Question

In: Accounting

Information for 22 to 26. In 2012 Norcraft Sisters Construction agreed to construct a residence hall...

Information for 22 to 26. In 2012 Norcraft Sisters Construction agreed to construct a residence hall at University of Houston at a price of $1,200,000. The information relating to the costs and billings for this contract is shown below. 2012 2013 2014 Costs incurred during the year $ 280,000 $320,000 $850,000 Estimated costs to complete 520,000 300,000 –0– Customer billings to date 300,000 400,000 850,000 Collection of billings to date 200,000 320,000 800,000

22. Assuming that the percentage-of-completion method is used, compute the amount of gross profit (loss) to be recognized on income statement in 2012 and 2013, respectively

a. $400,000 and 300,000.

b. $140,000 and 60,000.

c. $140,000 and 200,000.

d. $0 and $0.

23. Assuming that the percentage-of-completion method is used, which of the following is reported on the balance sheet at Dec. 31, 2012?

a. Receivable under current assets with a balance of $420,000

b. Net of Construction in Progress and Billings on C.I.P under current assets with a balance of $120,000

c. Billings on C.I.P under current liabilities with a balance of $300,000

d. Construction in Progress under current liabilities with a balance of $280,000

24. Assuming that the percentage-of-completion method is used, what is the amount of Revenue from Long-Term Contracts and Construction Expenses recognized for the year 2013? Revenue Expenses

a. $800,000 $320,000

b. $380,000 $ 320,000

c. $380,000 $ 600,000

d. $800,000 $ 600,000

25. Assuming that the completed contract method is used, compute the amount of gross profit (loss) to be recognized in 2012 and 2013, respectively.

a. $50,000 and 60,000.

b. $0 and 60,000.

c. $50,000 and 300,000.

d. $0 and $0.

26. If in 2013, the estimated cost to complete is estimated to be 400,000, instead of 300,000, compute the gross profit (loss) recognized in 2013 for the percentage-of-completion method and the completed contract method, respectively

a. $(20,000) and 0.

b. $0 and (20,000).

c. $(20,000) and (20,000).

d. $0 and $0.

Solutions

Expert Solution

Number 22:
2012 2013 2014
Contract Value A 1200000 1200000 1200000
Cost incurred during the year B 280000 600000 1450000
Estimated cost to complete C 520000 300000
Total Estimated Cost (B+C)=D 800000 900000 1450000
Total Estimated Gross Profit (A-D)=E 400000 300000 -250000
% Completion B/D%=F 35         66.67 100
Gross Profit Earned till date (E*F%) 140000 200000 -250000
Less: Recognized in previous Year 0 140000 60000
=to be recognized in current Year 140000 60000 -310000

Number 23

Net of construction in progress and billing on CIP under current asset with a balance of 120000
Number 24
Revenue 380000 and Expense 320000
Expense= Cost incurred during the year=600000-280000 320000
Revenue=Expense+Profit recognized during 2013=320000+60000 380000

Number 25: d 0 and 0 since in compelted method, contract revenue to be recognised after completion.

26
Completed Contract Method 0 0

Related Solutions

]Information for 22 to 26. In 2016 Norcraft Sisters Construction agreed to construct a residence hall...
]Information for 22 to 26. In 2016 Norcraft Sisters Construction agreed to construct a residence hall at University of Houston at a price of $1,200,000. The information relating to the costs and billings for this contract is shown below. 2016. 2017 2018 Cost incurred during the year 280,000 320,000 850,000 Estimated osts to complete. 520,000 300,000 0 Customer billing date 300,000 400,000 850,000 Collection of billing date 200,000 320,000 800,000 22. Assuming that the percentage-of-completion method is used, compute the...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over time...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over time...
Questions 22-26 are based on the following information. CAPM and stock valuation. Your aunt, Beth, plans...
Questions 22-26 are based on the following information. CAPM and stock valuation. Your aunt, Beth, plans to invest in the common stock of Smart-investment Corporation. Knowing that you are studying finance, she asks for your suggestion. Your calculation shows that yield on Treasury securities is 6%. You know that the S&P 500 Index’s expected annual return is 14%. Your econometric model tells you that beta of this company’s stock is 1.25. Aunt Beth tells you that this company just paid...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT