In: Finance
year 0 | year 1 | year 2 | year 3 | year 4 | |
cashflow for S | -100 | 40 | 50 | 30 | 30 |
cashflow for L | -100 | 10 | 10 | 50 | 90 |
If the company's cost of capital is 5% and the decision is made by choosing the project with the higher IRR, how much value will be forgone?
a. $4.01
b. $20.80
c. $29.89
d. $1.79
e. $12.45
Project S | |||||
IRR is the rate at which NPV =0 | |||||
IRR | 0.199347165 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -100 | 40 | 50 | 30 | 30 |
Discounting factor | 1 | 1.199347 | 1.438434 | 1.725181 | 2.0690913 |
Discounted cash flows project | -100 | 33.35148 | 34.76003 | 17.38948 | 14.499119 |
NPV = Sum of discounted cash flows | |||||
NPV Project S = | 0.000105764 | ||||
Where | |||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
IRR= | 19.93% | ||||
Project L | |||||
IRR is the rate at which NPV =0 | |||||
IRR | 0.152058482 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -100 | 10 | 10 | 50 | 90 |
Discounting factor | 1 | 1.152058 | 1.327239 | 1.529057 | 1.7615627 |
Discounted cash flows project | -100 | 8.680115 | 7.534439 | 32.6999 | 51.091 |
NPV = Sum of discounted cash flows | |||||
NPV Project L = | 0.005455073 | ||||
Where | |||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
IRR= | 15.21% | ||||
Project S | |||||
Discount rate | 0.05 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -100 | 40 | 50 | 30 | 30 |
Discounting factor | 1 | 1.05 | 1.1025 | 1.157625 | 1.2155063 |
Discounted cash flows project | -100 | 38.09524 | 45.35147 | 25.91513 | 24.681074 |
NPV = Sum of discounted cash flows | |||||
NPV Project S = | 34.04 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
Project L | |||||
Discount rate | 0.05 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -100 | 10 | 10 | 50 | 90 |
Discounting factor | 1 | 1.05 | 1.1025 | 1.157625 | 1.2155063 |
Discounted cash flows project | -100 | 9.52381 | 9.070295 | 43.19188 | 74.043223 |
NPV = Sum of discounted cash flows | |||||
NPV Project L = | 35.83 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
Project S has higher IRR thus it will be chosen but its NPV is 35.83-34.04 = 1.79 lesser than project L