The Flixborough, UK, Cyclohexane Disaster, 1 June 1974
Cause of the accident :-
- Two months before the incident, R-5 was found to be
leaking.
- A 6 ft. long crack had developed.
- A water hose stream was directed to the crack to cool and
quench the small cyclohexane leak.
- The cooling water contained nitrates which encourage stress
corrosion of certain carbon steels.
- Thus, by trying to relieve the situation, the quenching was
actually acting as a promoter of corrosion Ultimately, the reactor
had to be removed from service.
- There was no experienced works manager, WM, available on site
at the time of the removal of R-5.
- The previous WM, a good maintenance engineer with 25 yrs of
experience, had quit because an anticipated promotion was given to
an outside person.
- As there was no experienced mechanical engineer on site, those
remaining decided to “fast track” or “scratch pad” a solution for
the intended by-pass.
- They sketched a full-scale by-pass line in chalk on the
maintenance floor.
- No stress analyses calculations were performed on the by-pass
connection.
- The by-pass line was quickly installed and the plant put into
start-up mode.
- Shortly after start-up, the by-pass line failed causing 40,000
lbs of cylcohexane to leak into the confined spaces of the reactor
support structure.
- Within two minutes, the vapor cloud exploded.
Lessons to be learnt from this disaster :-
- The main root cause of this incident was the use of cooling
water with nitrates to quench cyclohexane leaks on the
reactors.
- Another root cause was installing a by-pass line, or any line
for that mater, without stress analysis. This is a recipe for
disaster.
- A third root cause was management must recognize when they are
vulnerable to critical manpower changes.
- More control is required to conduct good engineering practices
once the plant is up and running.
- Poor location and poor construction of the control room.
- Plant was too congested at the design stage.
- Must minimize hazardous inventories.
- Process hazard review required at regular intervals.
- Plant must adhere to pressure vessel regulations.
- Require emergency planning with the community.