Question

In: Finance

Consider the following three projects: Project/time line 0 1 2 3 4 A -95 50 40...

Consider the following three projects:

Project/time line

0

1

2

3

4

A

-95

50

40

40

0

B

-115

35

40

45

50

C

-125

60

60

60

-20

The cost of capital of the firm is 10%.

Based on the IRR decision rule:

1. Should you invest in Project A?

Below are multiple choice for the IRR calculation

i) 16.55%

ii) 17.61%

iii) 18.31%

iv) 20.22%

v) Cannot calculate

Answer: I should/should not (choose one) invest in Project A.

2. Should you invest in Project B?

Below are multiple choice for the IRR calculation

i) 16.55%

ii) 17.61%

iii) 18.31%

iv) 20.22%

v) Cannot calculate

Answer: I should/should not (choose one) invest in Project B.

3. Should you invest in Project C?

Below are multiple choice for the IRR calculation

i) 16.55%

ii) 17.61%

iii) 18.31%

iv) 20.22%

v) Cannot calculate

Answer: I should/should not (circle one) invest in Project C.

4. Assume that we can only take one of the projects. Which one would we choose?

Answer: You would choose project ____________

Solutions

Expert Solution

The Internal Rate of Return (IRR) is a measure of annualized rate of return for an investment. IRR is essentially that rate of return where the Net Present Value (NPV) of a project is zero. IRR is computed using the following algebraic formula:

where CF represent the cash flows in different years.

IRR can be calculated using the IRR or XIRR function in an excel spreadsheet or using a financial calculator. An approximation of IRR can be obtained manually using trial and error.

The IRRs for projects A, B and C are as follows:

Project IRR
A 18.31%
B 16.55%
C 15.30%

IRR Decision Rule: An investment is economically feasible if its IRR exceeds the firm's cost of capital as the NPV would be positive in this case and the shareholder's wealth will increase.

1. Correct Option - iii)

I should invest in project A as the IRR is higher than the cost of capital.

2. Correct Option - i)

I should invest in project B as the IRR is higher than the cost of capital.

3. Correct Option - None

I should invest in project C as the IRR is higher than the cost of capital.

4. If one one of the project could be chosen then the firm should go with Project A as it has the highest IRR among the three.


Related Solutions

Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project...
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: -$1000, 375, 375, 375, 375,-100 Project B: -$1000, 900, 700, 500, -200, 200 The cost of capital for both projects is 10% 1. Find the NPV and MIRR of projects A and B. If project A and B are mutually exclusive. 2. Find the crossover rate for projects A and B. 3. What is the profitability index for projects A and B? How...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 -$ 152 $22 $39 $58 $82 Project 2          −826 0 0 7,010 −6,506 Project 3 21 41 61 80   −247 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest1%​). c. What is the NPV of each project if the cost of capital is 5%​?20 %50%​? a. For which of these...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 −$151 $ 21 $ 39 $ 59 $ 80 Project 2                                                −824 00 00 6,999 −6,501 Project 3 2020 40 62 81 −245 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest 1%​). c. What is the NPV of each project if the cost of capital is 5%​? 20%​? 50%​? a....
​​ Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100...
​​ Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100 $35 $35 $35 $35 B Cash flows -$100 $60 $50 $40 $30 If project B is risker than project A, in which project A has WACC = 6.00% while project B has WACC = 8.50%. If these two projects are mutually exclusive, which project should the company accept? Compute: NPV, IRR, MIRR, payback, and discounted payback period for each project. # please with details.
Consider the following project: Year 0 1 2 3 4 Project A -20.00 8.00 7.00 6.00...
Consider the following project: Year 0 1 2 3 4 Project A -20.00 8.00 7.00 6.00 7.00 Find the payback for this project. (ROUND TO TWO DECIMAL PLACES)
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5...
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: ($1000), 100, 600, 700, 900, 300 Project B: ($1000), 900, 700, 500, 300, 300 The cost of capital for both projects is 10% 1. Find NPV, IRR and profitability index (PI) of projects A and B. 2. If projects A and B are mutually exclusive, which project would you select 3. Find the crossover rate for projects A and B
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5
  Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: ($1000), 100, 600, 700, 900, 300 Project B: ($1000), 900, 700, 500, 300, 300 The cost of capital for both projects is 10% 1. Find NPV, IRR and profitability index (PI) of projects A and B. 2. If projects A and B are mutually exclusive, which project would you select 3. Find the crossover rate for projects A and B
3. AICC is considering the following two projects: (2 pts) Project Year 0 1 2 3...
3. AICC is considering the following two projects: (2 pts) Project Year 0 1 2 3 A Cash flows -$50 $15 $25 $25 B Cash flows -$50 $20 $25 $30 a. If these projects are mutually exclusive, which project should the company invest in based on the NPV and IRR if the WACC = 10%? b. Calculate MIRR, payback period, and discounted payback period for the project you chose to invest in from part A only.
Consider the following page reference string: 0, 1, 2, 3, 1, 0, 4, 5, 1, 0,...
Consider the following page reference string: 0, 1, 2, 3, 1, 0, 4, 5, 1, 0, 1, 2, 6, 5, 2, 1, 0, 1, 2, 5 How many page faults would occur for the following replacement algorithms, assuming one, three, five, and seven frames? Remember that all frames are initially empty, so your first unique pages will cost one fault each. Optimal replacement LRU replacement CLOCK replacement FIFO replacement
year 0 year 1 year 2 year 3 year 4 cashflow for S -100 40 50...
year 0 year 1 year 2 year 3 year 4 cashflow for S -100 40 50 30 30 cashflow for L -100 10 10 50 90 If the company's cost of capital is 5% and the decision is made by choosing the project with the higher IRR, how much value will be forgone? a. $4.01 b. $20.80 c. $29.89 d. $1.79 e. $12.45
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT