Question

In: Accounting

Flynn Industries has three activity cost pools and two products. It expects to produce 2,560 units...

Flynn Industries has three activity cost pools and two products. It expects to produce 2,560 units of Product BC113 and 1,220 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Expected Use of Cost Drivers per Product Activity Cost Pools Cost Drivers Estimated Overhead Expected Use of Cost Drivers per Activity Product BC113 Product AD908 Machine setup Setups $17,015 41 24 17 Machining Machine hours 105,252 5,012 1,120 3,892 Packing Orders 29,799 473 187 286 Using the above data, do the following: Prepare a schedule showing the computations of the activity-based overhead rates per cost driver. Activity Cost Pools Estimated Overhead Expected Use of Cost Drivers per Activity Activity-Based Overhead Rates Machine setup $ setups $ per setup Machining machine hours $ per machine hr. Packing orders $ per order $ LINK TO TEXT Prepare a schedule assigning each activity’s overhead cost to the two products. BC113 AD908 Activity Cost Pools Expected Use of Cost Drivers per Product Activity-Based Overhead Rates Cost Assigned Expected Use of Cost Drivers per Product Activity-Based Overhead Rates Cost Assigned Machine setup $ $ $ $ Machining $ $ Packing $ $ Total assigned costs $ $ LINK TO TEXT Compute the overhead cost per unit for each product. (Round answers to 2 decimal places, e.g. 12.25.) BC113 AD908 Overhead cost per unit $ $ Click if you would like to Show Work for this question: Open Show Work

Solutions

Expert Solution

Solution 1:

Computation of activity rates
Activity Estimated Overhead Cost Activity Base Usage of Activity Base Activity Rate
Machine setup $17,015.00 Setups 41 $415.00 Per Setup
Machining $105,252.00 Machine hours 5012 $21.00 Per Machine hour
Packing $29,799.00 Orders 473 $63.00 Per order
Total $152,066.00

Solution 2:

Assignment of overhead to Products
Activity cost pools BC 113 AD908
Expected use of cost drivers per product Activity based overhead rates Cost assigned Expected use of cost drivers per product Activity based overhead rates Cost assigned
Machine setup 24 $415.00 $9,960.00 17 $415.00 $7,055.00
Machining 1120 $21.00 $23,520.00 3892 $21.00 $81,732.00
Packing 187 $63.00 $11,781.00 286 $63.00 $18,018.00
Total $45,261.00 $106,805.00

Solution 3:

Computation of overhead cost per unit
Particulars BC113 AD908
Overhead assigned $45,261.00 $106,805.00
Nos of units 2560 1220
Overhead per unit $17.68 $87.55

Related Solutions

Sonoma Manufacturing has five activity cost pools and two products (a budget tape vacuum and a...
Sonoma Manufacturing has five activity cost pools and two products (a budget tape vacuum and a deluxe tape vacuum). Information is presented below:                                                                                                          Cost Drivers by Product Activity Cost Pool                     Cost Driver          Est. Overhead           Budget             Deluxe   Ordering and Receiving             Orders                     $   120,000                  600                  400 Machine Setup                          Setups                          297,000                  500                  400 Machining                                Machine hours           1,000,000            150,000            100,000 Assembly                                  Number of Parts        1,600,000         1,400,000            800,000 Inspection                                Inspections                   300,000                  550                  450 Instructions Compute the estimated overhead cost per unit for each product. Production is 700,000 units of Budget and 200,000 units of Deluxe. Round your answer to the nearest cent. Assume Sonoma used a more traditional OH...
Randel Manufacturing has five activity cost pools and two products (a budget tape vacuum and a...
Randel Manufacturing has five activity cost pools and two products (a budget tape vacuum and a deluxe tape vacuum). Information is presented below:                                                                                                          Cost Drivers by Product Activity Cost Pool                 Cost Driver       Est. Overhead      Budget            Deluxe Ordering and Receiving Orders                  $   130,000                  600                  400 Machine Setup Setups                       297,000                  500                  400 Machining                               Machine hours        1,000,000           150,000           100,000 Assembly Parts                       1,600,000        1,200,000           800,000 Inspection Inspections                300,000                  550                  450 Instructions Compute the overhead cost per unit for each product. Production is 700,000 units of...
Sonoma Manufacturing has five activity cost pools and two products (a budget tape vacuum and a...
Sonoma Manufacturing has five activity cost pools and two products (a budget tape vacuum and a deluxe tape vacuum). Production is 700,000 units of Budget and 200,000 units of Deluxe. Information is presented below: Cost Drivers by Product Activity Cost Pool Cost Driver Estimated Overhead Budget Deluxe Ordering and Receiving Orders $120,000                    600                                  400 Machine Setup Setups              $297,000                    500                                  400 Machining Machine hours                  $1,000,000            150,000                          100,000 Assembly Parts                  $1,400,000         1,200,000...
A company has two products: standard and deluxe. The company expects to produce 41,537 Standard units...
A company has two products: standard and deluxe. The company expects to produce 41,537 Standard units and 42,734 Deluxe units. It uses activity-based costing and has prepared the following analysis showing budgeted cost and cost driver activity for each of its three activity cost pools. Budgeted Activity of Cost Driver Budgeted OH Cost Standard Deluxe Activity 1: Purchasing $ 93,000 2,500 Purchases 5,250 Purchases Activity 2: Designing $ 92,000 4,500 Designs 5,500 Designs Activity 3: Shipping $ 87,000 3,000 Orders...
The Blossum Company has an activity –based costing system with three activity cost pools-Design, Marketing, and...
The Blossum Company has an activity –based costing system with three activity cost pools-Design, Marketing, and Other. The company’s overhead costs, which consist of equipment depreciation and indirect labor, have been allocated to the cost pools already. Costs in the Design cost pool are assigned to products based on Direct Labor Hours (DLH’s) and the costs in the Marketing cost pool are assigned to products based on the number of cases. Costs in the other cost pool are not assigned...
Corporation has an activity-based costing system with three activity cost pools—Processing, Supervising, and Other. In the...
Corporation has an activity-based costing system with three activity cost pools—Processing, Supervising, and Other. In the first stage allocations, costs in the two overhead accounts, equipment expense and indirect labor, are allocated to the three activity cost pools based on resource consumption. Data used in the first stage allocations follow: Overhead costs: Equipment expense $73,000 Indirect labor $1,000 Distribution of Resource Consumption Across Activity Cost Pools: Processing Supervising Other Equipment expense 20% 10% 70% Indirect labor 20% 20% 60% In...
Pecot Industries has provided the following data from its activity-based costing system: Activity Cost Pools Est....
Pecot Industries has provided the following data from its activity-based costing system: Activity Cost Pools Est. Overhead Cost Expected Activity Assembly $498,520 44,000 Machine hours Processing orders $54,263 1,100 Orders Inspection $77,589 1,110 Inspection hours Data concerning Pecot’s product LB28 appears below:             Number of units produced      430             Machine hours                        990             Number of orders                    70             Inspection hours                      20             Direct materials cost               $37.74 per unit             Direct labor cost                     $10.45 per unit Calculate the total unit product...
Diehl Corporation uses an activity-based costing system with three activity cost pools. The company has provided...
Diehl Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity based costing system: Costs: Manufacturing overhead $ 480,000 Selling and administrative expenses 100,000 Total $ 580,000 Distribution of resource consumption: Activity Cost Pools Order Size Customer Support Other Total Manufacturing overhead 5% 85% 10% 100% Selling and administrative expenses 60% 20% 20% 100% The "Other" activity cost pool consists of the costs of idle capacity...
Deemer Corporation has an activity-based costing system with three activity cost pools--Processing, Supervising, and Other. In...
Deemer Corporation has an activity-based costing system with three activity cost pools--Processing, Supervising, and Other. In the first stage allocations, costs in the two overhead accounts, equipment expense and indirect labor, are allocated to the three activity cost pools based on resource consumption. Data used in the first stage allocations follow: Overhead costs: Equipment expense $ 128,000 Indirect labor $ 11,000 Distribution of Resource Consumption Across Activity Cost Pools: Activity Cost Pools Processing Supervising Other Equipment expense 0.20 0.60 0.20...
Ollivier Corporation has an activity-based costing system with three activity cost pools-Processing, Supervising, and Other. In...
Ollivier Corporation has an activity-based costing system with three activity cost pools-Processing, Supervising, and Other. In the first stage allocations, costs in the two overhead accounts, equipment expense and indirect labor, are allocated to the three activity cost pools based on resource consumption. Data used in the first stage allocations follow:   Overhead costs:   Equipment expense $53,000   Indirect labor $6,400 Distribution of Resource Consumption Across Activity Cost Pools: Activity Cost Pools Processing Supervising Other   Equipment expense 0.50     0.40     0.10...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT