Question

In: Operations Management

You are the project manager of a software development company. Your company receives supplies of chips...

You are the project manager of a software development company. Your company receives supplies of chips from a foreign supplier. Their sales manager has approached you to inform you that if you can increase your order by 30%, the shipment will be free for your organization. This however will bring additional cost of $100 on your current budget that is $5000 p.a. What type of Risk is this? Identify at least three things you can do in response given consideration to best practices?

Solutions

Expert Solution

Solution:

Risk is defined as a possibility of something adverse happening. It has an element of uncertainty that may result in an undesirable outcome. For example, a factory getting damaged by fire, political uncertainties leading to business closure, COVID-19 type pandemic, etc.

In the context of the given case, it is given that with a 30% additional order (which means at 130%), the order value would be $5100 which causes a budget variance of $100. This is an example of Budget Risk where a project's budget and/or estimate gets adversely impacted due to factors within or beyond control.

Strategies to mitigate the stated Budget Risk:

  1. Perform a Return On Investment (ROI) analysis to see if the additional order quantity is required and if it will result in higher benefits - If no, then the order quantity does not need to be increased;
  2. If the decision makes business sense, one should try to maintain the current budget by asking the supplier to give a discount worth $100;
  3. Alternately, one should try to maintain the current budget by asking the supplier to give the free shipment for a slightly smaller order size (say 125%).

Related Solutions

3.You are the project manager of a software development company. Your company receives supplies of chips...
3.You are the project manager of a software development company. Your company receives supplies of chips from a foreign supplier. Their sales manager has approached you to inform you that if you can increase your order by 30%, the shipment will be free for your organization. This however will bring additional cost of $100 on your current budget that is $5000 p.a. What type of Risk is this? Identify at least three things you can do in response given consideration...
You are the Project Manager for a major software development project.
a.You are the Project Manager for a major software development project. You are concerned that one of the project constraints is going unbalanced, but the project sponsor is unable to understand your concern since he is not familiar with the concept of project constraints. How would you explain this concept and its significance in project success, to the project sponsor? You can use the Iron Triangle to illustrate the concept.b. Saudi Railways has announced a project to add a new...
You are the project manager for a software development project for an updated management system. The...
You are the project manager for a software development project for an updated management system. The cost of doing it in-house is $27,000. You estimate you'll spend $2,000 per month updating the software with client information, government regulations, and maintenance. You know that a contractor do the programming for your company and charge a fee based on the number of personnel using the program every month. This contractor will charge you $4 per month per user of the accounting system....
List your responsibilities as a Software Development Project Manager, and explain how you measure the success...
List your responsibilities as a Software Development Project Manager, and explain how you measure the success and failure in any project? Give examples.
Scenario You are the manager of a software development team working on new applications for your...
Scenario You are the manager of a software development team working on new applications for your company, Optimum Way Development, Inc. Your director has called for all development teams to submit product briefs detailing their current projects. The director plans to share the most promising product briefs with clients at an upcoming meeting. You have software design documents for two potential projects. Directions You must choose one of the potential products and use the information contained in the technical specification...
The board of directors of you company is considering a very roburst software development project that...
The board of directors of you company is considering a very roburst software development project that will enhance efficiency and effectiveness of its operations as well as improve the the productivity of its staff. as the System Analyst, you are nominated to be the project manager for this project. Identify a specific software development project of your choice. For your project, a. List the functional and non-functional requirements of the system. b. Identify the stakeholders from whom you will gather...
You are asked to check the feasibility of software development project. The initial development cost is...
You are asked to check the feasibility of software development project. The initial development cost is $10M and the project will require an annual maintenance by the team of engineers and product managers. The annual salary of the team member is $150K. In year 1, the project will require 5 team members and in years 2-4 it will require 10 team members. The subscription revenues start in year 2 and end in year 4 (3 years). The average client pays...
Situation: Your manager is leading a project to develop new software that is essential to the...
Situation: Your manager is leading a project to develop new software that is essential to the success of the midsized manufacturing firm where you work. The firm has decided to hire outside contractors to execute the project. One candidate firm boasts that its software development practices are at level 4 of CMMI. Another firm claims that all its software development practices are ISO 9001 compliant. Your manager has come to you and asked for your opinion on how much weight...
Mary and George both work for a software development company. The manager of the new product...
Mary and George both work for a software development company. The manager of the new product division was originally the leader of the project team for which she interviewed and hired George. Mary, another project team member, also interviewed George but strongly opposed hiring him for the project because she thought he was not competent to do the job. Seven months after George was hired, the manager left the project to start her own company and recommended that George and...
You are completing a software development project. This project is expected to add SIX new features...
You are completing a software development project. This project is expected to add SIX new features to a popular software program you sell to customers. The projected cost for the project is $100,000 and the development is expected to take 5 weeks. At the end of the second week, you spent $17,500 per new software feature and you completed the development of two new features. You are about to start the development of the third new software feature. Based on...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT