Question

In: Civil Engineering

1A. Identify a new project that has been constructed in your area. Who was the lead...

1A. Identify a new project that has been constructed in your area. Who was the lead design firm? Identify the subconsultants/designers hired by this firm. Identify the training and/or registration of the key designers that were used on the project.

B.Within the Architecture-Engineering-Construction (AEC) industry you hear the terms project Manager and program Manager used. Do some research and describe the difference.

C. Visit a job site and identify the trades that are presently working there. Write up a description of work for each trade.

Solutions

Expert Solution

1.A.The lead designer will often be the architect, however this is not necessarily the case and appointment documents for other consultants will generally offer provision for them the be nominated lead designer.

The lead designer (sometimes referred to as the design coordinator), directs and co-ordinates other designers in the consultant team as well as any specialist designersthat are appointed. This role might include:

  • Co-ordinating site surveys.
  • Co-ordinate the preparation of information for the project brief.
  • Co-ordinating the preparation of designs and specifications.
  • Integrating different aspects of the design and their interfaces into the overall design.
  • Co-ordinating internal and external consultations and design reviews.
  • Defining the form and content of design information to be prepared.
  • Reporting to the client on design matters and seeking approvals.
  • Co-ordinating the preparation of schedules of inspections, tests, mock ups and samples.
  • Co-ordinating consultations, negotiations and submissions to planning authorities and other statutory and non statutory authorities.
  • Co-ordinating the preparation of tender documentationand reviewing submissions.
  • Co-ordinating quality control systems.
  • Co-ordinating the issue of production information to contractors and the review of designs prepared by contractors.
  • Co-ordinating procedures for inspections, commissioning, testing and client training.

1.B.The main distinction is that a Project Manager will create, drive, and execute project planning on one, or more likely multiple projects. The Program Manager is overseeing multiple Project Managers and all of their respective work, and tying it into a larger picture and documents/software to track all deliverables across a much larger picture (this includes interactions, dependencies, and larger blockers to make sure all projects under them go off as smoothly as possible). In most orgs, this means operatively that the Project Manager might have 10% or more of a large program, whereas the Program Manager should be looking at and overseeing all of it. In larger orgs, there is sometimes also a Portfolio Manager to oversee multiple programs, although in many cases this is a Director level task.

1.C.Trades:

  • Boilermaker
  • Carpenter
  • Carpet Installer
  • Cement & Concrete Finisher
  • Dredge Operator
  • Electrician/Technician
  • Equipment Operator
  • Elevator Mechanic
  • Estimator
  • Fencer/Fence Erector
  • Flooring Installer
  • Foreman
  • Glazier
  • HVAC Tech
  • Insulation Worker
  • Iron-worker
  • Laborer
  • Landscaper
  • Mason
  • Millwright
  • Painter
  • Pile Driver Operator
  • Plasterer
  • Plumber, Pipefitter, Steamfitter
  • Sheet Metal Worker
  • Safety Manager
  • Construction Manager
  • Ironworker
  • Roofer
  • Safety Manager
  • Welder

Related Solutions

You are a project manager who has been assigned to a new project that would require  “Porting...
You are a project manager who has been assigned to a new project that would require  “Porting of the existing backend server code-base that currently runs on the OS platform ABC to another OS platform XYZ so that the backend sever code-base would run on XYZ OS platform as well the OS platform ABC, when finished”.  Both of the OS platforms are used heavily by the company and are well understood by the technical staff. The functionalities would remain the same and...
A new office building has been constructed at a cost of $3,000,000. It is estimated to...
A new office building has been constructed at a cost of $3,000,000. It is estimated to have a life of 50 years with a value at that time of $200,000. It will have maintenance costs of $10,000 per year. It will also have major repairs costing $80,000 that occur at years 10, 20, 30 and 40. It will have additional repairs at the end of year 25 costing $250,000. Determine the equivalent uniform annual cost if the rate of interest...
A new office building has been constructed at a cost of $3,000,000. It is estimated to...
A new office building has been constructed at a cost of $3,000,000. It is estimated to have a life of 50 years with a value at that time of $200,000. It will have maintenance costs of $10,000 per year. It will also have major repairs costing $80,000 that occur at years 10, 20, 30 and 40. It will have additional repairs at the end of year 25 costing $250,000. Determine the equivalent uniform annual cost if the rate of interest...
Need a good explanationIf a new railroad embankment is to be constructed in an area...
If a new railroad embankment is to be constructed in an area that restricts how wide its base may be, name some of the design alternatives you would consider to limit the embankment width at its base.
You have been asked to replace the project manager who was heading up your firm’s new...
You have been asked to replace the project manager who was heading up your firm’s new compensation and benefits system. One of the reasons the project manager is being replaced is because the project schedule had the wrong resources assigned (e.g., resources who do not fully understand compensation and benefits). You have been asked to solve this problem quickly by either replacing the resources or getting the resources up-to-speed on compensation and benefits. Present your recommendation for solving this critical...
You are the lead S-Corporations tax specialist in your area. Your client, Cathyrn, has purchased an...
You are the lead S-Corporations tax specialist in your area. Your client, Cathyrn, has purchased an S Corporation and needs to be versed on how this type of corporation works. Identify three operating issues (e.g. accounting period, income/loss allocation, operating/liquidating distributions, stock basis calculations, fringe benefit rules) that Cathyrn should be aware of in managing this form of business.
Question. Your boss has instructed you to evaluate a new project the firm has been considering...
Question. Your boss has instructed you to evaluate a new project the firm has been considering moving forward with. Other analysts in the firm have identified projected cash flows for the project, which are shown below. The firm's WACC is 9.7%. Given the additional risk of this project, your boss has asked you to add 1.2% to the discount rate for this project. Identify the project's Net Present Value, Internal Rate of Return, and Discounted Payback Period (with fractional years...
Exercise # 1. Analyze an actual project recently built in your area. Identify the major activities...
Exercise # 1. Analyze an actual project recently built in your area. Identify the major activities that occurred in each of the project phases and who accomplished them. Develop a flowchart or network diagram and present it to your class. 2. Class members should each examine a different local project and determine the following: • Project cost per square foot • Economic Life • Design-construction time • Income in dollars per square foot • Compare the viability of different project...
You have been appointed as the Project Manager for a New Product Launch Project by your...
You have been appointed as the Project Manager for a New Product Launch Project by your company. You must prepare a set of documents for the project kick-off meeting coming up next month. Task 1: Prepare a Project Charter for the New Product Launch Project (according to the choice of your product as explained above). Please use the Project Charter template given below Name of the Project Background [Why is the project being undertaken? Describe an opportunity or problem that...
Your hospital has been approached by a major employer in your market area to negotiate a...
Your hospital has been approached by a major employer in your market area to negotiate a preferred provider arrangement. The employer is seeking a 25% discount from your current charges. Describe a structure that you might use to summarize the financial implications of this decision. Describe the factors that are critical in this decision.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT