In: Finance
Project A Project B
C0 ($25,000) ($23,000)
C1 $14,742 $ 6,641
C2 $14,742 $ 6,641
C3 $14,742 $ 6,641
C4 $ 6,641
C5 $ 6,641
C6 $ 6,641
C7 $ 6,641
C8 $ 6,641
C9 $ 6,641
1. Payback Method
Payback Period = Initial Investment / Net annual cashflows
For Project A:
Intial Investment = $25,000
Net annual cashflows = $14742
Payback Period (Project A) = 25000/14742 = 1.695 Years
For Project B:
Intial Investment = $23,000
Net annual cashflows = $ 6641
Payback Period (Project B) = 23000/6641 = 3.463 Years
Hence, Project A is better than Project B as money is getting returned in a much shorter time.
-------------------------------------------------------------------------------------------------------------
1. NPV Method
For Project A
We can calculate NPV in the following way
Discount Rate (r) | 12% | |||
years | 0 | 1 | 2 | 3 |
Cash-Outflows | 25,000 | |||
Cash-Inflows | 14,742 | 14,742 | 14,742 | |
Net Cashflows (Inflow - Outflow) | -25,000 | 14,742 | 14,742 | 14,742 |
Discounted
Cashflow = Net CF / (1+r)^years |
-25,000 | 13,163 | 11,752 | 10,493 |
NPV = sum of all discounted CF | 10,407.80 |
IRR = IRR (net CF) | 35.002% |
For Project B
We can calculate NPV in the following way
Discount Rate (r) | 12% | |||||||||
years | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
Cash-Outflows | 23,000 | |||||||||
Cash-Inflows | 6,641 | 6,641 | 6,641 | 6,641 | 6,641 | 6,641 | 6,641 | 6,641 | 6,641 | |
Net Cashflows (Inflow - Outflow) | -23,000 | 6,641 | 6,641 | 6,641 | 6,641 | 6,641 | 6,641 | 6,641 | 6,641 | 6,641 |
Discounted
Cashflow = Net CF / (1+r)^years |
-23,000 | 5,929 | 5,294 | 4,727 | 4,220 | 3,768 | 3,365 | 3,004 | 2,682 | 2,395 |
NPV = sum of all discounted CF | 12,384.91 | |||||||||
IRR = IRR (net CF) | 24.998% |
Hence we can see that NPV (Project B) > NPV (Project A).
Hence, we should chose Project B over Project A if NPV method is considered
------------------------------------------------------------------------------------------------------------------
3. IRR Method
In the above method we have already calculated the IRR
IRR (Project A) = 35.002%
IRR (Project B) = 24.998 %
Hence, IRR (Project A) > IRR (Project B)
Hence, we should chose Project A over Project B if IRR method is considered