Question

In: Finance

year 0 year 1 year 2 year 3 year 4 cashflow for S -100 40 50...

year 0 year 1 year 2 year 3 year 4
cashflow for S -100 40 50 30 30
cashflow for L -100 10 10 50 90

If the company's cost of capital is 5% and the decision is made by choosing the project with the higher IRR, how much value will be forgone?

a. $4.01

b. $20.80

c. $29.89

d. $1.79

e. $12.45

Solutions

Expert Solution

Project S
IRR is the rate at which NPV =0
IRR 0.199347165
Year 0 1 2 3 4
Cash flow stream -100 40 50 30 30
Discounting factor 1 1.199347 1.438434 1.725181 2.0690913
Discounted cash flows project -100 33.35148 34.76003 17.38948 14.499119
NPV = Sum of discounted cash flows
NPV Project S = 0.000105764
Where
Discounting factor = (1 + IRR)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 19.93%
Project L
IRR is the rate at which NPV =0
IRR 0.152058482
Year 0 1 2 3 4
Cash flow stream -100 10 10 50 90
Discounting factor 1 1.152058 1.327239 1.529057 1.7615627
Discounted cash flows project -100 8.680115 7.534439 32.6999 51.091
NPV = Sum of discounted cash flows
NPV Project L = 0.005455073
Where
Discounting factor = (1 + IRR)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 15.21%
Project S
Discount rate 0.05
Year 0 1 2 3 4
Cash flow stream -100 40 50 30 30
Discounting factor 1 1.05 1.1025 1.157625 1.2155063
Discounted cash flows project -100 38.09524 45.35147 25.91513 24.681074
NPV = Sum of discounted cash flows
NPV Project S = 34.04
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project L
Discount rate 0.05
Year 0 1 2 3 4
Cash flow stream -100 10 10 50 90
Discounting factor 1 1.05 1.1025 1.157625 1.2155063
Discounted cash flows project -100 9.52381 9.070295 43.19188 74.043223
NPV = Sum of discounted cash flows
NPV Project L = 35.83
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

Project S has higher IRR thus it will be chosen but its NPV is 35.83-34.04 = 1.79 lesser than project L


Related Solutions

Consider the following two​ projects: Project    Year 0 Cashflow   Year 1 Cashflow    Year 2 Cashflow    Year...
Consider the following two​ projects: Project    Year 0 Cashflow   Year 1 Cashflow    Year 2 Cashflow    Year 3 Cashflow   Year 4 Cashflow Discount rate A    -100 40 50 60 N/A .15 B -147   50 70 90 5 .15 An incremental IRR of Project B over Project A is _________%. (Please round to two decimal places, write the number only without "%". i.e. if the answer is "5%", write "5.00")
PPS S/O A B A B 1 $48 $40 50 100 2 52 49 50 100...
PPS S/O A B A B 1 $48 $40 50 100 2 52 49 50 100 3 39 24 50 200 4 58 27 50 200 5 66 25 50 200 *Stock B has a two-for-one stock split in year 3. Calculate the price-weighted index and the value-weighted index. Calculate the percentage change from year 2 to year 3 for both indexes. PPS=Price per share. S/O= Shares outstanding
Consider the following three projects: Project/time line 0 1 2 3 4 A -95 50 40...
Consider the following three projects: Project/time line 0 1 2 3 4 A -95 50 40 40 0 B -115 35 40 45 50 C -125 60 60 60 -20 The cost of capital of the firm is 10%. Based on the IRR decision rule: 1. Should you invest in Project A? Below are multiple choice for the IRR calculation i) 16.55% ii) 17.61% iii) 18.31% iv) 20.22% v) Cannot calculate Answer: I should/should not (choose one) invest in Project...
​​ Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100...
​​ Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100 $35 $35 $35 $35 B Cash flows -$100 $60 $50 $40 $30 If project B is risker than project A, in which project A has WACC = 6.00% while project B has WACC = 8.50%. If these two projects are mutually exclusive, which project should the company accept? Compute: NPV, IRR, MIRR, payback, and discounted payback period for each project. # please with details.
A= 1 2 4 0 1 -2 -1 0 1 2 0 3 8 1 4...
A= 1 2 4 0 1 -2 -1 0 1 2 0 3 8 1 4 . Let W denote the row space for A. (a) Find an orthonormal basis for W and for W⊥. (b) Compute projW⊥(1 1 1 1 1 ).
exampleInput.txt 1 2 3 0 2 3 4 0 1 3 5 0 1 2 6...
exampleInput.txt 1 2 3 0 2 3 4 0 1 3 5 0 1 2 6 1 5 6 8 2 4 6 7 3 4 5 9 10 5 8 9 4 7 9 6 7 8 6 How can I detect when 'cin' starts reading from a new line. The amount of numbers in each row is unknown. I need them in type 'int' to use the data.
0. 0. 0. 0.0. 0. 0. 0. 0. 1. 1. 1. 1. 1. 1. 2. 2. 2. 3. 4.
0. 0. 0. 0.0. 0. 0. 0. 0.   1. 1. 1. 1. 1. 1. 2. 2. 2. 3.   4. A.)MEAN – B.)MEDIAN - C.)MODE - D.)STANDARD DEVIATION – E.)5 NUMBER SUMMARY – F.)BOX AND WHISKERS PLOT – G.) OUTLIERS-
0. 0. 0. 0.0. 0. 0. 0. 0. 1. 1. 1. 1. 1. 1. 2. 2. 2. 3. 4.
0. 0. 0. 0.0. 0. 0. 0. 0.   1. 1. 1. 1. 1. 1. 2. 2. 2. 3.   4. A.)5 NUMBER SUMMARY – B.)BOX AND WHISKERS PLOT – C.) OUTLIERS-
Let S = {-3, -2, -1, 0, 1, 2, 3}. Define a relation R on S...
Let S = {-3, -2, -1, 0, 1, 2, 3}. Define a relation R on S by: xRy if and only if x = y + 4n for some integer n. a) Prove that R is an equivalence relation. b) Find all the distinct equivalence classes of R.
Project Year 0 Year 1 Year 2 Year 3 Year 4 A    -$ 49 $ 25...
Project Year 0 Year 1 Year 2 Year 3 Year 4 A    -$ 49 $ 25 $ 22 $ 22 $ 15 B -$ 101 $ 19 $ 39 $ 51 $ 61 a. What are the IRRs of the two​ projects? b. If your discount rate is 4.8%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT