Question

In: Accounting

C. On 1st January 2018, Global Drilling Ltd entered into a GHS22million contract for the construction...

C. On 1st January 2018, Global Drilling Ltd entered into a GHS22million contract for the construction of an office complex at Tema. The building was completed at the end of December 2018. During the period, the following payments were made to the contractor:
Payment date
Amount
GHS’m 1 January 2018 2.00 31 March 2018 6.00
30 September 2018 12.00 31 December 2018 2.00 22.00
Global Drilling’s borrowings as at its year end of 31st December 2018 were as follows:
 10% 4-year Loan Note with simple interest payable annually, which relates specifically to the building project, loans outstanding at 31st December 2018 amounted to GHS7,000,000. Interest of GHS700,000 was incurred on these borrowings during the year, and interest income of GHS200,000
was earned on these funds while they were held in anticipation of payments.
 12.5% Five-year Loan Note with simple interest payable annually; debt outstanding at 1st January 2018 amounted to GHS10,000,000 and remained unchanged during the year.
 10% Five-year Loan Note with simple interest payable annually; debt outstanding at 1st January 2018 amounted to GHS15,000,000 and remained unchanged during the year
Required:
Calculate the borrowing costs to be capitalised.

Solutions

Expert Solution

The borrowing cost to be capitalised is :

  • the borrowing cost eligible for capitalisation on the specific borrowing is the actual borrowing costs incurred on that borrowing during the period, less any investment income on the temporary investment of those borrowings
  • The borrwoing cost eligible for capitalisation on the general borrowing is calculated by applying a weighted average borrowing cost rate on the average investment made during the year after applying specific borrowing.

Expenditures incurred in obtaining a qualifying asset are first allocated to any specific borrowings. The remaining expenditures are allocated to any general borrowings.

Statement showing calcualtion of general borrowings allocated to Expenditure

Expenditure

(in millions)

Amount allocated to general borrowings

(in millions)

Weighted for period outstanding

(in millions)

1January 2008 2 0 0*
31 March 2008 6 1* 1*9/12=0.75
30 September 2008 12 12 12*3/12=3
31 December 2008 2 2 2*0/12
22 million 3.75 million

Specific borrowings of GHS 7,000,000 are fully utilised; remainder of expenditure is therefore allocated to general borrowings.

The capitalisation rate relating to general borrowings is the weighted average of the borrowing costs applicable to the entity’s borrowings that are outstanding during the period, other than borrowings made specifically for the purpose of obtaining a qualifying asset.

Weighted average borrowing cost to be capitalised: 12.5%*(10/25)+10%(15/25)

=11%

Amount (GHS in million)
Specific loan 0.7
General borrowings (GHS 3.75 MILLION*11%) 0.4125
Total 1.1125
Less interest income on specific borrwoings .2
Amount eligible for capitalisation 1.3125

Borrowing cost to be capitalised=GHS 1,312,500


Related Solutions

ABC Ltd (“ABC”) entered into a contract on 1st January 20x6 to build a factory building...
ABC Ltd (“ABC”) entered into a contract on 1st January 20x6 to build a factory building for its customer on its customer’s land for $20 million. The completion is expected to be in two years’ time. ABC’s policy is to bill its clients based on 60% in the first year and the balance upon completion of the project. ABC has a 31st December financial year end. It has adopted FRS 115 Revenues from Contracts with Customers and adopts the input...
Stone Age Construction Pte Ltd entered into a construction contract to build a commercial building for Bintang Ltd for $9,200,000.
Stone Age Construction Pte Ltd entered into a construction contract to build a commercial building for Bintang Ltd for $9,200,000. Construction commenced on 1 January 2021. The following details relate to the construction project as at 31 December 2021:                                                   S'000Progress billing to-date             5,520Cash receipt to-date                  5,120Costs incurred to-date               4,032Estimated total costs                  6,400Stone Age Construction Pte Ltd accounted for the contract using the percentage-of-completion method.Required:(a) For the year ended 2021, calculate the percentage of completion to-date, revenue recognised for the year...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018. 2019 2020 Cost incurred during the year $2,624,000  $3,690,000  $2,074,600 Estimated costs to complete as of year-end 5,576,000   1,886,000 0 Billings during the year 2,200,000   4,114,000   3,686,000 Cash collections during the year 2,000,000   3,800,000   4,200,000 Westgate Construction uses the completed contract method of accounting for long-term construction contracts. Required: 1. Calculate the...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT