Question

In: Finance

Year Project A Project B 1 -400 -650 2 -528 210 3 -219 210 4 -150...

Year Project A Project B
1 -400 -650
2 -528 210
3 -219 210
4 -150 210
5 1100 210
6 820 210
7 990 210
8 -325 210

WACC 10%

What is NPV,IRR, for both projects and also solve for the crossover rate.

Solutions

Expert Solution

CALCULATION OF NPV,IRR AND CROSS OVER RATE
A B C D DISCOUNTED CASHFLOW DIFFEERENCE IN CASHFLOW(G)
Year Project A Project B DISOUNT FACTOR AT 10% PROJECT A PROJECT B
1 -400 -650 0.909 -363.6 -590.85 250
2 -528 210 0.826 -436.128 173.46 -738
3 -219 210 0.751 -164.469 157.71 -429
4 -150 210 0.683 -102.45 143.43 -360
5 1100 210 0.621 683.1 130.41 890
6 820 210 0.564 462.48 118.44 610
7 990 210 0.513 507.87 107.73 780
8 -325 210 0.467 -151.775 98.07 -535
NET PRESENT VALUE (NPV) 435.028 338.4
INTERNAL RATE OF RETURN FORMULS, =IRR(B4:B11) &=IRR(C4:C11)* 21% 26%
CROSS OVER RATE , FORMULA, =IRR(G4:G11)# 15%
*IRR IS THE RATE AT WHICH NV OF THE PROJECT EQUALS TO ZERO
EQUATION IS , NPV= Σ(CASHFLOW/(1+R)ˆt)
#CROSS OVER RATE IS THE RATE AT NPV OF ONE PROJECT EQUALS THE OTHER
EQUTION IS NPV OF PROJECT A = NPV OF PROJECT B
ie, Σ(CASHFLOW OF PROJECT A /(1+R)ˆt)=Σ(CASHFLOW OF PROJECT B/(1+R)ˆt)
CONCLUSION:
NPV OF PROJECT A 435.028
NPV OF PROJECT B 338.4
IRR OF PROJECT A 21%
IRR OF PROJECT B 26%
CROSS OVER RATE 15%

Related Solutions

Year Project A Project B 1 -400 -650 2 -528 210 3 -219 210 4 -150...
Year Project A Project B 1 -400 -650 2 -528 210 3 -219 210 4 -150 210 5 1100 210 6 820 210 7 990 210 8 -325 210 WACC 10% What is NPV,IRR, for both projects and also solve for the crossover rate.
A project cost $650 and has cash flows of $150 for the first year, $100 for...
A project cost $650 and has cash flows of $150 for the first year, $100 for the second year, and $80 in each of the subsequent years. What is the payback period of the project?
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project...
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: -$1000, 375, 375, 375, 375,-100 Project B: -$1000, 900, 700, 500, -200, 200 The cost of capital for both projects is 10% 1. Find the NPV and MIRR of projects A and B. If project A and B are mutually exclusive. 2. Find the crossover rate for projects A and B. 3. What is the profitability index for projects A and B? How...
Project Year 0 Year 1 Year 2 Year 3 Year 4 A    -$ 49 $ 25...
Project Year 0 Year 1 Year 2 Year 3 Year 4 A    -$ 49 $ 25 $ 22 $ 22 $ 15 B -$ 101 $ 19 $ 39 $ 51 $ 61 a. What are the IRRs of the two​ projects? b. If your discount rate is 4.8%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently?
TABLE 4 Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Cash...
TABLE 4 Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A -15000 6000 7000 6000 6000 6000 B -15000 7000 7000 7000 7000 7000 C -18000 12000 2000 2000 2000 2000 "Consider the cash flow of the three projects depicted in Table 4. The cost of capital is 7.5%. If an investor decided to take projects with a payback period of 2 years...
Car Index No: Miles (X) Maintenance (Y) 1 80,000 $1200 2 29,000 $150 3 53,000 $650...
Car Index No: Miles (X) Maintenance (Y) 1 80,000 $1200 2 29,000 $150 3 53,000 $650 4 13,000 $200 5 45,000 $325 6 50,000 ? Given: Maintenance expenses of 5 different cars for corresponding recorded miles. Problem: If a car driven 50,000 miles, how much would be the maintenance cost? Use Linear Regression equation to find the maintenance cost.
Project 1 Project 2 project 3 Project 4 Initial CF -4,000,000 -5,000,000 -10,000,000 5,000,000 Year 1...
Project 1 Project 2 project 3 Project 4 Initial CF -4,000,000 -5,000,000 -10,000,000 5,000,000 Year 1 CF 1,000,000 2,000,000 4,000,000 2,700,000 Year 2 CF 2,000,000 3,000,000 6,000,000 2,700,000 Year 3 CF 3,000,000 3,000,000 5,000,000 2,700,000 You have a $10 million capital budget and must make the decision about which investments your firm should accept for the coming year. The firm’s cost of capital is 12 percent. Use the information on the four projects to determine what project(s) your firm should...
Project 1 Project 2 Project 3 Project 4 Initial CF -4,000,000 -5,000,000 -10,000,000 5,000,000 Year 1...
Project 1 Project 2 Project 3 Project 4 Initial CF -4,000,000 -5,000,000 -10,000,000 5,000,000 Year 1 CF 1,000,000 2,000,000 4,000,000 2,700,000 Year 2 CF 2,000,000 3,000,000 6,000,000 2,700,000 Year 3 CF 3,000,000 3,000,000 5,000,000 2,700,000 You have a $10 million capital budget and must make the decision about which investments your firm should accept for the coming year. The firm’s cost of capital is 12 percent. Use the information on the four projects to determine what project(s) your firm should...
The income level of 4 individuals in country A are $150, $140, $210, and $220. The...
The income level of 4 individuals in country A are $150, $140, $210, and $220. The poverty line is $200. The HCR, PG, PGI, TPG. and SPGI are A: 50%; 27.5; 20; 110; 0.058 B: 50%; 27.5; 13.75; 110; 0.038 C. 50%; 20; 13.75; 80; 0.038 D. 50%; 27.5; 16.75; 140; 0.068
Year 0 1 2 3 4 Project 1 −$152 $19 $42 $58 $82 Project 2                            &nb
Year 0 1 2 3 4 Project 1 −$152 $19 $42 $58 $82 Project 2                                                −827 0 0 6,992 −6,490 Project 3 20 38 62 82                                                −246 a. For which of these projects is the IRR rule​ reliable? The IRR rule is reliable for (project 2 /project 3 /project 1) Unless all of the (positive/negative) cash flows of the project precede the (positive/negative) ones, the IRR rule may give the wrong answer and should not be used.​ Furthermore, there may...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT