In: Accounting
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
Direct Labor-Hours per Unit |
Annual Production |
||
Hubs | 0.70 | 26,000 | units |
Sprockets | 0.30 | 48,000 | units |
Additional information about the company follows:
Hubs require $30 in direct materials per unit, and Sprockets require $16.
The direct labor wage rate is $11 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
Estimated | Activity | ||||
Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
Machine setups (number of setups) | $ | 29,160 | 135 | 108 | 243 |
Special processing (machine-hours) | $ | 129,500 | 3,700 | 0 | 3,700 |
General factory (organization-sustaining) | $ | 277,400 | NA | NA | NA |
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Solution
Activity rate | ||
Machine setups | $ 120.00 | Per setup |
Special processing | $ 35.00 | Per machine hour |
.
Hubs | Sprockets | |
Direct material | $ 30.00 | $ 16.00 |
Direct labor | $ 7.70 | $ 3.30 |
Overheads | $ 5.60 | $ 0.27 |
Total Cost per unit | $ 43.30 | $ 19.57 |
Working
Calculation of Activity rates | |||||
Activity Cost Pool | Activity driver | Overhead Cost (A) | Expected Activity (B) | Activity rate (A/B) | |
Machine setups | Number of setup | $ 29,160 | 243 | $ 120.00 | Per setup |
Special processing | Number of machine hour | $ 129,500 | 3700 | $ 35.00 | Per machine hour |
.
Cost assigned to Hubs | |||
Activity name | Activity Rates | Activity | ABC Cost |
(A) | (B) | (A x B) | |
Machine setups | $ 120.00 | 135.00 | $ 16,200.00 |
Special processing | $ 35.00 | 3,700.00 | $ 129500.00 |
Total Overheads assigned | $ 145,700.00 | ||
Production | 26,000.00 | ||
Overhead cost per unit | $ 5.60 |
.
Cost assigned to Sprockets | |||
Activity name | Activity Rates | Activity | ABC Cost |
(A) | (B) | (A x B) | |
Machine setups | $ 120.00 | 108 | $ 12,960 |
Special processing | $ 35.00 | 0 | $ 0 |
Total Overheads assigned | $ 12,960.00 | ||
Production | 48,000.00 | ||
Overhead cost per unit | $ 0.27 |