At the end of April, Cavy Company had completed Job 766 and 765. Job 766 is for 675 units, and Job 765 is for 900 units. Acco

At the end of April, Cavy Company had completed Job 766 and 765. Job 766 is for 675 units, and Job 765 is for 900 units. According to the individual job cost sheets the information is as follows: 

Job Direct Materials Direct Labor Machine Hours 

Job 765 $5,670 $3,500 27

Job 766  $8,900  $4,775  44

Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour, determine the (a) balance on the job cost sheets for each job, and (b) the cost per unit at the end of April.

Solutions

Expert Solution

a) Job 765 Job 766
Direct Materials $    5,670.00 $    8,900.00
Direct Labor $    3,500.00 $    4,775.00
Applied Overheads (27*200 / 44*200) $    5,400.00 $    8,800.00
total $ 14,570.00 $ 22,475.00
Divided by units 900 675
cost per unit (b) $          16.19 $          33.30

Related Solutions

At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job...
At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job cost sheets reveal the following information: JobDirect MaterialsDirect LaborMachine Hours Job 765$10,920              $3,276        39 Job 76614,706              4,644        86 Job 765 produced 234 units, and Job 766 consisted of 344 units. Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $135 per hour. a. Determine the balance on the job cost sheets for each job. Job 765$ Job 766$ b. Determine the...
At the end of April, Cavy Company had completed Job 766 and 765. According to the individual job cost sheets the information is as follows:
At the end of April, Cavy Company had completed Job 766 and 765. According to the individual job cost sheets the information is as follows:JobDirect MaterialsDirect LaborMachine Hours    Job 765$5,670$3,50027Job 766$8,900$4,77544    Job 765 produced 152 units, and Job 766 consisted of 250 units.Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour, determine the (a) balance on the job cost sheets for each job, and (b) the cost per unit at the end...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 400 units for Job 40 at $12 per unit and 900 units for Job 42 at $18 per unit. During August, Prichard Company accumulated 200 hours of direct labor costs on Job 40...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 500 units for Job 40 at $18 per unit and 900 units for Job 42 at $14 per unit. During August, Prichard Company accumulated 500 hours of direct labor costs on Job 40...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 2,000 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 700 units for Job 40 at $16 per unit and 900 units for Job 42 at $16 per unit. During August, Kaye Company accumulated 200 hours of direct labor costs on Job 40...
Job Costs At the end of May, Bergan Company had completed Jobs 200 and 305. Job...
Job Costs At the end of May, Bergan Company had completed Jobs 200 and 305. Job 200 is for 2,390 units, and Job 305 is for 2,053 units. The following data relate to these two jobs: On May 7, Bergan Company purchased on account 10,000 units of raw materials at $8 per unit. During May, raw materials were requisitioned for production as follows: 7,500 units for Job 200 at $8 per unit and 1,480 units for Job 305 at $5...
5.0 Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42....
5.0 Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 200 units for Job 40 at $20 per unit and 1,200 units for Job 42 at $24 per unit. During August, Ingram Company accumulated 200 hours of direct labor costs on Job...
1. The Cavy Company accumulated 600 hours of direct labor on Job 567 and 740 hours...
1. The Cavy Company accumulated 600 hours of direct labor on Job 567 and 740 hours on Job 999. The direct labor was incurred at a rate of $16 per direct labor hour for Job 567 and $26 per direct labor for Job 999. Journalize the entry to record the flow of labor costs into production. (cash, factory overhead, wage expense, wage payable, work in process) __________ (cash, factory overhead, wage expense, accounts payable, work in process) __________ 2. FastFlow...
Job Cost Flows, Journal Entries On April 1, Sangvikar Company had the following balances in its...
Job Cost Flows, Journal Entries On April 1, Sangvikar Company had the following balances in its inventory accounts: Materials Inventory $12,760 Work-in-Process Inventory 21,350 Finished Goods Inventory 8,600 Work-in-process inventory is made up of three jobs with the following costs: Job 114 Job 115 Job 116 Direct materials $2,804 $2,640 $3,650 Direct labor 1,800 1,560 4,300 Applied overhead 1,080 936 2,580 During April, Sangvikar experienced the transactions listed below. Materials purchased on account, $30,000. Materials requisitioned: Job 114, $16,500; Job...
Job Cost Flows, Journal Entries On April 1, Sangvikar Company had the following balances in its...
Job Cost Flows, Journal Entries On April 1, Sangvikar Company had the following balances in its inventory accounts: Materials Inventory $12,760 Work-in-Process Inventory 21,320 Finished Goods Inventory 8,700 Work-in-process inventory is made up of three jobs with the following costs: Job 114 Job 115 Job 116 Direct materials $2,774 $2,640 $3,650 Direct labor 1,800 1,560 4,300 Applied overhead 1,080 936 2,580 During April, Sangvikar experienced the transactions listed below. Materials purchased on account, $28,000. Materials requisitioned: Job 114, $16,500; Job...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT