Question

In: Finance

You are given the following cash flows for the project: Time 0 Time 1 Time 2...

  1. You are given the following cash flows for the project:

Time 0

Time 1

Time 2

Time 3

Time 4

-115,000

30,000

50,000

50,000

20,000

If the If the required rate of return is 13%, (1) what is the payback period, (2) what is the NPV, (3) what is the IRR, and (4) what is the Profitability Index (PI). Should we accept the project?

Solutions

Expert Solution

Comments
Payback period                    2.70 Years Payback period is within 4 year's life.So,on payback period it is acceptable.
NPV $           -2,375 Negative.So, on this basis project is not acceptable.
IRR 11.98% IRR is less than required return.So, on this basis also, project is not acceptable.
Profitability Index                    0.98 Profitability Index is less than 1.So, on this basis project is not acceptable.
The objective of investment is to create money.Negative NPV shows that project is not generating money.
So, on overall basis, we should not accept the project/
Working:
Year Cash flow Cumulative cash flow Discount factor Present value of cash flows Cumulative present value of cash flows
a b c d=1.13^-a e=b*d f
0 $       -1,15,000 $ -1,15,000               1.0000 $       -1,15,000 $     -1,15,000
1 $             30,000 $     -85,000               0.8850 $             26,549 $         -88,451
2 $             50,000 $     -35,000               0.7831 $             39,157 $         -49,294
3 $             50,000 $      15,000               0.6931 $             34,653 $         -14,641
4 $             20,000 $      35,000               0.6133 $             12,266 $           -2,375
=irr(B5:B9)
11.98%
Payback period = 2+(35000/50000)
=                    2.70
Profitability index = Present value of cash inflows / Initial cost of project
= (-2375+115000) / $       1,15,000
= $       1,12,625 / $       1,15,000
=                    0.98

Related Solutions

A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2...
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2 7,630 3 5,040 4 −1,580 Assuming the appropriate interest rate is 10 percent, what is the MIRR for this project using the discounting approach? 19.21% 15.23% 13.96% 11.63% 17.77%
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2...
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2 7,360 3 4,800 4 −1,640 Assuming the appropriate interest rate is 7 percent, what is the MIRR for this project using the discounting approach?
A project has the following cash flows: Year Cash Flows 0 −$127,800 1 47,000 2 63,800...
A project has the following cash flows: Year Cash Flows 0 −$127,800 1 47,000 2 63,800 3 51,600 4 28,100 The required return is 8.3 percent. What is the profitability index for this project?
Calculate the NPV given the following cash​ flows YEAR   CASH FLOWS 0 -60,000 1 25,000 2...
Calculate the NPV given the following cash​ flows YEAR   CASH FLOWS 0 -60,000 1 25,000 2 25,000 3 15,000 4 15,000 5 10,000 6   10,000 if the appropriate required rate of return is 8 percent. Should the project be​ accepted? What is the​ project's NPV​?
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2...
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2 8,100 3 6,600 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ What is the NPV at a discount rate of 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ What is the NPV...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2 –27,600 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2 –48,100    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 11.5 percent?    c. NPV at 0 percent?    d. NPV at 23 percent?
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2...
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2 7,600 3 6,100     What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)      NPV $       What is the NPV at a discount rate of 9 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)      NPV $   ...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 -$ 152 $22 $39 $58 $82 Project 2          −826 0 0 7,010 −6,506 Project 3 21 41 61 80   −247 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest1%​). c. What is the NPV of each project if the cost of capital is 5%​?20 %50%​? a. For which of these...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 −$151 $ 21 $ 39 $ 59 $ 80 Project 2                                                −824 00 00 6,999 −6,501 Project 3 2020 40 62 81 −245 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest 1%​). c. What is the NPV of each project if the cost of capital is 5%​? 20%​? 50%​? a....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT