Question

In: Operations Management

Given the following project: 1. Develop a time limited resource profile chart assuming unlimited resource availability....

Given the following project: 1. Develop a time limited resource profile chart assuming unlimited resource availability. That is, determine the resource requirement on a weekly basis if the project is to be completed in the minimum time. 2. Develop a resource-constrained schedule using the sequential heuristic.

Activity

Predecessor

Duration

(week)

Required No.

of Workers

1

-

3

2

2

-

2

1

3

2

3

2

4

2,5

4

2

5

1

4

1

6

3,4,1

3

1

7

3

4

2

8

5

3

1

Assume the followings:

  • The original relationships of the network cannot be violated.
  • Scheduling priority for each activity is determined via the following rules
  • least total slack
  • early start time
  • smallest duration
  • maximum resource level
  • once an activity is scheduled it continues without interruption

The available resource is three units

Solutions

Expert Solution

Time-limited resource profile is as follows:

---------------------------------------------------

In the original schedule, we see that resource requirement in period 3, 8, and 9 exceeds the available resources (3). Therefore, activities C and G are rescheduled.

Resulting resource-constrained schedule is as follows:


Related Solutions

Given the following project: Develop a time limited resource profile chart assuming unlimited resource availability. That...
Given the following project: Develop a time limited resource profile chart assuming unlimited resource availability. That is, determine the resource requirement on a weekly basis if the project is to be completed in the minimum time. Develop a resource-constrained schedule using the sequential heuristic. Activity Predecessor Duration (week) Required No. of Workers 1 - 3 2 2 - 2 1 3 2 3 2 4 2,5 4 2 5 1 4 1 6 3,4,1 3 1 7 3 4 2...
1. Suppose there is a decrease in the availability of an important major resource, such as...
1. Suppose there is a decrease in the availability of an important major resource, such as oil. Which shift would most likely occur?         a.    The aggregate supply would shift right.         b.    The aggregate supply would shift left.         c.     The aggregate demand would shift right.         d.    The aggregate demand would shift left. 2. How does the aggregate demand and aggregate supply model reflect a rise in wage rates?         a.    The short-run...
You are given the following cash flows for the project: Time 0 Time 1 Time 2...
You are given the following cash flows for the project: Time 0 Time 1 Time 2 Time 3 Time 4 -115,000 30,000 50,000 50,000 20,000 If the If the required rate of return is 13%, (1) what is the payback period, (2) what is the NPV, (3) what is the IRR, and (4) what is the Profitability Index (PI). Should we accept the project?
NPV profile of a project. Given the following cash flow of Project​ L-2, draw the NPV...
NPV profile of a project. Given the following cash flow of Project​ L-2, draw the NPV profile. Hint​: Be sure to use a discount rate of zero for one intercept ​(y​-axis) and solve for the IRR for the other intercept ​(x​-axis). Year 0   -$250,000 Year 1   $49,000 Year 2   $80,000 Year 3   $114,000 Year 4   $139,000 What is the NPV of Project​ L-2 where zero is the discount​ rate? What is the IRR of Project​ L-2? Which of the graphs...
Given the following spot rates and assuming the bonds and the time periods are semi-annual: Time...
Given the following spot rates and assuming the bonds and the time periods are semi-annual: Time Spot Rate 1 3.00% 2 3.30% 3 3.50% 4 3.90% 5 4.40% 6 4.75% 7 4.95% 8 5.05% 9 5.15% 10 5.25% 11 5.40% 12 5.50% 13 5.60% 14 5.65% 15 5.75% 16 5.80% 1.What is the price of a 4% coupon bond maturing in 5 years? 2. What is the YTM on the above bond? 3. What is the implied forward rate on...
Develop a python program to create a quiz with limited time and attempts!!! Add comments and...
Develop a python program to create a quiz with limited time and attempts!!! Add comments and screenshot of running the program quiz could be of anything like , what's the sum of 2&2. There should be number of attempts(limited) suppose if the answer is wrong.
1. The concept of scarcity in economics refers to   limited resources and unlimited wants a shortage...
1. The concept of scarcity in economics refers to   limited resources and unlimited wants a shortage of food    unlimited resources and limited wants   the fact that resources can sometimes be limited 2. How does a decrease in the price of smart phones affect the demand for headphones? It will likely decrease a demand for headphones.     It will likely increase a supply of headphones.    It should not have any effect on the headphone market.    It will likely increase...
Develop a chart that includes the structure and function of the following: • Skin • Keratinocytes...
Develop a chart that includes the structure and function of the following: • Skin • Keratinocytes • Melanocytes • Langerhans cells • Merkel • Cells • Dermis • Basement membrane zone • Sebaceous gland • Eccrine gland • Apocrine gland • Nails • Hair
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 -...
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 - 3 3 1, 2 2 4 3 5 5 3 4 The required project completion time is 12. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 2 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4"?
1.         Fill in the following chart for the correlation coefficient. No credit will be given unless...
1.         Fill in the following chart for the correlation coefficient. No credit will be given unless the entire chart is filled in. Name Symbol What it Tells Us Abs. or Rel.? (give units if absolute) Boundaries What Extremes Signify Population Correlation Coefficient Sample Correlation Coefficient 2.         Fill in the following chart for the coefficient of determination. No credit will be given unless the entire chart is filled in. Name Symbol What it Tells Us Abs. or Rel.? (give units if...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT