Question

In: Finance

Woodbridge Manufacturing case in Appendix E, and use the three primary project evaluation methods (NPV, IRR...

Woodbridge Manufacturing case in Appendix E, and use the three primary project evaluation methods (NPV, IRR and Payback) to determine the acceptability of this capital expenditure project. The cost of the new equipment to build a new product, including shipping and installation, (the initial investment outlay) is $100,000. The net additional receivables and inventory needed to support sales of the new project of $12,979 is scheduled to be incurred during year 1. (Side note: This is a little unusual. Generally these costs are incurred at time 0.) The new product is expected to have a five year life, and during that time the sum of the additional gross margin over and above what the previous product earned, plus the tax savings from the greater depreciation (the supplemental annual cash flows) amounts to $38,875 each year. In addition, the $14,469 in additional receivables and inventory (included in the net $12,979 year 1 investment outlay) will be recovered at the end of year 5 (the terminal value). (Second side note: You may ask, how can they recover more in receivables and inventory than they invested in the first place? The answer is the original amount is the net between what was invested for this new project ($14,469) and what had been already invested in the prior project ($1, 940)). In this case there was no salvage value on the machine that was used for the project, but if there were, the net after-tax cash flow from the salvage value would also be included in the terminal value. The Treasury Department at your company tells you the appropriate weighted average cost of capital (the discount rate) is 10% for this type of project. Calculate the NPV and state whether, from a financial standpoint, this project would be acceptable based on the NPV criteria. Calculate the IRR and Payback. What do these methods indicate as far as the acceptability of the project?

1) The marketing manager feels the total supplemental annual cash flows over the five years of the project were good at $194,375, but felt the adoption rate would likely be much faster, resulting in a cash flow profile of $38,875 in year 1, $77,750 in year 2, $38,875 in year 3, $29,200 in year 4 and $9,675 in year 5. How do these changes affect the project evaluation measures and acceptability?

The controller feels that the adoption rate would likely be much slower, resulting in a cash flow profile of $9,675 in year 1, $29,200 in year 2, $38,875 in year 3, $77,750 in year 4 and $38,875 in year 5. How do these changes affect the project evaluation measures and acceptability?

The company Treasury Department decides that the discount rate should be increased to 15%, based on a closer evaluation of the risks of the project. Going back to the original cash flow profile, what affect does this change have on the project return and its acceptability?

From these examples, sum up what you have learned about the NPV project evaluation method. What general rules can you draw from these calculations and results?

Solutions

Expert Solution

year cash flow negative flow positive flow
0 -100000 -100000
1 25896 -12979 38875
2 38875 38875
3 38875 38875
4 38875 38875
5 53344 14469 38875
npv payback irr
44551.85 2.906 years 24.5%

this project will be accepted as it has positive NPV & adds value for the company

1.

year total cash flow negative flow positive flow
0 -100000 -100000
1 25896 -12979 38875
2 77750 77750
3 38875 38875
4 29200 29200
5 24144 24144
npv payback irr
₹ 51,940.90 1.953 years 30.2%

this project will also be accepted as it has +ve NPV & good IRR lower payback period

2.

year cash flow negative flow positive flow
0 -100000 -100000
1 -3304 -12979 9675
2 29200 29200
3 38875 38875
4 38875 38875
5 53344 14469 38875
npv payback irr
₹ 10,010.00 3.906

12.9%

although lower NPV compared to other projects it will still be accepted. but in comparison 1. is much better.

In original cash flow profile situation if WACC increased to 15%

year cash flow negative flow positive flow
0 -100000 -100000
1 25896 -12979 38875
2 38875 38875
3 38875 38875
4 38875 38875
5 53344 14469 38875
npv
₹ 26,222.59

overall conclusion - the timing of cash flows is important in calculation of NPV. If higher positive cash flow is recieved early on then the NPV is higher compared to where cash flow is recieved in later period. If IRR & NPV conflicts use NPV ALWAYS  


Related Solutions

compare and contrast the npv and irr methods of capital investment evaluation
compare and contrast the npv and irr methods of capital investment evaluation
Discuss: Evaluate the strengths and limitations of NPV and IRR methods. Also, compare NPV and IRR.
Discuss: Evaluate the strengths and limitations of NPV and IRR methods. Also, compare NPV and IRR.
Explain the project assessment methods the organization should have used to assess these projects (IRR, NPV,...
Explain the project assessment methods the organization should have used to assess these projects (IRR, NPV, payback, and ARR). What are the advantages and drawbacks to using each one?
Use the present value tables in Appendix A and Appendix B to compute the NPV of...
Use the present value tables in Appendix A and Appendix B to compute the NPV of each of the following cash inflow: $30,750 received annually at the end of years 1 through 5 followed by $26,250 received annually at the end of years 6 through 10. The discount rate is 14 percent.
If the IRR for a project is 20%, then the project's NPV would be:
If the IRR for a project is 20%, then the project's NPV would be:
Calculations of the NPV, IRR and the payback for the project and an analysis of the...
Calculations of the NPV, IRR and the payback for the project and an analysis of the results. I need the excel formula calculation and analysis of the questions You have identified a potential opportunity for WBC, which involves undertaking a project that will have a ten-year life. The project requires an initial purchase of equipment and furniture totalling $4,500,000, plus ancillary programming capability and machinery costing $1,500,000. The equipment and furniture will depreciate and have a salvage value of $500,000...
14. (Toolkit – Decision Rules – PBAK, IRR, NPV) Calculating NPV & IRR: Your next project...
14. (Toolkit – Decision Rules – PBAK, IRR, NPV) Calculating NPV & IRR: Your next project provides an annual cash flow of $15,400 for nine years and costs $67,000 today. Is this a good project at 8% required return? How about 20%? Question 14 options: Yes, Yes Yes, No No, Yes No, No
How would you decide between two capital project choices if the different analysis methods (NPV, IRR,...
How would you decide between two capital project choices if the different analysis methods (NPV, IRR, etc.) were pointing to different options? What are the relative strengths and weaknesses of each? Original posts should contain a minimum of 120 words, and at least one response with a minimum of 40 words should be made to a classmate's post.
1. Compute the NPV of a project with the following information. The IRR is 9%. The...
1. Compute the NPV of a project with the following information. The IRR is 9%. The project life is 3 years. The initial cost is $19,000. In years 1 and 2 the cash inflows are $4,500 and $5,500, respectively. Cash flow in year 3 is missing. WACC is 12%.
Problem #4 Calculate NPV, Payback, Discounted Payback, IRR and Modified IRR for the following project Initial...
Problem #4 Calculate NPV, Payback, Discounted Payback, IRR and Modified IRR for the following project Initial Investment: -100,000 Annual project cash flow 22,000 for 6 years Cost of capital is 6%
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT