In: Math
The city of Bloomington is about to build a new water treatment plant. Once the plant is designed (D) we can select the site (S), the building contractor (C and the operating personnel (P). Once the site is selected we may erect the building (B). We can order the water treatment machine (W) and prepare the operations manual (M) only after the contractor is selected. We can begin training the operators (T) when both the operations manual and operating personnel selected are completed. When the water treatment and building are finished, we can install the treatment machine (I). Once the treatment machine is installed and the operators are trained, we can obtain an operating license (L). The time to complete each activity is assumed to be a normal distribution and the estimated mean and standard deviation of the time (in months) needed to complete each activity is defined below:
ACTIVITY |
DESCRIPTION |
MEAN |
STANDARD DEVIATION |
D |
Design plant |
6 |
1.5 |
S |
Select site |
2 |
0.3 |
C |
Select Building Contractor |
4 |
1.0 |
P |
Select Operating Personnel |
3 |
1.0 |
B |
Erect Building |
24 |
0.6 |
W |
Order Water Treatment machinery |
14 |
4.0 |
M |
Prepare Operations Manual |
3 |
0.4 |
T |
Train Operators |
4 |
1.0 |
I |
Install Treatment Machine |
6 |
1.0 |
L |
Obtain Operator License |
3 |
6.0 |
We will use the provided information to decide the predecessor for our PERT network construction. We will define the mean expected time for the activities to calculate the critical path. After that, we will find all the paths to complete the project. Finally, we will calculate the required probabilities from the critical path obtained.