In: Accounting
Sonia Inc. entered into a contract with Lala Inc. on July 1, 2018 to construct an office building. The total contract price for construction of the building is $400,000. The building was completed on December 31, 2020. Sonia’s fiscal year end is December 31.
Below is related information of Sonia Inc. regarding this construction:
2018 |
2019 |
2020 |
|
Actual cost incurred during the year |
$35,000 |
$215,000 |
$175,000 |
Estimated costs to complete |
315,000 |
170,000 |
0 |
Billings to Lala Inc. to date |
72,000 |
217,000 |
400,000 |
Please answer each of the following questions and clearly label which question you are answering. You can prepare it in Word, in Excel, or handwrite it. Once completed, upload the completed Word or Excel document or a picture of the handwritten work (22 points).
Please use the percentage-of-completion method for items 1-5.
Please use the completed contract method for item 6.