

A batch production operation has a machine setup time of 4.0 hr and a processing time...

A batch production operation has a machine setup time of 4.0 hr and a processing time of 1.50 min per cycle. Three parts are produced each cycle. No tool handling time is included in the cycle. Part handling time each cycle is 30 sec. It consists of the worker obtaining three starting work units from a parts tray, loading them into the machine, and then after processing, unloading the completed units and placing them into the same tray. Each tray holds 27 work units. When all of the starting work units have been replaced with completed units, the tray of completed parts is moved aside and a new tray of starting parts is moved into position at the machine. This irregular work element takes 4.0 min. Batch quantity is 2,700 units.

Determine

(a) average cycle time,

(b) time to complete the batch,

(c) average production rate.

Solutions

Expert Solution


Related Solutions

differentiate between batch processing and real-time processing. What are the advantages and disadvantages of each form...
differentiate between batch processing and real-time processing. What are the advantages and disadvantages of each form of data processing? Which form is more likely to be used in a doctor's office in preparing the monthly patient bills?
Activity rate = Estimated overhead costs/Expected activity Machine Setup: $20000/50 = $400 per setup Special Processing:...
Activity rate = Estimated overhead costs/Expected activity Machine Setup: $20000/50 = $400 per setup Special Processing: $200000/8000 = $25 per machine hour General Factory: $250000/12500 = $20 per direct labor hour 2. Product A Product B Product C Direct labor costs 40000 190000 50000 Direct materials 100000 120000 60000 Overheads: Machine setup 12000 4000 6000 Special processing 125000 70000 75000 General factory 50000 237500 40000 Total overheads 187000 311500 121000 Total costs 327000 621500 231000 3. Actual manufacturing overhead 625500...
Suppose there is a two-machine line, where each machine has a 1 minute operation time. There...
Suppose there is a two-machine line, where each machine has a 1 minute operation time. There is also a buffer with 1 Kanban card between the machines. Part 1 How many parts are produced in the 1st hour? Assume the buffer is empty at time 0. How many parts are produced in the second hour?   Part 2 Suppose now that Machine 1 now fails every hour, 10 minutes into the hour, for 10 minutes. How many parts are produced in...
Consider the following four--?step assembly operation with quality problems. -The first resource has a processing time...
Consider the following four--?step assembly operation with quality problems. -The first resource has a processing time of 7 minutes per unit and one employee doing the operation ? The second resource has a processing time of 4 minutes per unit. It also has one employee doing the operation. However, this is a very delicate task and 0.79 of all products have to be scrapped after this step. ? Two workers are staffed for the third resource. No quality problems occur...
Consider the following four--‐step assembly operation with quality problems. -The first resource has a processing time o...
Consider the following four--‐step assembly operation with quality problems. -The first resource has a processing time of 5 minutes per unit and one employee doing the operation ‐ The second resource has a processing time of 4 minutes per unit. It also has one employee doing the operation. However, this is a very delicate task and 0.85 of all products have to be scrapped after this step. ‐ Two workers are staffed for the third resource. No quality problems occur...
A worker-machine operation was found to involve 4.6 minutes of machine time per cycle in the...
A worker-machine operation was found to involve 4.6 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker’s time averaged 3.1 minutes per cycle, and the worker was given a rating of 121 percent (machine rating is 100 percent). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance percentage of 13 percent of work time which is applied only to the worker element (not the machine element), determine...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days)...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days) and due date information for each job are as follows: Job Processing Time Due Date A B C D E F 2 1 5 3 4 7 3 2 12 4 8 11 Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean flow time and mean tardiness of the six jobs under each sequencing rule. Which rule would you recommend?
What factor influences the decision to employ real-time data collection with batch updating rather that purely real-time processing? Explain.
What factor influences the decision to employ real-time data collection with batch updating rather that purely real-time processing? Explain. 
The Tools Company uses a lathe to machine an aluminum block. The operation time is 5...
The Tools Company uses a lathe to machine an aluminum block. The operation time is 5 minutes. On average, the lathe requires maintenance after 200 parts. The average maintenance time is about 2 hours. (For the purpose of these calculations, maintenance is the same as failure. A.) What is the production rate of the machine in parts per minute? (Round to 3 decimal places) B.) Continuing from Part 1, the next operation after turning (lathe operation), is a milling operation....
A machine, currently in operation, has a market value of $4000. The machine can still be...
A machine, currently in operation, has a market value of $4000. The machine can still be used over the next three years, but its market value will become $3000, $2500, $2,000 at the end of the first, second, and third years, respectively. The operating expenses of the machine amount to $20,000 during the first year, and will increase by $5,000 each year thereafter. This machine can be replaced by a newer model, which cost $30,000 for installation and will have...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT