In: Finance
Considering two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is less than the crossover rate.
Year | Project A | Project B | ||||
0 | −$27,000 | −$27,000 | ||||
1 | 10,000 | 18,100 | ||||
2 | 10,000 | 8,000 | ||||
3 | 18,000 | 10,120 | ||||
11.75%; A
11.75%; B
17.19%; B
18.64%; A
17.19%; A
Answer> Cross over rate is also known as weighted average cost of capital. In order to calculate the cross over rate, we will subtract the cash flows of project A and B for each year and solve it for NPV = 0. Let the crossover rate be r
Hence,
A B A-B PV
0 -27000 -27000 0 0
1 10000 18100 -8100 -8100/(1+r)
2 10000 8000 2000 2000/(1+r)^2
3 18000 10120 7880 7880/(1+r)^3
Now the difference in NPV should be zero for the cross over rate, hence
-8100/(1+r) + 2000/(1+r)^2 + 7880/(1+r)^3 = 0
since r cannot be negative, 1+r cannot be zero, hence removing 1+r from the denominator,
-8100 + 2000/(1+r) + 7880/(1+r)^2 = 0
(1+r)^2 * -8100 + (1+r)*2000 + 7880 = 0
8100(r^2 + 2*r + 1) - 2000*(1+r) = 7880
8100*r^2 + 16200*r +8100 - 2000 -2000*r =7880
8100*r^2 + 14200*r +6100 =7880
8100*r^2 + 14200*r -1780 = 0
On solving this, we get r = 0.1175
Hence r = 11.75%
now, calculating npv of each projects
Project a
10000/(1.1175) + 10000/(1.1175)^2 + 18000/(1.1175)^3 - 27000 = 8948.54 + 8007.65 + 12898.22 -27000 = 2854.41
Project b
18100/(1.1175) + 8000/(1.1175)^2 + 10120/(1.1175)^3 - 27000 = 16196.87 + 6406.12 + 7251.67 -27000 = 2854.66
Hence, if the required rate of return is less than the crossover rate, Project B should be selected, because it has a better cash flow in the 1st year, thus investment security is higher.
Hope this answers your question.