You have been asked to plan the following covert operation for the AIC:
Activity Duration (days) |
||||
Activity |
Immediate Predecessor |
Optimistic |
Most Likely |
Pessimistic |
A |
-- |
1 |
2 |
3 |
B |
A |
3 |
3 |
3 |
C |
B |
4 |
6 |
8 |
D |
A |
2 |
8 |
8 |
E |
A |
6 |
9 |
12 |
F |
D,C |
4 |
7 |
10 |
G |
D |
10 |
10 |
16 |
H |
D,E |
4 |
5 |
6 |
I |
F,G,H |
2 |
2 |
2 |
What is the probability of the project taking more than 25 days to complete? (In percentage and keep two decimal)