Question

In: Operations Management

3. The client of a project has requested the project team to crash 8 hours of...

3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing.

(a) What is the crash cost for 8 hours of time-savings?

(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?

Activity

Normal

Duration (hours)

Normal

Cost ($)

Crash

Duration (hours)

Crash

Cost (S)

Immediate

Predecessors

A

2

10

2

0

None

B

3

15

2

23

A

C

5

25

4

30

B

D

3

20

1

24

C

E

6

30

4

45

C

F

1

5

1

0

C,E

G

7

35

6

50

F

H

10

50

7

62

D,G

Evaluation

The Unit Exercises will be marked in its entirety out of 100. The following rubric indicates the criteria students are to adhere to, and their relative weights to the assignment overall.

Solutions

Expert Solution

PLEASE LIKE THIS ANSWER, IT HELPS ME A LOT. THANK YOU!!!

Solution:

Network Diagram:

Possible Paths:

Start-A-B-C-D-H-End = 23 hours

Start-A-B-C-E-F-G-H-End = 34 hours ......... Critical Path (longest duration path

Start-A-B-C-F-G-H-End = 28 hours

For reducing the project duration, the least incremental crash cost activities on Critical Path should be crashed.

Incremental Crash Cost = (Crash Cost - Normal Cost) / (Normal Duration - Crash Duration)

Activity Normal Time Crash Time Normal Cost Crash Cost Incremental Crash Cost
A 2 2 10 0 NA
B 3 2 15 23 8
C 5 4 25 30 5
D 3 1 20 24 2
E 6 4 30 45 7.5
F 1 1 5 0 NA
G 7 6 35 50 15
H 10 7 50 62 4

Crashing Schedule to reduce the project duration by 8 hours i.e 34 - 8 = 26 hours

Crashed Activity No Crashing H C E B G
No. of days Crashed 0 3 1 2 1 1
Crashing Cost 0 12 5 15 8 15
Total Crashing Cost 0 12 17 32 40 55
Critical Path A-B-C-E-F-G-H A-B-C-E-F-G-H A-B-C-E-F-G-H A-B-C-E-F-G-H A-B-C-E-F-G-H A-B-C-E-F-G-H
TPT 34 31 30 28 27 26

a) From the above table, crash cost for 8 hours of time-saving is $55

b) From the above table, 20$ budget is sufficient to crash 4 hours of time, as it will only require $17


Related Solutions

b.The lead engineer on the design team has requested that you match the reliability of the...
b.The lead engineer on the design team has requested that you match the reliability of the parallel system with a series system. All three of the valves in series will have the same probability of functioning correctly. What does this probability need to be to equal the probability of the parallel system? c. Comment on the advantages and disadvantages of using parallel systems in aircraft design. Based on the experimental data, it was determined that the probability of the three...
1. The nurse has taught a client who had a laparoscopic cholecystectomy 3 hours ago. Which...
1. The nurse has taught a client who had a laparoscopic cholecystectomy 3 hours ago. Which of the following statements by the client would indicate a correct understanding of the teaching? Select all that apply I will be able to return to work in 4 weeks. I will notify my primary health care provider if I experienced abdominal pain. I should ambulate frequently if I experience shoulder pain. I can resume my usual diet. I can take a shower in...
You are the supervising manager at an engineering firm. A client has requested your firm work...
You are the supervising manager at an engineering firm. A client has requested your firm work on a project that is handled frequently by your employees. The standard hours for projects of this nature is 36 hours for one engineer. You have decided to hand this incoming project to a brand new hire who just graduated with her engineering degree. What should your expectation be regarding the standard of 36 hours for this particular project? Why?
A major new client has requested your company to present an investment seminar to the municipal...
A major new client has requested your company to present an investment seminar to the municipal mayors of the represented Metros. As an investment specialist, you have been tasked to assist your company in preparing the presentation. To illustrate the common share valuation process, you have been asked to analyze Business Analytics, an employment agency that supplies word processor operators and computer programmers to businesses with temporarily heavy workloads. You are to answer the following: 2.1 Assume that Business Analytics...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost A - 4 $2000 4 - B A 4 $1500 2 4500 C A 6 5000 4 8000 D B 2 1000 2 - E B 6 8000 3 10000 F C 10 10000 7 14000 G D 7 3500 4 5000 H E 4 2500 2 5000 I G,H 3 2000 2 3500 J I,F 3 3000 1 4500 Consider the project shown...
Suppose you are a CPA, and your client has requested advice regarding establishing an irrevocable trust...
Suppose you are a CPA, and your client has requested advice regarding establishing an irrevocable trust for his two (2) grandchildern. He wants the income from the trust paid to the childern for 20 years and the principal distributed to the childern at the end of 20 years.. Use the internet to research the rules regarding irrevocable trusts, gift tax, and estate tax. Write a one to two (1 - 2) page client letter in wich you: 1) Analyze the...
Suppose you are a CPA, and your client has requested advice regarding establishing an irrevocable trust...
Suppose you are a CPA, and your client has requested advice regarding establishing an irrevocable trust for his two (2) grandchildern. He wants the income from the trust paid to the childern for 20 years and the principal distributed to the childern at the end of 20 years.. Use the internet to research the rules regarding irrevocable trusts, gift tax, and estate tax. Write a one to two (1 - 2) page client letter in wich you: 1) Analyze the...
Suppose you are a CPA, and your client has requested advice regarding establishing an irrecovable trust...
Suppose you are a CPA, and your client has requested advice regarding establishing an irrecovable trust for his two (2) grandchildern. He wants the income from the trust paid to the childern for 20 years and the principal distributed to the childern at the end of the 20 years. Based on the above scenario, write one to two (1-2) page client letter analyzing: 1) The effect of an irrevocable trust on the gift tax and future estate taxes for your...
For the project with the five activities given below, you are required to crash the project...
For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days. For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily...
You are part of an accounting firm Advisory team that has been engaged by a client...
You are part of an accounting firm Advisory team that has been engaged by a client to assess how they might make their “sales to order” process more “efficient”, perhaps with the introduction of new technologies. The client has provided a written description of their business, and the process under review, as follows: HHH is a small manufacturer of university based sportswear (a highly competitive market where fast response times are prized by customers). Sales span every region of the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT