Question

In: Accounting

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred). 3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 3,820,000 $ 3,220,000 Estimated costs to complete as of year-end 5,796,000 3,120,000 0 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 3,820,000 $ 3,960,000 Estimated costs to complete as of year-end 5,796,000 4,140,000 0

Solutions

Expert Solution

1 2018 2019 2020
CONTRACT PRICE $                                                              10,000,000 $   10,000,000 $                10,000,000
ACTUAL COSTS TO DATE* $                                                                 2,604,000 $      6,636,000 $                  8,576,400
ESTIMATED COST TO COMPLETE $                                                                 5,796,000 $      1,764,000 $                                  -  
TOTAL ESTIMATED COSTS $                                                                 8,400,000 $      8,400,000 $                  8,576,400
ESTIMATED GROSS PROFIT(LOSS) RECOGNISITION $                                                                 1,600,000 $      1,600,000 $                  1,423,600
(ACTUAL IN 2020)
NOTE ACTUAL COSTS TO DATE*
2018 $2,604,000
2019 $2604000+$4032000
2020 $6636000+$1940400
REVENUE RECOGNISITION
ACTUAL COSTS TO DATE / TOTAL ESTIMATED COSTS
*CONTRACT PRICE
2018 2,604,000/8,400,000*10,000,000= $                  3,100,000
2019 6,636,000/8400000*10,000,000-$3,100,000= $                  4,800,000
2020 $10,000,000-$3,100,000-$4,800,000= $                  2,100,000
GROSS PROFIT(LOSS) RECOGNISITION
REVENUE-ACTUAL COST
2018 $3,100,000-$2,604,000= $                      496,000
2019 $4,800,000-$4,032,000= $                      768,000
2020 TOTAL GROSS PROFIT RECOGNIZED ON PROJECT $                  1,423,600
LESS :GROSS PROFIT RECOGNIZED IN 2019 $                      768,000
LESS :GROSS PROFIT RECOGNIZED IN 2018 $                      496,000
GROSS PROFIT 2020 $                      159,600
2a.
DATE GENERAL JOURNAL DEBIT CREDIT
2018 CONSTRUCTION IN PROGRESS…DR $                                                                 2,604,000
TO VARIOUS ACCOUNTS $      2,604,000
2018 ACCOUNTS RECEIVABLE…DR $                                                                 2,040,000
TO BILLINGS ON CONTRUCTION CONTRACT $      2,040,000
2018 CASH…DR $                                                                 1,820,000
TO ACCOUNTS RECEIVABLE $      1,820,000
2018 CONSTRUCTION IN PROGRESS…DR $                                                                    496,000
COST OF CONSTRUCTION $                                                                 2,604,000
TO REVENUE FROM LONG TERM CONTRACT $      3,100,000
2b.
DATE GENERAL JOURNAL DEBIT CREDIT
2019 CONSTRUCTION IN PROGRESS…DR $                                                                 4,032,000
TO VARIOUS ACCOUNTS $      4,032,000
2019 ACCOUNTS RECEIVABLE…DR $                                                                 4,596,000
TO BILLINGS ON CONTRUCTION CONTRACT $      4,596,000
2019 CASH…DR $                                                                 4,000,000
TO ACCOUNTS RECEIVABLE $      4,000,000
2019 CONSTRUCTION IN PROGRESS…DR $                                                                    768,000
COST OF CONSTRUCTION $                                                                 4,032,000
TO REVENUE FROM LONG TERM CONTRACT $      4,800,000
2c.
DATE GENERAL JOURNAL DEBIT CREDIT
2020 CONSTRUCTION IN PROGRESS…DR $                                                                 1,940,400
TO VARIOUS ACCOUNTS $      1,940,400
2020 ACCOUNTS RECEIVABLE…DR $                                                                 3,364,000
TO BILLINGS ON CONTRUCTION CONTRACT $      3,364,000
2020 CASH…DR $                                                                 4,180,000
TO ACCOUNTS RECEIVABLE $      4,180,000
2020 CONSTRUCTION IN PROGRESS…DR $                                                                    159,600
COST OF CONSTRUCTION $                                                                 1,940,400
TO REVENUE FROM LONG TERM CONTRACT $      2,100,000
3 BALANCE SHEET 2018 2019
CURRENT ASSETS:
ACCOUNT RECEIVABLE $         220,000 $            816,000
CONSTRUCTION IN PROGRESS $                                                                 3,100,000 $                  7,900,000
LESS:BILLINGS                                                                   (2,040,000)                    (6,636,000)
COSTS IN EXCESS OF BILLINGS          1,060,000            1,264,000
4 2018 2019 2020
CONTRACT PRICE $                                                              10,000,000 $   10,000,000 $                10,000,000
ACTUAL COSTS TO DATE* $                                                                 2,604,000 $      6,424,000 $                  9,644,000
ESTIMATED COST TO COMPLETE $                                                                 5,796,000 $      3,120,000 $                                  -  
TOTAL ESTIMATED COSTS $                                                                 8,400,000 $      9,544,000 $                  9,644,000
ESTIMATED GROSS PROFIT(LOSS) RECOGNISITION $                                                                 1,600,000 $         456,000 $                      356,000
(ACTUAL IN 2020)
NOTE ACTUAL COSTS TO DATE*
2018 $2,604,000
2019 $2604000+$3820000
2020 $6424000+$3220000
REVENUE RECOGNISITION
ACTUAL COSTS TO DATE / TOTAL ESTIMATED COSTS
*CONTRACT PRICE
2018 2,604,000/8,400,000*10,000,000= $                  3,100,000
2019 6,424,000/9544000*10,000,000-$3,100,000= $            3,630,930.43 $        3,630,930
2020 $10,000,000-$3,100,000-$3,630,930= $                  3,269,070
GROSS PROFIT(LOSS) RECOGNISITION
REVENUE-ACTUAL COST
2018 $3,100,000-$2,604,000= $                      496,000
2019 $3,630,930-$3,820,000= $                    (189,070)
2020 TOTAL GROSS PROFIT RECOGNIZED ON PROJECT $                      356,000
LESS :GROSS PROFIT RECOGNIZED IN 2019 $                    (189,070)
LESS :GROSS PROFIT RECOGNIZED IN 2018 $                      496,000
GROSS PROFIT 2020 $                        49,070
5 2018 2019 2020
CONTRACT PRICE $                                                              10,000,000 $   10,000,000 $                10,000,000
ACTUAL COSTS TO DATE* $                                                                 2,604,000 $      6,424,000 $                10,384,000
ESTIMATED COST TO COMPLETE $                                                                 5,796,000 $      4,140,000 $                                  -  
TOTAL ESTIMATED COSTS $                                                                 8,400,000 $   10,564,000 $                10,384,000
ESTIMATED GROSS PROFIT(LOSS) RECOGNISITION $                                                                 1,600,000 $       (564,000) $                    (384,000)
(ACTUAL IN 2020)
NOTE ACTUAL COSTS TO DATE*
2018 $2,604,000
2019 $2604000+$3820000
2020 $6424000+$3960000
REVENUE RECOGNISITION
ACTUAL COSTS TO DATE / TOTAL ESTIMATED COSTS
*CONTRACT PRICE
2018 2,604,000/8,400,000*10,000,000= $                  3,100,000
2019 6,424,000/10564000*10,000,000-$3,100,000= $            2,981,029.91 $        2,981,030
2020 $10,000,000-$3,100,000-$2,981,030= $                  3,918,970
GROSS PROFIT(LOSS) RECOGNISITION
REVENUE-ACTUAL COST
2018 $3,100,000-$2,604,000= $                      496,000
2019 $2,981,030-$3,820,000= $                    (838,970)
2020 TOTAL GROSS PROFIT RECOGNIZED ON PROJECT $                    (384,000)
LESS :GROSS PROFIT RECOGNIZED IN 2019 $                    (838,970)
LESS :GROSS PROFIT RECOGNIZED IN 2018 $                      496,000
GROSS PROFIT 2020 $                      (41,030)

Related Solutions

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018. 2019 2020 Cost incurred during the year $2,624,000  $3,690,000  $2,074,600 Estimated costs to complete as of year-end 5,576,000   1,886,000 0 Billings during the year 2,200,000   4,114,000   3,686,000 Cash collections during the year 2,000,000   3,800,000   4,200,000 Westgate Construction uses the completed contract method of accounting for long-term construction contracts. Required: 1. Calculate the...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year-end 5,041,000 2,414,000 0 Billings during the year 2,190,000 2,496,000 5,314,000 Cash collections during the year 1,895,000 2,400,000 5,705,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT