In: Statistics and Probability
Given the following project:
| 
 Activity  | 
 Predecessor  | 
 Duration (week)  | 
 Required No. of Workers  | 
| 
 1  | 
 -  | 
 3  | 
 2  | 
| 
 2  | 
 -  | 
 2  | 
 1  | 
| 
 3  | 
 2  | 
 3  | 
 2  | 
| 
 4  | 
 2,5  | 
 4  | 
 2  | 
| 
 5  | 
 1  | 
 4  | 
 1  | 
| 
 6  | 
 3,4,1  | 
 3  | 
 1  | 
| 
 7  | 
 3  | 
 4  | 
 2  | 
| 
 8  | 
 5  | 
 3  | 
 1  | 
Assume the followings:
The available resource is three units
1)
Time-limited resource profile

2)
In the original schedule, we see that resource requirement in period 3, 8, and 9 exceeds the available resources (3). Therefore, activities C and G are rescheduled.
Resulting resource-constrained schedule is as follows:

-------------------------------------
DEAR STUDENT,
IF YOU HAVE ANY QUERY ASK ME IN THE COMMENT BOX,I AM HERE TO HELPS YOU.PLEASE GIVE ME POSITIVE RATINGS
*****************THANK YOU***************