Question

In: Finance

NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...

NPVs, IRRs, and MIRRs for Independent Projects

Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000 and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows:

Year Truck Pulley
1 $5,100 $7,500
2 5,100 7,500
3 5,100 7,500
4 5,100 7,500
5 5,100 7,500
  1. Calculate the IRR for each project. Round your answers to two decimal places.

    Truck: %

    What is the correct accept/reject decision for this project?
    -Select-AcceptReject


    Pulley: %

    What is the correct accept/reject decision for this project?
    -Select-AcceptReject


  2. Calculate the NPV for each project. Round your answers to the nearest dollar, if necessary. Enter each answer as a whole number. For example, do not enter 1,000,000 as 1 million.

    Truck: $

    What is the correct accept/reject decision for this project?
    -Select-AcceptReject


    Pulley: $

    What is the correct accept/reject decision for this project?
    -Select-AcceptReject


  3. Calculate the MIRR for each project. Round your answers to two decimal places.

    Truck: %

    What is the correct accept/reject decision for this project?
    -Select-AcceptReject


    Pulley: %

    What is the correct accept/reject decision for this project?
    -Select-AcceptReject

Solutions

Expert Solution

Answer to Part b.
Calculation of NPV:

Project Truck:

NPV = -$18,000 + $5,100/1.14^1 + $5,100/1.14^2 + $5,100/1.14^3 + $5,100/1.14^4 + $5,100/1.14^5
NPV = -$491.29

Reject the project, as it has negative NPV.

Project Pulley:

NPV = -$22,000 + $7,500/1.14^1 + $7,500/1.14^2 + $7,500/1.14^3 + $7,500/1.14^4 + $7,500/1.14^5
NPV = $3,748.11

Accept the project, as it has positive NPV.


Related Solutions

NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000 and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000, and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $17,100, and that for the pulley system is $22,430. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000 and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $17,100 and that for the pulley system is $22,430. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000 and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
Problem 10-08 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces...
Problem 10-08 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000 and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500...
Problem 10-8 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces...
Problem 10-8 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000, and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500...
Problem 10-08 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces...
Problem 10-08 NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $19,000 and that for the pulley system is $20,000. The firm's cost of capital is 12%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 $5,100   $7,500 3 $5,100 $7,500 4 $5,100   $7,500...
Edelman Engineering is considering including two pieces of equipment, a truck and an     overhead pulley...
Edelman Engineering is considering including two pieces of equipment, a truck and an     overhead pulley system in this year’s capital budget. The projects are independent. The   cash outlay for the truck is $17,100 and for the pulley system it is $22,430. The firm’s cost of capital is 14%. After tax cash flows are as follows:                                     Year                            Truck                           Pulley                                     1                                  $5,100                         $7,500                                     2                                  $5,100                         $7,500                                                                         3                                  $5,100                         $7,500                                                                         4                                  $5,100                         $7,500                                     5                                 ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT