Question

In: Math

The city of Bloomington is about to build a new water treatment plant. Once the plant...

The city of Bloomington is about to build a new water treatment plant. Once the plant is designed (D) we can select the site (S), the building contractor (C and the operating personnel (P). Once the site is selected we may erect the building (B). We can order the water treatment machine (W) and prepare the operations manual (M) only after the contractor is selected. We can begin training the operators (T) when both the operations manual and operating personnel selected are completed.  When the water treatment and building are finished, we can install the treatment machine (I). Once the treatment machine is installed and the operators are trained, we can obtain an operating license (L). The time to complete each activity is assumed to be a normal distribution and the estimated mean and standard deviation of the time (in months) needed to complete each activity is defined below:

ACTIVITY

DESCRIPTION

MEAN

STANDARD DEVIATION

D

Design plant

6

1.5

S

Select site

2

0.3

C

Select Building Contractor

4

1.0

P

Select Operating Personnel

3

1.0

B

Erect Building

24

0.6

W

Order Water Treatment machinery

14

4.0

M

Prepare Operations Manual

3

0.4

T

Train Operators

4

1.0

I

Install Treatment Machine

6

1.0

L

Obtain Operator License

3

6.0

  1. Draw the PERT network for the project
  2. Calculate the critical path and estimated completion time of the project
  3. Using this estimated completion time, determine the probability of completing the project in (1) under 50 months and (2) over 55 months
  4. Use simulation to calculate the estimated completion time and to determine the probability of completing the project in (1) under 50 months and (2) over 55 months (use a monte carlo simulation of 200 repetitions)
  5. Explain why the answers to questions (b) and (c ) may differ to that determined in question (d).
  6. Use simulation to estimate the probability that B, I and T are critical activities

Solutions

Expert Solution

We will use the provided information to decide the predecessor for our PERT network construction. We will define the mean expected time for the activities to calculate the critical path. After that, we will find all the paths to complete the project. Finally, we will calculate the required probabilities from the critical path obtained.


Related Solutions

The Iowa City Water Treatment Plant and the University of Iowa Water Treatment Plant remove calcium...
The Iowa City Water Treatment Plant and the University of Iowa Water Treatment Plant remove calcium hardness (Ca2+) by precipitating (making) CaCO3(s). If, after establishing equilibrium with CaCO3(s), the dissolved Ca2+ concentration is 10 mg/L and the pH is 10.5. a. What is the CO32- concentration in mol/L? b. What is the HCO3- concentration in mol/L? c. What is the alkalinity in mg/L as CaCO3?
Q4. You are working in a waste water treatment plant, once your treatment plant receives sewage...
Q4. You are working in a waste water treatment plant, once your treatment plant receives sewage water with more colloidal or dissolved organic materials. As an Engineer what type of treatment will you prefer for this sewage water? Justify and explain the method selected by you.
Suppose that a city has to justify the net benefits of a proposed water treatment plant....
Suppose that a city has to justify the net benefits of a proposed water treatment plant. (A) Name and discuss the importance of the four things that the City must consider in terms of estimating the Present Value of Net Benefits (PVNB). (B) Calculate the PVNB’s from the following information: Year​ 0 ​1​ 2​ 3​ 4​ 5​ 6​ Cost​ 100 ​ 50​ 30​ 20​ 20​ 10​ 10​​ Benefit​ 10​ 20 ​20​ 40​ 100​ 120​ 150​ (i) PVNB (@ 4%) =...
The Water Treatment Plant and the University Water Treatment Plant remove calcium hardness (Ca2+) by precipitating...
The Water Treatment Plant and the University Water Treatment Plant remove calcium hardness (Ca2+) by precipitating (making) CaCO3(s). If, after establishing equilibrium with CaCO3(s), the dissolved Ca2+ concentration is 10 mg/L and the pH is 10.5. a. What is the CO32- concentration in mol/L? b. What is the HCO3- concentration in mol/L? c. What is the alkalinity in mg/L as CaCO3?
A certain municipality is planning to construct a new water treatment plant. The average water requirement...
A certain municipality is planning to construct a new water treatment plant. The average water requirement is equivalent to 123456 m3 /d). The peak flow rate is twice the average flow rate. A jar test experiment revealed the following results: Alum dose: 15 mg/L Temperature: 20 o C Coagulation: G = 850 s-1 , t = 40 s Flocculation: GT =123456 . Settling: t = 1.5 h. a) Determine the size of the coagulation tank (L=2W, W=D) and flocculation tank...
Fun City has decided to build a new municipal water park with pools, water slides, and...
Fun City has decided to build a new municipal water park with pools, water slides, and so forth. You have been hired to conduct a study to determine if the water park can pass the test. A nearby and very similar city currently has a water park similar to the one Fun City is considering. The nearby city currently charges $10 for admission and, on a typical day, attracts 4,000 persons. Last year, it charged $15, but only attracted 3,000...
Wollongong City is considering the construction of a new waste treatment plant. Land acquisition will cost...
Wollongong City is considering the construction of a new waste treatment plant. Land acquisition will cost $120,000. The construction works required for the plant will cost $600,000. Environmental inspection and other expenses will cost $60,000. The plant will be built in Year 0 and will become fully operational in Year 1 for six years (i.e. until Year 6). The annual operating cost for the plant is estimated to be fixed at $120,000 during its anticipated 6-year service life. This waste...
A new water treatment plant proposed for Anytown, has an initial cost of P56 million. The...
A new water treatment plant proposed for Anytown, has an initial cost of P56 million. The new plant will service the 7,500 residential customers for the next 30 years. It is expected to save each customer P125 per year. The plant will require a major overhaul every 5 years, costing P1million. Determine the benefit/cost ratio at the city’s interest rate of 6%. Use PW and EUAC.
The City of Pawnee, IN (not a real city) is planning to build a new hospital...
The City of Pawnee, IN (not a real city) is planning to build a new hospital next year that has a property value of $100 million. The Pawnee government plans to keep the property tax rate the same every year and to provide the same government services as they did last year. That is, the total budgeted expenditures and income from other sources will remain unchanged. Note: This question does not require any numerical calculations. Will the average amount of...
A manufacturer plans to open a new plant. The new plant will cost $4,000,000 to build...
A manufacturer plans to open a new plant. The new plant will cost $4,000,000 to build and make ready for production. Company management believes that the plant will produce a net profit of $130,000 in the first year and that profit will increase 5% per year until year 7 at which point profit will remain constant for the remainder of the plant’s useful life. Determine the payback period for the plant. Do not consider the effect of interest. Express your...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT