In: Accounting
Sonoma Manufacturing has five activity cost pools and two products (a budget tape vacuum and a deluxe tape vacuum). Production is 700,000 units of Budget and 200,000 units of Deluxe. Information is presented below: |
|||||
Cost Drivers by Product |
|||||
Activity Cost Pool |
Cost Driver |
Estimated Overhead |
Budget |
Deluxe |
|
Ordering and Receiving |
Orders |
$120,000 |
600 |
400 |
|
Machine Setup |
Setups |
$297,000 |
500 |
400 |
|
Machining |
Machine hours |
$1,000,000 |
150,000 |
100,000 |
|
Assembly |
Parts |
$1,400,000 |
1,200,000 |
800,000 |
|
Inspection |
Inspections |
$300,000 |
550 |
450 |
|
Total |
$3,117,000 |
||||
Round answers to the nearest cent. |
Required:
Assume simple costing system used machine hours only as the single cost allocation base.
Compute a single overhead rate
Compute the amount of overheads allocated to Budget and Deluxe.
Compute the amount of overhead per unit allocated to Budget and Deluxe.
b. |
Compute total overhead costs assigned to each product and the overhead cost per unit for each product, using activity-based costing. |
Question A
Single Plantwide Overhead Rate = Total Estimated Manufacturing Overhead / Total Machine Hours
Total Estimated Manufacturing Overhead = $ 31,17,000
Total Machine Hours = 250,000 Hours
Single Plantwide Overhead Rate = 31,17,000 / 250,000
Single Plantwide Overhead Rate = $ 12.47 per Machine Hour
Question 2 and 3
Particulars | Budget | Deluxe |
Machine Hours | 150,000 | 100,000 |
* Single Plantwide Overhead Rate | 12.47 | 12.47 |
Total Estimated Manufacturing Overhead | 1,870,200 | 1,246,800 |
÷ Number of Units Produced | 700,000 | 200,000 |
Manufacturing Overhead Cost per Unit | 2.67 | 6.23 |
Question 4
Manufacturing Overhead Allocation using Activity Based Costing
A | B | C=A/B | ||
Particulars | Activity Cost | Activity Driver | Activity Allocation Rates | |
Ordering and Receiving | 120,000 | 1,000 | 120 | Per Order |
Machine Setups | 297,000 | 900 | 330 | Per Setup |
Machining | 1,000,000 | 250,000 | 4 | Per Machine Hour |
Assembly | 1,400,000 | 2,000,000 | 0.70 | Per Part |
Inspection | 300,000 | 1,000 | 300 | Per Inspection |
Total | 31,17,000 |
Activity Driver is Total of Activity Driver for Budget and Deluxe.
A | B | C=A*B | D | E = A*D | |
Particulars | Activity Allocation Rate | Activity for Budget | Total Overhead for Budget | Activity for Deluxe | Total Overhead for Deluxe |
Machining and Ordering | 120 | 600 | 72,000 | 400 | 48,000 |
Machine Setup | 330 | 500 | 165,000 | 400 | 132,000 |
Machining | 4 | 150,000 | 600,000 | 100,000 | 400,000 |
Assembly | 0.70 | 1,200,000 | 840,000 | 800,000 | 560,000 |
Inspection | 300 | 550 | 165,000 | 450 | 135,000 |
Total | 1,842,000 | 1,275,000 |
Particulars | Budget | Deluxe |
Total Manufacturing Overheads | 1,842,000 | 1,275,000 |
÷ Number of Units Produced | 700,000 | 200,000 |
Manufacturing Overhead per Unit | 2.63 | 6.38 |