Question

In: Operations Management

Give a detailed overview and analysis of two key aspects of university building construction project using...

Give a detailed overview and analysis of two key aspects of university building construction project using project management concepts, tools and techniques.
You should focus your analysis on any two topics below;
*Scheduling project resource and costs
*Project stakeholder management
*Managing project (Teams) human resources
*Managing project scope...
VERY URGENT
DETAILED ANSWERS NEEDED
WIYH REFERENCING
PLEASE ANSWER ASAP

Solutions

Expert Solution

Introduction-

Project Management- It refers to leading a team work towards the desired sets of goal in order to achieve them and thus ensuring success of the whole project through effective and efficient management of the project. In project management every aspect is planned out in detail whether human resources required, financial resources,raw material to be required, managing stakeholders etc prior to the start of the project in order to effectively carry out its activities

In order for the construction of a college building project using project mangement concept, tools and techniques the two key aspects of the following are

1) Scheduling project resources and cost- It refers to the overall management of the resources and the cost requirement of the project.Here the project manager is responsible for the arrangement of the required resources and its cost that is required in the project by estimating them prior to the start of the project , for which a manager need to make a detailed plan regarding what are resources to be required in this construction project than how to procure the required resources what will be the sources from which they are collected and what will be its estimated cost to be included in the project and other such detail of the resourceswill be acquired by the project manager

The project manager is also responsible for the overall cost of the project as cost factor is the factor that is involved at every step of the project. for which the project manager need to make the proper estimation of the cost factor that is involved in each step of the project so in order to know the actual cost of the project and thus making arrangement for the required financial resources for the project This construction project requires cost from the very first level i.e from acquiring resources and than making arrangement to bring them at the required destination, than the cost requires to acquire human resources , cost of required tools and equipment required in the process and so other

2) Managing Project (team) Human resources- Human resources are considered of the important aspect of any of the project as with the availability of human resources no project can be completed and no just the availability of human resources will be sufficient for the human resources but a proper and effective management is required for the available human resources for the effective executive and implemention of the project thus for which the project manager makes its best effort through its knowledge and experiences to manage these human resources.

This construction of a college building requires human resources at various level for its successful implementation thus the project manager will first check out the areas where and at what level these human resources are required than makes the arrangement to acquire these human resources through the hiring and recruiting process which ensure the right person to the right job as these human resources are required at various level from lower level i.e labours to the higher level i.e leader and assistant manager so making the required recruitment of these resources Thus after making effective recruitment the project manager also needs to provide them with the required training in order to make their working smooth and effective and they requires proper and effective guidance for the project.


Related Solutions

LO3 Discuss the key stages in a construction project, and how Building Information Modelling informs the...
LO3 Discuss the key stages in a construction project, and how Building Information Modelling informs the different stages P6 Identify, with examples, modern construction processes and sequences used within today’s industry, highlighting the way they respond to sustainability needs. P7 Explain contract planning techniques used within micro and macro projects. P8 Identify where BIM impacts upon operations and construction companies.
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
Define rework in construction project and milestone in construction project and give example .
Define rework in construction project and milestone in construction project and give example .
As part of the Project Scope Statement of a house construction project, prepare the detailed Milestone...
As part of the Project Scope Statement of a house construction project, prepare the detailed Milestone Schedule (Baseline Milestone – Date) by arranging the following activity items/milestones in a proper sequence from No. 1 to 15, assuming the first milestone date as 05- 01-2020 and the last as 30-09-2020. Assume the dates in between corresponding to the various milestones which are given in no particular order: Foundation complete, Excavation complete, Permits approved & construction begins, Contract signed, Design complete, Framing...
You are the project manager responsible for a new building construction in northern Virginia. The building...
You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and...
Beavis Construction Company was the low bidder on a construction project to build an office building...
Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below: 2017 2018 2019 Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000 Estimated costs to complete 4,500,000 1,500,000 -0- Billings during the year 1,400,000 5,200,000 1,400,000 Cash collections during the year 1,000,000 4,000,000 3,000,000 Assume that Beavis recognizes revenue on this contract over time according...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $530,000 and $730,000 B Normal probability distribution with a mean bid of $630,000 and a standard deviation of $43,000 If required, round your answers to three...
Comparison of two hypothetical cases: Project 1: New construction of a highrise building in Wall Street,...
Comparison of two hypothetical cases: Project 1: New construction of a highrise building in Wall Street, Manhattan, NYC. Project 2: New construction of LNG tanks in Cameron, Louisiana Two projects are greatly different in terms of project type and location. Discuss and compare unique impacts on the environment and public that may occur in each project.
Can u give a sample of a detailed Inspection Report for the Structural of a Building...
Can u give a sample of a detailed Inspection Report for the Structural of a Building excluding the finishing works. Kindly indicate the Sub-structure inspection and Superstructure inspection.
Give excell sheet for load calculation for designing building in staad and etabs Give detailed excell...
Give excell sheet for load calculation for designing building in staad and etabs Give detailed excell format for stair case design also .
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT