In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
2018. 2019 2020
Cost incurred during the year
$2,624,000 $3,690,000 $2,074,600
Estimated costs to complete as of year-end
5,576,000 1,886,000 0
Billings during the year
2,200,000 4,114,000 3,686,000
Cash collections during the year
2,000,000 3,800,000 4,200,000
Westgate Construction uses the completed contract method of
accounting for long-term construction contracts.
Required:
1. Calculate the...