You are the new CM for a 2 story OFFICE building that is lagging behind by...

You are the new CM for a 2 story OFFICE building that is lagging behind by the following:

Wall framing in upper floor is incomplete and needs 2 more days to complete.

Doors for installation first floor have not been delivered.

Painting contractor crew cannot start painting since floor is not clear of debris ect.

Foreman has left due to family emergency.

Electrical contractor is 3 days behind.

Give your interpretation of how you will approach this situation and provide a method of solution. Note you are replacing the CM who has being removed and morale is low.

Solutions

Expert Solution

Firstly after taking the charge I will schedule a meeting with everyone. Will ask everyone about their problems and will ask them to give the solutions themselves.

After listening to everyone , I will make a chart on write the activities to be done and ask each of them to give a specific deadline, failing which they will suffer from penality.

Firstly I will start with quick desicion and result approach. I will ask the workers to clear the debris of the floor and ask the Painting contractor to start with the paint. Then I will enquire about the door installation , if they are not able to deliver on time then I will award the work to someone else who is capable to delivering as well as installing doors on time.

Will ask the electrical contractor as well as wall framing workers to recruit more labour force or to work in day and night schedule to complete the time within deadline.

I will have a word with Foreman and ask him to send a replacement so that work goes on smoothly.


Related Solutions

You are field manager for the general contractor on a multi-story office building under construction. The...
You are field manager for the general contractor on a multi-story office building under construction. The project has risen all 15 floors above the foundation. The roof is on and the exterior façade of the structure, consisting of alternating blue glass ribbon windows and red granite panels, has “dried in” the project many weeks ago. On the third, seventh and fifteenth floors, the executive offices located on the corners of the building have blue glass doors that lead outside to...
A governmental entity is the recipient of a bequest of a multi-story office building that the...
A governmental entity is the recipient of a bequest of a multi-story office building that the government intends to use as a new city hall. The building has a historical cost of $850,000; a book value in the hands of the benefactor of $700,000; and a fair value of $1,050,000. The city should recognize on its governmental fund financial statements, donations revenue of a) $-0-. b) $700,000. c) $850,000. d) $1,050,000 Explanation to why answer is d A governmental entity...
A government is the recipient of a bequest of a multi-story office building that the government...
A government is the recipient of a bequest of a multi-story office building that the government intends to use as a new city hall. The building has a historical cost of $850,000; a book value in the hands of the benefactor of $700,000; and a fair value of $1,050,000. The city should recognize on its governmental fund financial statements donations revenue of $-0-. $700,000. $850,000. $1,050,000 Explanation to the answer please
The property you are appraising is a five-story office building. Each floor has 10,000 square feet...
The property you are appraising is a five-story office building. Each floor has 10,000 square feet of rentable space and is suitable for single occupancy. Two tenants have leases. Floor 3 is occupied under a five-year lease with three years remaining. The current rental is $128,600 per year. Floor 4 is occupied under a new five-year lease and the rent is $150,000 per year. Floors 1, 2, and 5 are vacant. The rent being paid for the fourth floor is...
A large 20-story steel structure is planned for an office building the Denver Metropolitan. The exploration...
A large 20-story steel structure is planned for an office building the Denver Metropolitan. The exploration program revealed that foundation soil comprises of 25-foot clay with undrained shear strength of 1,000 psf overlying a thick stiff clay shale with the undrained shear strength of 3,000 psf. To avoid construction noise, the architect selected 3-ft diameter drilled shaft foundation. The drilled shafts are socketed 15 feet in the stiff clay shale. Calculate: a. The ultimate capacity of the drilled shaft. b....
You are the owner of a 65,000 square foot office building. You purchased the building five...
You are the owner of a 65,000 square foot office building. You purchased the building five years ago for $11,500,000. During that entire time the building was triple net leased to a tenant who was also responsible for all maitenance and capital upkeep. The net rent the tenant paid was flat at $12.50 per square foot per year. You have just negotiated a lease extension which will raise the rent to $14.00 per square foot for the next 10 years....
A large, two-story office building has a first floor which measures 500 ft by 750 ft...
A large, two-story office building has a first floor which measures 500 ft by 750 ft and a second story which is 500 ft by 500 ft. This building used 76,650 GWh of electricity last year and 120,035 therms of natural gas. a) What is the EUI of the building? How does this compare to similar buildings? b) Currently the office encourages carpooling and public transportation and therefore does not have a parking structure attached. They are considering adding this...
1. Company Amliba.Inc is considering building a second headquarter in a new city. The new office...
1. Company Amliba.Inc is considering building a second headquarter in a new city. The new office will create 5000 new jobs for the city. So the government is incentivized to support the project. The company plans to issue $100 million bond with coupon rate of 8%. Coupon will be paid annually and the bond matures in 5 year. As a form of support, local government guarantee the bond, so the YTM of the bond at issuance is 5%. Another bond...
A new office building has been constructed at a cost of $3,000,000. It is estimated to...
A new office building has been constructed at a cost of $3,000,000. It is estimated to have a life of 50 years with a value at that time of $200,000. It will have maintenance costs of $10,000 per year. It will also have major repairs costing $80,000 that occur at years 10, 20, 30 and 40. It will have additional repairs at the end of year 25 costing $250,000. Determine the equivalent uniform annual cost if the rate of interest...
A new office building has been constructed at a cost of $3,000,000. It is estimated to...
A new office building has been constructed at a cost of $3,000,000. It is estimated to have a life of 50 years with a value at that time of $200,000. It will have maintenance costs of $10,000 per year. It will also have major repairs costing $80,000 that occur at years 10, 20, 30 and 40. It will have additional repairs at the end of year 25 costing $250,000. Determine the equivalent uniform annual cost if the rate of interest...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT