In: Finance
NPV profile of a project. Given the following cash flow of Project L-2, draw the NPV profile. Hint: Be sure to use a discount rate of zero for one intercept (y-axis) and solve for the IRR for the other intercept (x-axis).
Year 0 -$250,000
Year 1 $49,000
Year 2 $80,000
Year 3 $114,000
Year 4 $139,000
What is the NPV of Project L-2 where zero is the discount rate?
What is the IRR of Project L-2?
Which of the graphs below best fits the NPV profile of the project?
(a)-Net Present Value (NPV) of Project L-2 where zero is the discount rate
If the Discount Rate is Zero, the NPV of the Project is the sum of the Future cash flows deducted by Initial Investment
Net Present Value (NPV) = Sum of future cash flow – initial Investment
= [$49,000 + $80,000 + $114,000 + $139,000] - $250,000
= $382,000 - $250,000
= $132,000
“Hence, the Net Present Value (NPV) of the Project L-2 at Zero Discount rate = $132,000”
(b)-Internal Rate of Return (IRR) of Project L-2
Step – 1, Firstly calculate NPV at a guessed discount Rate, Say 16% (R1)
Year |
Annual Cash Flow ($) |
Present Value factor at 16% |
Present Value of Cash Flow ($) |
1 |
49,000 |
0.86207 |
42,241 |
2 |
80,000 |
0.74316 |
59,453 |
3 |
1,14,000 |
0.64066 |
73,035 |
4 |
1,39,000 |
0.55229 |
76,768 |
TOTAL |
251,498 |
||
Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment
= $251,498 - $250,000
= $1,498
Step – 2, NPV at 16% is positive, Calculate the NPV again at a higher discount rate, Say 17% (R2)
Year |
Annual Cash Flow ($) |
Present Value factor at 17% |
Present Value of Cash Flow ($) |
1 |
49,000 |
0.85470 |
41,880 |
2 |
80,000 |
0.73051 |
58,441 |
3 |
1,14,000 |
0.62437 |
71,178 |
4 |
1,39,000 |
0.53365 |
74,177 |
TOTAL |
245,677 |
||
Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment
= $245,677 - $250,000
= -$4,323 (Negative NPV)
Therefore IRR = R1 + NPV1(R2-R1)
NPV1-NPV2
= 0.16 + [$1,498 x (0.17 – 0.16)]
$1,498 – (-$4,323)
= 0.16 + [$14.98 / $5,821]
= 0.16 + 0.0026
= 0.1626 or
= 16.26%
“Hence, the Internal Rate of Return (IRR) of Project L-2 would be 16.26%”
NOTE
The Formula for calculating the Present Value Factor is [1/(1 + r)n], Where “r” is the Discount/Interest Rate and “n” is the number of years.