]Information for 22 to 26. In 2016 Norcraft Sisters Construction agreed to construct a residence hall...

]Information for 22 to 26. In 2016 Norcraft Sisters Construction agreed to construct a residence hall at University of Houston at a price of $1,200,000. The information relating to the costs and billings for this contract is shown below.

2016. 2017 2018

Cost incurred during the year 280,000 320,000 850,000

Estimated osts to complete. 520,000 300,000 0

Customer billing date 300,000 400,000 850,000

Collection of billing date 200,000 320,000 800,000

22. Assuming that the percentage-of-completion method is used, compute the amount of gross profit (loss) to be recognized on income statement in 2016 and 2017, respectively

A. $400,000 and 300,000

B. $140,000 and 60,000

C. $140,000 and 200,000

D. $0 and. $0

Solutions

Expert Solution

Option c) is correct.

2016 2017 2018
Cost incurred to date $        280,000 $        600,000 $        1,450,000
Estimated cost to complete $        520,000 $        300,000
Total cost $        800,000 $        900,000 $        1,450,000
Cost completion % (Cost incurred/ total cost) 35.00% 66.67% 100.00%
Revenue (cost completion %*contract price) $        420,000 $        800,000 $        1,200,000
Cost incurred $        280,000 $        600,000 $        1,450,000
Profit $        140,000 $        200,000 $         (250,000)

Related Solutions

Information for 22 to 26. In 2012 Norcraft Sisters Construction agreed to construct a residence hall...
Information for 22 to 26. In 2012 Norcraft Sisters Construction agreed to construct a residence hall at University of Houston at a price of $1,200,000. The information relating to the costs and billings for this contract is shown below. 2012 2013 2014 Costs incurred during the year $ 280,000 $320,000 $850,000 Estimated costs to complete 520,000 300,000 –0– Customer billings to date 300,000 400,000 850,000 Collection of billings to date 200,000 320,000 800,000 22. Assuming that the percentage-of-completion method is...
The Ugenti Construction Company contracted to construct a warehouse building for $2,600,000. Construction began in 2016...
The Ugenti Construction Company contracted to construct a warehouse building for $2,600,000. Construction began in 2016 and was completed in 2017. Data relating to the contract are summarized below:                                                                                    2016                  2017       Costs incurred during the year.................      $   360,000         $1,650,000       Estimated costs to complete as of 12/31.        1,560,000                   -             Billings during the year ..........................           430,000         2,170,000       Cash collections during the year..............           320,000         2,280,000 Required: 1.   Compute the amount of gross...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over time...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over time...
Questions 22-26 are based on the following information. CAPM and stock valuation. Your aunt, Beth, plans...
Questions 22-26 are based on the following information. CAPM and stock valuation. Your aunt, Beth, plans to invest in the common stock of Smart-investment Corporation. Knowing that you are studying finance, she asks for your suggestion. Your calculation shows that yield on Treasury securities is 6%. You know that the S&P 500 Index’s expected annual return is 14%. Your econometric model tells you that beta of this company’s stock is 1.25. Aunt Beth tells you that this company just paid...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT