Question

In: Finance

Project Year 0 Year 1 Year 2 Year 3 Year 4 A    -$ 49 $ 25...

Project Year 0 Year 1 Year 2 Year 3 Year 4

A    -$ 49 $ 25 $ 22 $ 22 $ 15

B -$ 101 $ 19 $ 39 $ 51 $ 61

a. What are the IRRs of the two​ projects?

b. If your discount rate is 4.8%​, what are the NPVs of the two​ projects?

c. Why do IRR and NPV rank the two projects​ differently?

Solutions

Expert Solution

a)Calculation of IRR(Internal rate of return)

IRR is the discounting rate at which Net present value of project is equal to zero.We can find the IRR of the projects by trial and error method as follows;

let assume the discount rate of 15% and 30%

NPV of both projects at 15% is as follows

Year Cash Flow($) Discounting factor@15% Present Value
Project A Project B Project A Project A Project B
0 -49 -101 1 -49 -101
1 25 19 .870 21.75 16.53
2 22 39 .756 16.63 29.48
3 22 51 .658 14.48 33.56
4 15 61 .572 8.58 34.89
NPV 12.44 13.46

NPV of both projects at 30% is as follows

Year Cash Flow($) Discounting factor@30% Present Value
Project A Project B Project A Project A Project B
0 -49 -101 1 -49 -101
1 25 19 .769 19.23 14.61
2 22 39 .592 13.02 23.09
3 22 51 .455 10.01 23.21
4 15 61 .350 5.25 21.35
NPV -1.49 -18.74

Now,IRR is;

=Lower Discount rate+(NPV at lower discount rate/Present value of cash inflows at lower discount rate-Present value of cash inflows at higher discount rate)*Difference between higher rate and lower rate)

Project A's IRR=15%+(12.44/61.44-47.51)*15

=15%+13.40

=28.40%

Thus IRR for project A is 28.40%(approx)

Project B's IRR=15%+(13.46/114.46-82.26)*15

=15%+6.27

=21.27%

Thus IRR for project B is 21.27%

b)Calculation of NPV

Statement showing calculation of NPV

Year Cash flow(a) Discounting Factor @4.8%(b) Present Value(a*b)
Project A Project B Project A Project B
0 -49 -101 1 -49 -101
1 25 19 .954 23.85 18.126
2 22 39 .910 20.02 35.49
3 22 51 .869 19.12 44.319
4 15 61 .830 12.45 50.63
NPV($) 26.44 47.57

c)NPV and IRR are similar in sense that both are discounted cash flow models.But they also differ in their main approach.NPV is abosolute measure i.e . it is the dollar amount of value added or lost by undertaking a project.IRR is a relative measure i.e it is the rate of return that a project offers over its life span.

The underlying cause of NPV and IRR conflict is the nature of projects(mutually exclusive or independent) and size of the project.


Related Solutions

Year 0 1 2 3 4 FCF ($ million) -30 25 25 25    25 FCF...
Year 0 1 2 3 4 FCF ($ million) -30 25 25 25    25 FCF for firm Canyon Shopping Center (CSC) is listed in the table above. After year 4 FCF is expected to grow at a constant rate of 2%. The weighted average cost of capital for CSC is 7%. If cash = $10 million, the market value of ASC’s debt = $35 million, and the number of shares outstanding is 5 million, estimate the share price.
Year 0 1 2 3 4 FCF ($ million) -30 25 25 25 25 FCF for...
Year 0 1 2 3 4 FCF ($ million) -30 25 25 25 25 FCF for firm Canyon Shopping Center (CSC) is listed in the table above. After year 4 FCF is expected to grow at a constant rate of 2%. The weighted average cost of capital for CSC is 7%. If cash = $10 million, the market value of ASC’s debt = $35 million, and the number of shares outstanding is 5 million, estimate the share price. Instruction: Type...
TABLE 4 Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Cash...
TABLE 4 Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A -15000 6000 7000 6000 6000 6000 B -15000 7000 7000 7000 7000 7000 C -18000 12000 2000 2000 2000 2000 "Consider the cash flow of the three projects depicted in Table 4. The cost of capital is 7.5%. If an investor decided to take projects with a payback period of 2 years...
Year 0 1 2 3 4 Project 1 −$152 $19 $42 $58 $82 Project 2                            &nb
Year 0 1 2 3 4 Project 1 −$152 $19 $42 $58 $82 Project 2                                                −827 0 0 6,992 −6,490 Project 3 20 38 62 82                                                −246 a. For which of these projects is the IRR rule​ reliable? The IRR rule is reliable for (project 2 /project 3 /project 1) Unless all of the (positive/negative) cash flows of the project precede the (positive/negative) ones, the IRR rule may give the wrong answer and should not be used.​ Furthermore, there may...
Determine the rate of return for this project. Year 0 1 2 3 4 5 Cash...
Determine the rate of return for this project. Year 0 1 2 3 4 5 Cash flow -$12,300 $4000 $4000 $3000 $3000 $3000 14.21% 12.75% 13.11% 13.85%
Consider the following project: Year 0 1 2 3 4 Project A -20.00 8.00 7.00 6.00...
Consider the following project: Year 0 1 2 3 4 Project A -20.00 8.00 7.00 6.00 7.00 Find the payback for this project. (ROUND TO TWO DECIMAL PLACES)
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 -$ 152 $22 $39 $58 $82 Project 2          −826 0 0 7,010 −6,506 Project 3 21 41 61 80   −247 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest1%​). c. What is the NPV of each project if the cost of capital is 5%​?20 %50%​? a. For which of these...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 −$151 $ 21 $ 39 $ 59 $ 80 Project 2                                                −824 00 00 6,999 −6,501 Project 3 2020 40 62 81 −245 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest 1%​). c. What is the NPV of each project if the cost of capital is 5%​? 20%​? 50%​? a....
A= 1 2 4 0 1 -2 -1 0 1 2 0 3 8 1 4...
A= 1 2 4 0 1 -2 -1 0 1 2 0 3 8 1 4 . Let W denote the row space for A. (a) Find an orthonormal basis for W and for W⊥. (b) Compute projW⊥(1 1 1 1 1 ).
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project...
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: -$1000, 375, 375, 375, 375,-100 Project B: -$1000, 900, 700, 500, -200, 200 The cost of capital for both projects is 10% 1. Find the NPV and MIRR of projects A and B. If project A and B are mutually exclusive. 2. Find the crossover rate for projects A and B. 3. What is the profitability index for projects A and B? How...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT