Question

In: Accounting

At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job...

At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job cost sheets reveal the following information:

JobDirect MaterialsDirect LaborMachine Hours

Job 765$10,920              $3,276        39

Job 76614,706              4,644        86

Job 765 produced 234 units, and Job 766 consisted of 344 units.

Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $135 per hour.

a. Determine the balance on the job cost sheets for each job.

Job 765$

Job 766$

b. Determine the cost per unit at the end of April. Round your answers to the nearest cent.

Job 765$

Job 766$

Solutions

Expert Solution

a.
Balance on the job cost sheets for each job.

Job 765$ = $19,461

Job 766$ = $30,960

b.
Cost per unit at the end of April.

Job 765$ = $83.17

Job 766$ = $90.00


Step by step explanation:

It is given that,
Manufacturing overhead rate is applied by using machine hours at a rate of $135 per hour

Machine hours:

Job 765 = 39 hours
Job 766 = 86 hours

Hence,

Manufacturing overhead applied:

Job 765 = 39 × $135 = $5,265
Job 766 = 86 × $135 = $12,610

Cost per unit:

Cost per unit = Total job cost / Number of units produced

Total job cost:

Job 765 = $19,461
Job 766 = $30,960

Number of units produced
Job 765 = 234 units
Job 766 = 344 units

Cost per unit:

Job 765 = $19,461/234 = $83.17
Job 766 = $30,960/344 = $90.00


Related Solutions

At the end of April, Cavy Company had completed Job 766 and 765. Job 766 is...
At the end of April, Cavy Company had completed Job 766 and 765. Job 766 is for 675 units, and Job 765 is for 900 units. According to the individual job cost sheets the information is as follows: Job Direct Materials Direct Labor Machine Hours Job 765 $5,670 $3,500 27Job 766  $8,900  $4,775  44Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour, determine the (a) balance on the job cost sheets for each job,...
At the end of April, Cavy Company had completed Job 766 and 765. According to the individual job cost sheets the information is as follows:
At the end of April, Cavy Company had completed Job 766 and 765. According to the individual job cost sheets the information is as follows:JobDirect MaterialsDirect LaborMachine Hours    Job 765$5,670$3,50027Job 766$8,900$4,77544    Job 765 produced 152 units, and Job 766 consisted of 250 units.Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour, determine the (a) balance on the job cost sheets for each job, and (b) the cost per unit at the end...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 400 units for Job 40 at $12 per unit and 900 units for Job 42 at $18 per unit. During August, Prichard Company accumulated 200 hours of direct labor costs on Job 40...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 500 units for Job 40 at $18 per unit and 900 units for Job 42 at $14 per unit. During August, Prichard Company accumulated 500 hours of direct labor costs on Job 40...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 2,000 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 700 units for Job 40 at $16 per unit and 900 units for Job 42 at $16 per unit. During August, Kaye Company accumulated 200 hours of direct labor costs on Job 40...
Job Costs At the end of May, Bergan Company had completed Jobs 200 and 305. Job...
Job Costs At the end of May, Bergan Company had completed Jobs 200 and 305. Job 200 is for 2,390 units, and Job 305 is for 2,053 units. The following data relate to these two jobs: On May 7, Bergan Company purchased on account 10,000 units of raw materials at $8 per unit. During May, raw materials were requisitioned for production as follows: 7,500 units for Job 200 at $8 per unit and 1,480 units for Job 305 at $5...
5.0 Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42....
5.0 Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 200 units for Job 40 at $20 per unit and 1,200 units for Job 42 at $24 per unit. During August, Ingram Company accumulated 200 hours of direct labor costs on Job...
Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost On April 1, Sangvikar Company had...
Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost On April 1, Sangvikar Company had the following balances in its inventory accounts: Materials Inventory $12,590 Work-in-Process Inventory 21,170 Finished Goods Inventory 8,750 Work-in-process inventory is made up of three jobs with the following costs: Job 114 Job 115 Job 116 Direct materials $2,386 $2,655 $3,175 Direct labor 1,740 1,660 4,220 Applied overhead 1,218 1,162 2,954 During April, Sangvikar experienced the transactions listed below. Materials purchased on account, $28,590. Materials...
Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost On April 1, Sangvikar Company had...
Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost On April 1, Sangvikar Company had the following balances in its inventory accounts: Materials Inventory $12,790 Work-in-Process Inventory 21,150 Finished Goods Inventory 8,840 Work-in-process inventory is made up of three jobs with the following costs: Job 114 Job 115 Job 116 Direct materials $2,390   $2,698 $3,870 Direct labor 1,740 1,540 4,340 Applied overhead 1,044 924 2,604 During April, Sangvikar experienced the transactions listed below. a. Materials purchased on account, $28,850....
Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost On April 1, Sangvikar Company had...
Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost On April 1, Sangvikar Company had the following balances in its inventory accounts: Materials Inventory $12,840 Work-in-Process Inventory 21,700 Finished Goods Inventory 8,720 Work-in-process inventory is made up of three jobs with the following costs: Job 114 Job 115 Job 116 Direct materials $2,438 $2,621 $4,035 Direct labor 1,900 1,480 4,260 Applied overhead 1,235 962 2,769 During April, Sangvikar experienced the transactions listed below. Materials purchased on account, $29,320. Materials...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT