Question

In: Finance

Novell, Inc., has the following mutually exclusive projects. Year Project A. Project B __ __ 0...

Novell, Inc., has the following mutually exclusive projects.

Year Project A. Project B

__ __

0 22, 000 25,000

1 13,000 14,000

2 9,500 10,500   

3 3,100 9,500

a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g. 32.161.)

Project A. _____ years

Project B ______ years

a-2. If the company's payback period is two years, which, if either, of these projects should be chosen? (Choose the correct answer)

Project A

Project B

Both Projects

Neither project

b-1. What is the NPV for each project if the appropriate discount rate is 16 percent? (A negative answer should be indicated by a minus sing. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

Project A. ______

Project B. _______

b-2. Which, if either, of these projects should be chosen if the appropriate discount rate is 16 percent? (Choose the correct answer)

Project A

Project B

Both projects

Neither project

Solutions

Expert Solution

Cash flows:

Project A:
Year 0: -$22000
Year 1: $13000
Year 2: $9500
Year 3: $3100

We have taken negative sign in the year 0 cash flow as it is a cash outflow (investment made at the beginning).

Project B:
Year 0: -$25000
Year 1: $14000
Year 2: $10500
Year 3: $9500

Part a-1: Payback period for each project:

Cumulative cash flows for project A:
Year 0: -22000
Year 1: 13000-22000=-9000
Year 2: 9500-9000=500
Year 3: 3100

Payback period=Full years until recovery + (Unrecovered cost at the beginning of last year)/(Cash flow during last year)

=1+9000/9500=1.947368421 or 1.947 years (Rounded to three decimal places)

Cumulative cash flows for project B:
Year 0: -25000
Year 1: 14000-25000=-11000
Year 2: 10500-11000=-500
Year 3: 9500-500=9000

Payback period=2+500/9500=2.052631579 or 2.053 (Rounded to three decimal places)

Part a-2:
Answer: Project A should be chosen because the payback period is less than 2.
Given that the projects are mutually exclusive projects. Mutually exclusive projects are a set of projects out of which only one project can be selected.
Given that the company's payback period is two years, so the project with payback period less than 2 (that is project A) should be selected.

Part b-1:

Given that the discount rate is 16%
NPV=-Initial investment + Present value of future cash flows.
NPV for project A with the following cash flows:
Year 0: -$22000
Year 1: $13000
Year 2: $9500
Year 3: $3100
NPV=-22000+13000/(1+16%)^1+9500/(1+16%)^2+3100/(1+16%)^3
=-22000+13000/1.16+9500/1.3456+3100/1.560896
NPV of project A=-1747.017098 or -$1747.02 (Rounded to two decimal places)

NPV for project B with the following cash flows:
Year 0: -$25000
Year 1: $14000
Year 2: $10500
Year 3: $9500
NPV=-25000+14000/(1+16%)^1+10500/(1+16%)^2+9500/(1+16%)^3
=-25000+14000/1.16+10500/1.3456+9500/1.560896
NPV of project B=958.4238796 or $958.42 (Rounded to two decimal places)

Part b-2:
Answer: Project B should be chosen because of positive NPV of $958.42.


Related Solutions

Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000    –$30,000      1 15,500    16,500      2 12,000    10,500      3 3,600    12,000    a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Project A: Years Project B: Years a-2. If the company's payback period is two years, which, if either, of these projects should be...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$21,000...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$21,000    –$24,000      1 12,500    13,500      2 9,000    10,000      3 3,000    9,000       a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Project A: _____ years Project B: _____ years b-1. What is the NPV for each project if the appropriate discount rate is...
Novell, inc. has the following mutually exclusive projects. year Project A Project B 0 18,000 21,000...
Novell, inc. has the following mutually exclusive projects. year Project A Project B 0 18,000 21,000 1 11,000 12,000 2 7,500 8,500 3 2,700 7,500 a.1 calculate the payback period for each project. Project A Years Project B Years a.2. If the company's payback period is two years, which, if either, of these projects, should be chosen? ( Project A, Project B, Both projects, Neither project) b.1 what is the NPV for each project if the appropriate discount rate is...
Novell, Inc., Has the following mutually exclusive project Year Project A Project B 0 $20,000 $23,000...
Novell, Inc., Has the following mutually exclusive project Year Project A Project B 0 $20,000 $23,000 1 12,000 13,000 2 8,500 9,500 3 2,900 8,500 a.1. Calculate the payback period for each period ( do not round intermediate calculations and round your answers to decimal places) Project A Years Project B    Years a.2 If the company's payback period is two years, which, if either, of these projects, should be chosen? b.1. What is the NPV for each project if...
ri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
ri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,300 –$ 8,700 1 7,500 3,400 2 6,500 2,900 3 2,100 5,300 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project A Project B If the appropriate discount rate is 12...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,800 –$ 9,200 1 8,400 3,900 2 7,000 3,400 3 2,100 5,800 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project B Project A If the appropriate discount rate is 10...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 15,000 –$ 10,300 1 9,500 5,000 2 8,100 4,500 3 2,100 6,900 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A ___ years Project B ___ years Based on the payback period, which project should the company accept? Project B or A? Project B Project A If...
Greystone, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,600...
Greystone, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,600 –$ 9,000 1 8,200 3,700 2 6,800 3,200 3 2,100 5,600 a. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) b. Based on the payback period, which project should the company accept? c. If the appropriate discount rate is 15 percent, what is the NPV for each project? (Do not...
Maxwell Software, Inc., has the following mutually exclusive projects.    Year Project A Project B   0...
Maxwell Software, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$26,000    –$29,000      1 15,000    16,000      2 11,500    10,000      3 3,500    11,500       a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.)    Payback period   Project A years     Project B years    a-2. Which, if either, of these projects should be chosen? Project...
Maxwell Software, Inc., has the following mutually exclusive projects.    Year Project A Project B   0...
Maxwell Software, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000    –$30,000      1 15,500    16,500      2 12,000    10,500      3 3,600    12,000       a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.)    Payback period   Project A years     Project B years
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT