Question

In: Civil Engineering

4a. A water authority has decided to procure a new water treatment station by design and...

4a. A water authority has decided to procure a new water treatment station by design and build. Identify and discuss the information you would advise the Client to provide for inclusion in the Contract Data

4b. What information should tenderers provide for inclusion in the Contract Data?

Solutions

Expert Solution

The development and implementation of water treatment technologies have been mostly driven by three primary factors: the discovery of new rarer contaminants, the promulgation of new water quality standards, and cost. For the first 75 years of this century, chemical clarification, granular media filtration, and chlorination were virtually the only treatment processes used in municipal water treatment. However, the past 20 years have seen a dramatic change in the water industry's approach to water treatment in which water utilities have started to seriously consider alternative treatment technologies to the traditional filtration/chlorination treatment approach. This paper identifies and discusses some of these "emerging" technologies.

Technology Development and Implementation Process

For a new technology to be considered it must have advantages over traditional treatment processes. These can include lower capital and operations and maintenance costs, higher efficiency, easier operation, better effluent water quality, and lower waste production. Nevertheless, for a water treatment technology to be accepted and implemented at large municipal scale, it must be demonstrated in stages. Understanding this process is necessary in order to properly plan and introduce a new technology to municipal water treatment. A typical sequence of these stages might be summarized as follows:

Stage 1: Successful demonstration in another field.

Stage 2: Testing and development at bench- and pilot-scale levels (1 to 50 gpm).

Stage 3: Verification at demonstration-scale level (>100 gpm).

Stage 4: Multiple successful installations and operations at small full-scale level (0.5 to 5 MGD).

Stage 5: Implementation at a large-scale municipal water treatment plant.

Two important milestones must be achieved in parallel with the above stages: obtaining regulatory approval and reducing costs to competitive levels. Commonly, regulatory approval is necessary by the end of the demonstration-

Page 221

Suggested Citation:"11 New and Emerging Drinking Water Treatment Technologies." National Research Council. 1999. Identifying Future Drinking Water Contaminants. Washington, DC: The National Academies Press. doi: 10.17226/9595.

×

scale Verification stage (stage 3) and prior to installation at small full-scale plants (stage 4). However, for a new technology to reach full acceptance (stage 5), its cost must be competitive with that of other more conventional processes that achieve the same objective.

The time duration for each of the above stages can vary greatly depending on the technology being considered, how urgent it is to have it implemented, how long it takes for its cost to reach competitive levels, and the significance of its role in the overall water treatment train. The last factor is different from the others in that it recognizes the difference between a technology that is proposed as an alternative to filtration, for example, which is an essential component of water treatment, versus a technology that is proposed to replace a less important component such as a pump, automation, chemical feed, taste-and-odor control, or preoxidation.


Related Solutions

A municipal water authority is considering the installation of a new water system. Two options are...
A municipal water authority is considering the installation of a new water system. Two options are being considered. The first option is a steel pipeline with an installation cost of $225 million. Annual maintenance and pumping costs begin at $15 million and increase by $1.0 million per year. The second option is a gravity fed concrete canal with an installation cost of $400 million. Annual maintenance costs begin at $0.5 million and increase by $0.4 million per year. The water...
Fun City has decided to build a new municipal water park with pools, water slides, and...
Fun City has decided to build a new municipal water park with pools, water slides, and so forth. You have been hired to conduct a study to determine if the water park can pass the test. A nearby and very similar city currently has a water park similar to the one Fun City is considering. The nearby city currently charges $10 for admission and, on a typical day, attracts 4,000 persons. Last year, it charged $15, but only attracted 3,000...
Most traditional water treatment plants units and design limitation
Most traditional water treatment plants units and design limitation
A new water treatment plant proposed for Anytown, has an initial cost of P56 million. The...
A new water treatment plant proposed for Anytown, has an initial cost of P56 million. The new plant will service the 7,500 residential customers for the next 30 years. It is expected to save each customer P125 per year. The plant will require a major overhaul every 5 years, costing P1million. Determine the benefit/cost ratio at the city’s interest rate of 6%. Use PW and EUAC.
A certain municipality is planning to construct a new water treatment plant. The average water requirement...
A certain municipality is planning to construct a new water treatment plant. The average water requirement is equivalent to 123456 m3 /d). The peak flow rate is twice the average flow rate. A jar test experiment revealed the following results: Alum dose: 15 mg/L Temperature: 20 o C Coagulation: G = 850 s-1 , t = 40 s Flocculation: GT =123456 . Settling: t = 1.5 h. a) Determine the size of the coagulation tank (L=2W, W=D) and flocculation tank...
Design rapid sand filters for a water treatment plant to treat a flow rate of 25...
Design rapid sand filters for a water treatment plant to treat a flow rate of 25 mgd. Use 1.5 for a peak factor. Consider the location of overflow troughs, freeboard, and pressure head of water. Assume that the length of the filters is 2 times the width and that the filtration rate is 3 gpm/ft2. Assume anthracite over sand with 1 ft gravel under media, top of water level during filtration is below troughs, and a 3 ft head drop...
The city of Bloomington is about to build a new water treatment plant. Once the plant...
The city of Bloomington is about to build a new water treatment plant. Once the plant is designed (D) we can select the site (S), the building contractor (C and the operating personnel (P). Once the site is selected we may erect the building (B). We can order the water treatment machine (W) and prepare the operations manual (M) only after the contractor is selected. We can begin training the operators (T) when both the operations manual and operating personnel...
The accounting firm of Johnson and Johnson has decided to design a nonstatistical sample to examine...
The accounting firm of Johnson and Johnson has decided to design a nonstatistical sample to examine the accounts receivable balance of Francisco Fragrances, Inc., at October 31. As of October 31, there were 1,500 accounts receivable accounts with a balance of $5.5 million. The accounts receivable population can be segregated into the following strata: Number and Size of Accounts Book Value of Stratum 10 accounts > $ 50,000 $ 750,000 440 accounts > $ 5,000 3,000,000 1,050 accounts < $...
Suppose that a city has to justify the net benefits of a proposed water treatment plant....
Suppose that a city has to justify the net benefits of a proposed water treatment plant. (A) Name and discuss the importance of the four things that the City must consider in terms of estimating the Present Value of Net Benefits (PVNB). (B) Calculate the PVNB’s from the following information: Year​ 0 ​1​ 2​ 3​ 4​ 5​ 6​ Cost​ 100 ​ 50​ 30​ 20​ 20​ 10​ 10​​ Benefit​ 10​ 20 ​20​ 40​ 100​ 120​ 150​ (i) PVNB (@ 4%) =...
Your company has a $1,000,000. loan for a new assembly station. The interest rate for this...
Your company has a $1,000,000. loan for a new assembly station. The interest rate for this loan is 7% compounded annually. Your company will make $100,000 payment at the end of each year, starting the end of the first year. By calculation, your company will make 18 annual payments. Payments for Year-1 through Year-17 are the same at $100,000. Payment for the last Year-18 will be less than $100,000. To payback this loan of 1M based on this payment plan,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT