Question

In: Accounting

NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...

NPVs, IRRs, and MIRRs for Independent Projects

Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000 and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows:

Year Truck Pulley
1 $5,100 $7,500
2 5,100 7,500
3 5,100 7,500
4 5,100 7,500
5 5,100 7,500
  1. Calculate the IRR for each project. Round your answers to two decimal places.

    Truck:  %

    What is the correct accept/reject decision for this project?
    -Select-AcceptRejectItem 2


    Pulley:  %

    What is the correct accept/reject decision for this project?
    -Select-AcceptRejectItem 4


  2. Calculate the NPV for each project. Round your answers to the nearest dollar, if necessary. Enter each answer as a whole number. For example, do not enter 1,000,000 as 1 million.

    Truck: $  

    What is the correct accept/reject decision for this project?
    -Select-AcceptRejectItem 6


    Pulley: $  

    What is the correct accept/reject decision for this project?
    -Select-AcceptRejectItem 8


  3. Calculate the MIRR for each project. Round your answers to two decimal places.

    Truck:  %

    What is the correct accept/reject decision for this project?
    -Select-AcceptRejectItem 10


    Pulley:  %

    What is the correct accept/reject decision for this project?
    -Select-AcceptRejectItem 12

Solutions

Expert Solution

a.

Computations of IRR using excel:

A

B

C

1

Year

Cash Flow(Truck)

Cash Flow (Pulley)

2

0

($15,000)

($21,000)

3

1

$5,100

$7,500

4

2

$5,100

$7,500

5

3

$5,100

$7,500

6

4

$5,100

$7,500

7

5

$5,100

$7,500

8

IRR

20.76%

23.06%

Suppose the excel sheet looks like above table.

Insert formula in cell B8 as “=IRR(B2:B7) to get IRR for the project Truck as 20.76 %

Similarly to get IRR of Pulley inset formula “=IRR(C2:C7) in cell C8, which will display IRR as 23.06 %

IRR for Truck is 20.76 %

The Project should be accepted as IRR is higher than firm’s cost of capital 9 %.

b.

IRR for Pulley is 23.06 %

The Project should be accepted as IRR is higher than firm’s cost of capital 9 %.

c.

Computation of NPV:

Year

Computation

of PV Factor

PV Factor @ 9 % (F)

Cash Flow (Truck)

CT

Cash Flow (Pulley)

CP

PV (Truck)

(=F x CT)

PV (Pulley)

(=F x CP)

0

1/(1+0.09)^0

1

($15,000)

($21,000)

($15,000.000000)

($21,000.000000)

1

1/(1+0.09)^1

0.91743119266

$5,100

$7,500

$4,678.899083

$6,880.733945

2

1/(1+0.09)^2

0.84167999327

$5,100

$7,500

$4,292.567966

$6,312.599949

3

1/(1+0.09)^3

0.77218348006

$5,100

$7,500

$3,938.135748

$5,791.376100

4

1/(1+0.09)^4

0.70842521107

$5,100

$7,500

$3,612.968576

$5,313.189083

5

1/(1+0.09)^5

0.64993138630

$5,100

$7,500

$3,314.650070

$4,874.485397

NPV

$4,837.221443

$8,172.384475

NPV for Truck is $ 4,837

The Project should be accepted as NPV is positive.

d.

NPV for Pulley is $ 8,172

The Project should be accepted as NPV is positive.

e.

MIRR = n √ Terminal Value of Cash Inflow/Present Value of Cash Outflow – 1

n = No. of years of investment = 5

Year

Cash Flow

(Truck)

CT

Cash Flow (Pulley)

CP

Computation of Future Value Factor

Future Value factor @ 9 % (F)

Future value Truck

(F x CT)

Future value Pulley

(F x CP)

1

$5,100

$7,500

(1.09)^4

1.41158161

$7,199.066211

$10,586.862075

2

$5,100

$7,500

(1.09)^3

1.295029

$6,604.647900

$9,712.717500

3

$5,100

$7,500

(1.09)^2

1.1881

$6,059.310000

$8,910.750000

4

$5,100

$7,500

(1.09)^1

1.09

$5,559.000000

$8,175.000000

5

$5,100

$7,500

(1.09)^0

1

$5,100.000000

$7,500.000000

Terminal value

$30,522.024111

$44,885.329575

MIRR for Truck = 5 √ $30,522.024111 /$ 15,000 – 1

                           = [5 √ (2.03480160740)] – 1

                           = 1.152668471964 – 1

                      = 0.152668471964 or 15.27 %

Project Truck should be accepted as cost of capital is lower than MIRR.

MIRR for Pulley = 5 √ $44,885.329575 /$ 21,000 – 1

                           = [5 √ (2.13739664643)] – 1

                           = 1.164064445844 – 1

                          = 0.164064445844 or 16.41 %

Project Pulley should be accepted as cost of capital is lower than MIRR.


Related Solutions

NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000 and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000 and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000, and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $17,100, and that for the pulley system is $22,430. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $17,100 and that for the pulley system is $22,430. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000 and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
Problem 10-08 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces...
Problem 10-08 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000 and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500...
Problem 10-8 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces...
Problem 10-8 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000, and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500...
Problem 10-08 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces...
Problem 10-08 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $19,000 and that for the pulley system is $20,000. The firm's cost of capital is 12%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 $5,100   $7,500 3 $5,100 $7,500 4 $5,100   $7,500...
Edelman Engineering is considering including two pieces of equipment, a truck and an     overhead pulley...
Edelman Engineering is considering including two pieces of equipment, a truck and an     overhead pulley system in this year’s capital budget. The projects are independent. The   cash outlay for the truck is $17,100 and for the pulley system it is $22,430. The firm’s cost of capital is 14%. After tax cash flows are as follows:                                     Year                            Truck                           Pulley                                     1                                  $5,100                         $7,500                                     2                                  $5,100                         $7,500                                                                         3                                  $5,100                         $7,500                                                                         4                                  $5,100                         $7,500                                     5                                 ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT