In: Accounting
in 2018 the westgate construction company entered into a contract to construct a road for Santa Clara County for 10,000,000 The road was completed in 2020. Calculate the amount of revenue and gross profit to be recognized in each of the 3 years assuming the following costs to incur and costs to complete information. ( Do not round intermediate calculations and round your final answers to the nearest whole dollar amount.
2018 2019 2020
Cost incurred during the year $2,016,000 3,890,000 3,290,000
Estimated cost to complete as of year end $5,184,000 3,190,000
Year 2018:
Up-to-date cost = 2,016,000
Estimated cost = 5,184,000
Total cost = 2,016,000 + 5,184,000 = 7,200,000
Rate of completion = Up-to-date cost / Total cost
= 2,016,000 / 7,200,000
= 0.28
Amount of revenue = Total contract price × Rate of completion
= 10,000,000 × 0.28
= $2,800,000 (Answer)
Gross profit = Amount of revenue – Cost incurred
= 2,800,000 – 2,016,000
= $784,000 (Answer)
Year 2019:
Up-to-date cost = 2,016,000 + 3,890,000 = 5,906,000
Estimated cost = 3,190,000
Total cost = 5,906,000 + 3,190,000 = 9,096,000
Rate of completion = Up-to-date cost / Total cost
= 5,906,000 / 9,096,000
= 0.6492
Amount of revenue = (Total contract price × Rate of completion) – Revenue of 2018
= (10,000,000 × 0.6492) – 2,800,000
= 6,492,000 – 2,800,000
= $3,692,000 (Answer)
Gross profit = Amount of revenue – Cost incurred
= 3,692,000 – 3,890,000
= - $198,000 (Answer)
Year 2020:
Up-to-date cost = 2,016,000 + 3,890,000 + 3,290,000 = 9,196,000
Estimated cost = 0 (since this is the project completion year)
Total cost = 9,196,000
Rate of completion = Up-to-date cost / Total cost
= 9,196,000 / 9,196,000
= 1
Amount of revenue = (Total contract price × Rate of completion) – Revenue of 2018
= (10,000,000 × 1) – 2,800,000 – 3,692,000
= 10,000,000 – 6,492,000
= $3,508,000 (Answer)
Gross profit = Amount of revenue – Cost incurred
= 3,508,000 – 3,290,000
= $218,000 (Answer)