In: Accounting
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,016,000 | $ | 2,808,000 | $ | 2,613,600 | |||
Estimated costs to complete as of year-end | 5,184,000 | 2,376,000 | 0 | ||||||
Billings during the year | 2,180,000 | 2,644,000 | 5,176,000 | ||||||
Cash collections during the year | 1,890,000 | 2,500,000 | 5,610,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary
journal entries for the year 2018 (credit "Various accounts" for
construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2020 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to
prepare a partial balance sheet for 2018 and 2019 showing any items
related to the contract.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,016,000 | $ | 3,890,000 | $ | 3,290,000 | |||
Estimated costs to complete as of year-end | 5,184,000 | 3,190,000 | 0 | ||||||
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,016,000 | $ | 3,890,000 | $ | 4,170,000 | |||
Estimated costs to complete as of year-end | 5,184,000 | 4,280,000 | 0 | ||||||
Solution :-
1. Answer -
Particulars | 2018 | 2019 | 2020 |
Contract price ( C) | $10,000,000 | $10,000,000 | $10,000,000 |
Actual cost to date - (A) | $2,016,000 | $4,824,000 | $7,437,600 |
Estimated cost to complete - (B) | $5,184,000 | $2,376,000 | |
Total estimated costs - (D = A + B) | $7,200,000 | $7,200,000 | $7,437,600 |
Estimated gross profit (loss) Actual in 2020 ( E = C - D) | $2,800,000 | $2,800,000 | $2,562,400 |
Calculation of Revenue Recognition :-
2018 = ($2,016,000 ÷ $7,200,000) × $10,000,000 = $2,800,000
2019 = ($4,824,000 ÷ $7,200,000) × $10,000,000 = $6,700,000
2020 = ($10,000,000 - $2,800,000 - $6,700,000) = $500,000
Gross profit (loss) Recognition:-
2018 = $2,800,000 - $2,016,000 = $784,000
2019 = $6,700,000 - $2,808,000 = $3,892,000
2020 = Total gross profit recognised on the project - Gross profit recognised in 2019 - Gross profit recognised in 2018
Gross loss = $2,562,400 - $3,892,000 - $784,000 = ($2,113,600)
2 a Answer :- Journal entries
Date | Particulars | Debit | Credit |
2018 | construction in progress | $2,016,000 | |
Various accounts | $2,016,000 | ||
2018 | Accounts Receivable | $2,180,000 | |
Billings on construction contract | $2,180,000 | ||
2018 | cash | $1,890,000 | |
Accounts Receivable | $1,890,000 | ||
2018 | No Journal Entry |
2 b Answer :- Journal Entries
Date | Particulars | Debit | Credit |
2019 | Construction in progress | $28,08,000 | |
Various accounts | $2,808,000 | ||
2019 | Accounts Receivable | $2,644,000 | |
Billings on construction contract | $2,644,000 | ||
2019 | Cash | $2,500,000 | |
Accounts Receivable | $2,500,000 | ||
2019 | No Journal Entry is required |
4 Answer :-
Particulars | 2018 | 2019 | 2020 |
Contract price | $10,000,000 | $10,000,000 | $10,000,000 |
Actual Costs to date | $2,016,000 | $5,906,000 | $9,196,000 |
Estimated costs to complete | $5,184,000 | $3,190,000 | |
Total estimated costs | $7,200,000 | $9,096,000 | $9,196,000 |
Estimated gross profit ( Actual in 2020) | $2,800,000 | $904,000 | $804,000 |
Revenue Recognition :-
2018 =( $2,016,000÷ $7,200,000) × $10,000,000 = $2,800,000
2019 = ($5,906,000 ÷ $9,096,000) × $10,000,000 - $2,800,000 = $3,692,964
2020 = ($10,000,000 - $2,800,000 - $3,692,964) = $3,507,036
Gross profit (loss) Recognition :-
2018 = $2,800,000 - $2,016,000 = $ 784,000
2019 = $ 3,692,964 - $3,890,000 =($197,036)
2020 = Total gross profit recognised on project - Gross profit recognised in 2019 - Gross Profit recognised in 2018
= $804,000 + $197,036 - $784,000 = $217,036
5 Answer :-
PARTICULARS | 2018 | 2019 | 2020 |
Contract price | $10,000,000 | $10,000,000 | $10,000,000 |
Actual Costs to date | $2,016,000 | $5,906,000 | $10,076,000 |
Estimated cost to complete | $5,184,000 | $4,280,000 | |
Total estimated costs | $7,200,000 | $10,186,000 | $10,076,000 |
Estimated gross profit ( Actual in 2020) | $2,800,000 | ($186,000) | ($76,000) |
Revenue Recognition :-
2018 = ($2,016,000 ÷ $72,00,000) × $10,000,000 = $2,800,000
2019 = ($5,906,000 ÷ $10,186,000) × $10,000,000 - $2,800,000 = $2,998,154
2020 = $10,000,000 - $2,800,000 - $2,998,154 = $4,201,846
Gross profit (loss) Recognition :-
2018 = $2,800,000 - $2,016,000 = $784,000
2019 = $784,000 - $3,890,000 = ($3,106,000)
2020 = ($176,000) -$784,000 +$3,106,000 = $2,146,000