Question

In: Finance

On January 3rd, 2009 Holiday Inn Hotels entered into a contract with Great Designs Inc., an...

On January 3rd, 2009 Holiday Inn Hotels entered into a contract with Great Designs Inc., an interior decorating firm, to have their hotel rooms re-decorated with new carpeting, bedspreads, curtains and wall art. Holiday Inn Hotels paid Great Designs Inc., $100,000 upfront and the work was to be completed by June 1st, 2009. On June 1st, 2009 work in 30% of the rooms was still not complete. The Hotel had a large conference group checking in on June 30th, 2009 that would result in all the rooms being occupied. The Hotel, therefore, terminated its contract with Great Designs Inc., and hired a different designer to finish the work. The new designer completed the work on June 30th, 2009 at an additional cost of $15,000. Answer the following questions:

  1. Did Holiday Inn Hotels act correctly in discharging its contract with Great Designs Inc.? Explain.
  1. Assuming that Holiday Inn Hotels did properly terminate Great Designs Inc., to what amount of damages is Holiday Inn Hotels entitled? Explain.

                                                                                                                                     

Solutions

Expert Solution

a. Yes, Holiday Inn Hotels acted correctly as there was breach of contract on the part of Great Designers Inc.by failing to adhere to the terms of the contract.

There were two options before Holiday Inn Hotels: 1. To ignore the breach and allow Great Designs Inc. to continue, in which case., it might have to refuse accommodation to the conference group, if the designer did not complete by June 30 or 2. To treat it as a discharge of contract by breach

So, the management of the hotel acted in a rational manner by terminating the contract with the designer and hiring another designer in its place.

b. If there were liquidated damages stipulated in the contract between Holiday Inn Hotels and Great Designs Inc., the damages would be computed accordingly.

Otherwise, Holiday Inn Hotels would claim from Great Designs Inc. restitution of $ 100,000 paid upfront as reduced by the amount earned by the designer for 30 % of the work done, plus damages of $ 15,000 for the additional cost of $ 15,000 paid to the new designer.


Related Solutions

1. On January 1, 2020, Ginseng Inc. entered into a forward contract to purchase U.S. $6,000...
1. On January 1, 2020, Ginseng Inc. entered into a forward contract to purchase U.S. $6,000 for $6,336 Canadian in 30 days. On January 15, the fair value of the contract was $40 (reflecting the present value of the future cash flows under the contract). Assume that the company would like to update its records on January 15. (a) Prepare only the necessary journal entries on January 1 and 15, 2020. 2. (Derivative Transaction) On April 1, 2020, Petey Ltd....
Boerne Inc entered into a one-year contract to lease equipment from Spring Branch Leasing on January...
Boerne Inc entered into a one-year contract to lease equipment from Spring Branch Leasing on January 1, 2018. The fair value of the leased equipment at the inception of the lease was $600,000. Lease term 1 year (4 quarterly periods) Quarterly lease payments $30,000 at Jan. 1, 2018, and at April 1, July 1, and Oct 1. Economic life of asset 5 years Interest rate charged by the lessor 10% Required: Boerne elected the short-term lease option. Appropriate adjusting entries...
On January 1 2019 Areej entered into a contract with a customer to construct a stadium...
On January 1 2019 Areej entered into a contract with a customer to construct a stadium for consideration of $ 200 million. The contract was expected to take 2 years to complete. At 31 December 2019 Areej had incurred costs of $ 55 million, Costs to complete are estimated at $ 50 million. In addition to these costs, Amir purchased plant to be used on the contract at a cost of $ 30 million. This plant was purchased on 1...
Sonia Inc. entered into a contract with Lala Inc. on July 1, 2018 to construct an...
Sonia Inc. entered into a contract with Lala Inc. on July 1, 2018 to construct an office building. The total contract price for construction of the building is $400,000. The building was completed on December 31, 2020. Sonia’s fiscal year end is December 31. Below is related information of Sonia Inc. regarding this construction: 2018 2019 2020 Actual cost incurred during the year $35,000 $215,000 $175,000 Estimated costs to complete 315,000 170,000 0 Billings to Lala Inc. to date 72,000...
On January 1, Revis Consulting entered into a contract to complete a cost reduction program for...
On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. Revis will receive $41,600 from Green at the end of each month. If total cost savings reach a specific target, Revis will receive an additional $20,800 from Green at the end of the contract, but if total cost savings fall short, Revis will refund $20,800 to Green. Revis estimates an 80% chance that cost savings will reach the...
On 1 January 2017 Kuntan Ltd entered into an operating lease contract for premises in the...
On 1 January 2017 Kuntan Ltd entered into an operating lease contract for premises in the Windhoek Weinhill Mall. The lease is to run for a period of 4 years (contract expires on 31 December 2020). As a result of several factors , the board of directors decided on 31 December 2018 to move the entity to Merua Mall with effect from 2 January 2019. However the lease contract determines the following: Operating lease payments per year (no escalation) N$10...
On January 1, Revis Consulting entered into a contract to complete a cost reduction program for...
On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. Revis will receive $53,600 from Green at the end of each month. If total cost savings reach a specific target, Revis will receive an additional $26,800 from Green at the end of the contract, but if total cost savings fall short, Revis will refund $26,800 to Green. Revis estimates an 80% chance that cost savings will reach the...
On January 12, 2009, Capsule Corp. signed a $4 million contract to construct an office and...
On January 12, 2009, Capsule Corp. signed a $4 million contract to construct an office and warehouse for a small wholesale company. The project was originally expected to be completed in two years, but difficulties in hiring a sufficient pool of skilled workers extended the completion date by an extra year. As well, significant increases in the price of steel in the second year resulted in cost overruns on the project. Capsule Corp. was able to negotiate a partial recovery...
C. On 1st January 2018, Global Drilling Ltd entered into a GHS22million contract for the construction...
C. On 1st January 2018, Global Drilling Ltd entered into a GHS22million contract for the construction of an office complex at Tema. The building was completed at the end of December 2018. During the period, the following payments were made to the contractor: Payment date Amount GHS’m 1 January 2018 2.00 31 March 2018 6.00 30 September 2018 12.00 31 December 2018 2.00 22.00 Global Drilling’s borrowings as at its year end of 31st December 2018 were as follows: ...
1. On January 1, Revis Consulting entered into a contract to complete a cost reduction program...
1. On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. Revis will receive $68,000 from Green at the end of each month. If total cost savings reach a specific target, Revis will receive an additional $34,000 from Green at the end of the contract, but if total cost savings fall short, Revis will refund $34,000 to Green. Revis estimates an 80% chance that cost savings will reach...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT