In: Accounting
NPVs, IRRs, and MIRRs for Independent Projects
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000 and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows:
| Year | Truck | Pulley | ||
| 1 | $5,100 | $7,500 | ||
| 2 | 5,100 | 7,500 | ||
| 3 | 5,100 | 7,500 | ||
| 4 | 5,100 | 7,500 | ||
| 5 | 5,100 | 7,500 | ||
Calculate the IRR for each project. Round your answers to two decimal places.
Truck:  %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 2
Pulley:  %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 4
Calculate the NPV for each project. Round your answers to the nearest dollar, if necessary. Enter each answer as a whole number. For example, do not enter 1,000,000 as 1 million.
Truck: $  
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 6
Pulley: $  
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 8
Calculate the MIRR for each project. Round your answers to two decimal places.
Truck:  %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 10
Pulley:  %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 12
a.
Computations of IRR using excel:
| 
 A  | 
 B  | 
 C  | 
|
| 
 1  | 
 Year  | 
 Cash Flow(Truck)  | 
 Cash Flow (Pulley)  | 
| 
 2  | 
 0  | 
 ($15,000)  | 
 ($21,000)  | 
| 
 3  | 
 1  | 
 $5,100  | 
 $7,500  | 
| 
 4  | 
 2  | 
 $5,100  | 
 $7,500  | 
| 
 5  | 
 3  | 
 $5,100  | 
 $7,500  | 
| 
 6  | 
 4  | 
 $5,100  | 
 $7,500  | 
| 
 7  | 
 5  | 
 $5,100  | 
 $7,500  | 
| 
 8  | 
 IRR  | 
 20.76%  | 
 23.06%  | 
Suppose the excel sheet looks like above table.
Insert formula in cell B8 as “=IRR(B2:B7) to get IRR for the project Truck as 20.76 %
Similarly to get IRR of Pulley inset formula “=IRR(C2:C7) in cell C8, which will display IRR as 23.06 %
IRR for Truck is 20.76 %
The Project should be accepted as IRR is higher than firm’s cost of capital 9 %.
b.
IRR for Pulley is 23.06 %
The Project should be accepted as IRR is higher than firm’s cost of capital 9 %.
c.
Computation of NPV:
| 
 Year  | 
 Computation of PV Factor  | 
 PV Factor @ 9 % (F)  | 
 Cash Flow (Truck) CT  | 
 Cash Flow (Pulley) CP  | 
 PV (Truck) (=F x CT)  | 
 PV (Pulley) (=F x CP)  | 
| 
 0  | 
 1/(1+0.09)^0  | 
 1  | 
 ($15,000)  | 
 ($21,000)  | 
 ($15,000.000000)  | 
 ($21,000.000000)  | 
| 
 1  | 
 1/(1+0.09)^1  | 
 0.91743119266  | 
 $5,100  | 
 $7,500  | 
 $4,678.899083  | 
 $6,880.733945  | 
| 
 2  | 
 1/(1+0.09)^2  | 
 0.84167999327  | 
 $5,100  | 
 $7,500  | 
 $4,292.567966  | 
 $6,312.599949  | 
| 
 3  | 
 1/(1+0.09)^3  | 
 0.77218348006  | 
 $5,100  | 
 $7,500  | 
 $3,938.135748  | 
 $5,791.376100  | 
| 
 4  | 
 1/(1+0.09)^4  | 
 0.70842521107  | 
 $5,100  | 
 $7,500  | 
 $3,612.968576  | 
 $5,313.189083  | 
| 
 5  | 
 1/(1+0.09)^5  | 
 0.64993138630  | 
 $5,100  | 
 $7,500  | 
 $3,314.650070  | 
 $4,874.485397  | 
| 
 NPV  | 
 $4,837.221443  | 
 $8,172.384475  | 
NPV for Truck is $ 4,837
The Project should be accepted as NPV is positive.
d.
NPV for Pulley is $ 8,172
The Project should be accepted as NPV is positive.
e.
MIRR = n √ Terminal Value of Cash Inflow/Present Value of Cash Outflow – 1
n = No. of years of investment = 5
| 
 Year  | 
 Cash Flow (Truck) CT  | 
 Cash Flow (Pulley) CP  | 
 Computation of Future Value Factor  | 
 Future Value factor @ 9 % (F)  | 
 Future value Truck (F x CT)  | 
 Future value Pulley (F x CP)  | 
| 
 1  | 
 $5,100  | 
 $7,500  | 
 (1.09)^4  | 
 1.41158161  | 
 $7,199.066211  | 
 $10,586.862075  | 
| 
 2  | 
 $5,100  | 
 $7,500  | 
 (1.09)^3  | 
 1.295029  | 
 $6,604.647900  | 
 $9,712.717500  | 
| 
 3  | 
 $5,100  | 
 $7,500  | 
 (1.09)^2  | 
 1.1881  | 
 $6,059.310000  | 
 $8,910.750000  | 
| 
 4  | 
 $5,100  | 
 $7,500  | 
 (1.09)^1  | 
 1.09  | 
 $5,559.000000  | 
 $8,175.000000  | 
| 
 5  | 
 $5,100  | 
 $7,500  | 
 (1.09)^0  | 
 1  | 
 $5,100.000000  | 
 $7,500.000000  | 
| 
 Terminal value  | 
 $30,522.024111  | 
 $44,885.329575  | 
MIRR for Truck = 5 √ $30,522.024111 /$ 15,000 – 1
= [5 √ (2.03480160740)] – 1
= 1.152668471964 – 1
= 0.152668471964 or 15.27 %
Project Truck should be accepted as cost of capital is lower than MIRR.
MIRR for Pulley = 5 √ $44,885.329575 /$ 21,000 – 1
= [5 √ (2.13739664643)] – 1
= 1.164064445844 – 1
= 0.164064445844 or 16.41 %
Project Pulley should be accepted as cost of capital is lower than MIRR.