Question

In: Civil Engineering

1. To minimize the chance of losses, what process should a contractor use for updating the...

1. To minimize the chance of losses, what process should a contractor use for updating the schedule, if litigation is expected?

2. Explain how prefabrication can change the critical path of a schedule.

3. For the ISU Chiller Plant, how did craft workers lift heavy items inside the plant?

Solutions

Expert Solution

Answer 1)

Contractors often use completion date, bar chart and percentage of completion schedules to track progress, coordinate subcontractors and monitor delays but the law may require more sophisticated scheduling methods, such as Critical Path Method, Program Evaluation and Review Technique, or Precedent Diagramming Method, as a part of the contractor’s obligations in case of litigation.

For example, the contractor can add the amount of hours actually worked on a task to date, or change the percent complete. He can mark completed tasks as completed. He can carry out resource levelling if the reports show that there are people on the team who are taking on too much. This part of the update is all about the daily housekeeping and tracking.

There’s another part to updating the schedule, though. This relates to dealing with changes. As part of the update, he may have to add in new tasks. If a change has been approved, for example, there will be activities to enter related to the new work. Or the change might involve taking tasks out of the plan.

Such type of daily practices can help the contractor overcome losses in case of litigations.

Answer 2)

Prefabrication is the process of making buildings, or components of buildings, in a different location than the job site itself. Construction companies will transport the completed unit to the final site, where they will also complete the setup and handover buildings to their new owners. This process eliminates the need for traditionally sourced construction materials because off-site assembled parts result in less waste. As the raw materials are built off-site and shipped partially assembled, prefabrication reduces the cost of labor and the cost of materials.

This in turn, leads to a shorter schedule, no need of resource levelling, resource smoothening, on time schedule and also shortening of critical path. As critical path is shortened, float is minimized and due to availability of adequate labour, they can be more efficiently used to get better productivity and timely delivery of the project.

Answer 3)

In the ISU chiller plant, there is a skate-like board on which the heavy equipments are mounted and their wheels are offsetted and locked in the desired direction so that the board moves in no other direction. The workers just put the machine on the board and move it to the desired location. They call it as riding on air.


Related Solutions

What are some ways to minimize vitamin losses when cooking and storing food?
What are some ways to minimize vitamin losses when cooking and storing food?
What are some of your current concerns about inflation? What actions should be taken to minimize...
What are some of your current concerns about inflation? What actions should be taken to minimize your concerns? The term inflation has been loosely thrown around for years. Economists clarify what kind of inflation they are talking about - at least the accomplished economists do this. So for us here in class, let's use these terms to make sure we are all talking about the same thing: Price Inflation - the general increases in overall prices in the economy. This...
April is an independent contractor paid a total of $3,000 for 2016. What actions should you...
April is an independent contractor paid a total of $3,000 for 2016. What actions should you take to report April’s income? Do you need to complete forms for both April and government agencies? Are you required to withhold income tax for April? What if April received $500 instead of $3,000? Would you still report her income?
Question 1 There are many factors should consider to minimize the cost and drill well safely....
Question 1 There are many factors should consider to minimize the cost and drill well safely. Explain how mud program will improving the drilling rate.    Discuss five indicators present on "Driller's Console". What is the function of each indicator? Define each of the following terms used in drilling operations: Roller cone bits Cementing accelerator Bit Hydraulics Cement scratchers Explain the Advantages of AC Generators over DC Generators.   
1. A contractor is planning to use a crawler tractor with power shift transmission to push...
1. A contractor is planning to use a crawler tractor with power shift transmission to push 1,500 LCY. The tractor must haul the loose material up a 12% slope where it will be stockpiled for later removal. The contractor has measured the tractor blade load measurement: the pile length 12.6 ft, the pile width 8.1 ft, and the pile height 4 ft. The tractor weighs 44,400 pounds, and the coefficient of traction is estimated to be 0.7. The average haul...
Question 41 The 802.11 standard specifies the use of what technique in order to minimize the...
Question 41 The 802.11 standard specifies the use of what technique in order to minimize the potential for collisions? a. Carrier Sense Multiple Access with Collision Detection (CSMA/CD) b. Carrier Sense Single Access with Collision Adaptation (CSSA/CA) c. Carrier Sense Multiple Access with Collision Mitigation (CMSA/CM) d. Carrier Sense Multiple Access with Collision Avoidance (CSMA/CA) 1.25 points Question 42 The LLC sublayer is primarily concerned with managing MAC addresses in message frames. True False 1.25 points Question 43 The ST...
1. What are the key elements that determine if we should process an item further or...
1. What are the key elements that determine if we should process an item further or sell it at the split off point? 2. What are the key points we should consider in deciding whether to accept a special order?
what should the president's role be in the budgeting process
what should the president's role be in the budgeting process
Should an operating system process scheduler treat a process that makes extensive use of a hard-disk...
Should an operating system process scheduler treat a process that makes extensive use of a hard-disk storage device differently from one that makes extensive use of a solid-state storage device? Give your reasons.
For collaborative meetings, should the boss be a part of the process? What should the role...
For collaborative meetings, should the boss be a part of the process? What should the role of the boss be within meetings?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT