Question

In: Accounting

At the end of April, Cavy Company had completed Job 766 and 765. According to the individual job cost sheets the information is as follows:

At the end of April, Cavy Company had completed Job 766 and 765. According to the individual job cost sheets the information is as follows:

Job

Direct Materials

Direct Labor

Machine Hours

    

Job 765

$5,670

$3,500

27

Job 766

$8,900

$4,775

44

    

Job 765 produced 152 units, and Job 766 consisted of 250 units.

Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour, determine the (a) balance on the job cost sheets for each job, and (b) the cost per unit at the end of April.

Solutions

Expert Solution

a) Balance of Job cost sheet

Job 765 Job 766
Direct material 5670 8900
Direct labor 3500 4775
Overhead 27*200 = 5400 44*200 = 8800
Total Job cost 14570 22475

b) Cost per unit

Job 765 = 14570/152 = 95.86

Job 766 = 22475/250 = 89.90


Related Solutions

At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job...
At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job cost sheets reveal the following information: JobDirect MaterialsDirect LaborMachine Hours Job 765$10,920              $3,276        39 Job 76614,706              4,644        86 Job 765 produced 234 units, and Job 766 consisted of 344 units. Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $135 per hour. a. Determine the balance on the job cost sheets for each job. Job 765$ Job 766$ b. Determine the...
At the end of April, Cavy Company had completed Job 766 and 765. Job 766 is...
At the end of April, Cavy Company had completed Job 766 and 765. Job 766 is for 675 units, and Job 765 is for 900 units. According to the individual job cost sheets the information is as follows: Job Direct Materials Direct Labor Machine Hours Job 765 $5,670 $3,500 27Job 766  $8,900  $4,775  44Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour, determine the (a) balance on the job cost sheets for each job,...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 400 units for Job 40 at $12 per unit and 900 units for Job 42 at $18 per unit. During August, Prichard Company accumulated 200 hours of direct labor costs on Job 40...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 500 units for Job 40 at $18 per unit and 900 units for Job 42 at $14 per unit. During August, Prichard Company accumulated 500 hours of direct labor costs on Job 40...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 2,000 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 700 units for Job 40 at $16 per unit and 900 units for Job 42 at $16 per unit. During August, Kaye Company accumulated 200 hours of direct labor costs on Job 40...
Job Costs At the end of May, Bergan Company had completed Jobs 200 and 305. Job...
Job Costs At the end of May, Bergan Company had completed Jobs 200 and 305. Job 200 is for 2,390 units, and Job 305 is for 2,053 units. The following data relate to these two jobs: On May 7, Bergan Company purchased on account 10,000 units of raw materials at $8 per unit. During May, raw materials were requisitioned for production as follows: 7,500 units for Job 200 at $8 per unit and 1,480 units for Job 305 at $5...
Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 800 units for Job 40 at $10 per unit and 1,500 units for Job 42 at $20 per unit. During August, Ingram Company accumulated 800 hours of direct labor costs on Job 40...
5.0 Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42....
5.0 Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 200 units for Job 40 at $20 per unit and 1,200 units for Job 42 at $24 per unit. During August, Ingram Company accumulated 200 hours of direct labor costs on Job...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 44,000 $ 54,000 $ 49,000 Direct labor 16,000 29,100 44,000 Overhead applied 5,440 9,894 14,960 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $10,000; direct labor, $3,300; and overhead, $1,122. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 41,000 $ 51,000 $ 65,000 Direct labor 12,000 29,700 39,000 Overhead applied 5,400 13,365 17,550 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $13,000; direct labor, $3,500; and overhead, $1,575. Jobs 103 and 104 were...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT