Question

In: Operations Management

THE BATHTUB PERIOD The award of the Scott contract on January 3, 1987, left Park Industries...

THE BATHTUB PERIOD

The award of the Scott contract on January 3, 1987, left Park Industries elated. The Scott Project, if managed correctly, offered tremendous opportunities for follow-on work over the next several years. Park's management considered the Scott Project as strategic in nature.

The Scott Project was a ten-month endeavor to develop a new product for Scott Corporation. Scott informed Park Industries that sole-source production contracts would follow, for at least five years, assuming that the initial R&D effort proved satisfactory. All follow-on contracts were to be negotiated on a year-to-year basis.

Jerry Dunlap was selected as project manager. Although he was young and eager, he understood the importance of the effort for future growth of the company. Dunlap was given some of the best employees to fill out his project office as part of Park's matrix organization. The Scott Project maintained a project office of seven full-time people, including Dunlap, throughout the duration of the project. In addition, eight people from the functional department were selected for representation as functional project team members, four full-time and four half-time.

Although the workload fluctuated, the manpower level for the project office and team members was constant for the duration of the project at 2,080 hours per month. The company assumed that each hour worked incurred a cost of $60.00 per person, fully burdened.

At the end of June, with four months remaining on the project, Scott Corporation informed Park Industries that, owing to a projected cash flow problem, follow-on work would not be awarded until the first week in March (1988). This posed a tremendous problem for Jerry Dunlap because he did not wish to break up the project office. If he permitted his key people to be assigned to other projects, there would be no guarantee that he could get them back at the beginning of the follow-on work. Good project office personnel are always in demand.

Jerry estimated that he needed $40,000 per month during the “bathtub” period to support and maintain his key people. Fortunately, the bathtub period fell over Christmas and New Year's, a time when the plant would be shut down for seventeen days. Between the vacation days that his key employees would be taking, and the small special projects that his people could be temporarily assigned to on other programs, Jerry revised his estimate to $125,000 for the entire bathtub period.

At the weekly team meeting, Jerry told the program team members that they would have to “tighten their belts” in order to establish a management reserve of $125,000. The project team understood the necessity for this action and began rescheduling and replanning until a management reserve of this size could be realized. Because the contract was firm-fixed-price, all schedules for administrative support (i.e., project office and project team members) were extended through February 28 on the supposition that this additional time was needed for final cost data accountability and program report documentation.

Jerry informed his boss, Frank Howard, the division head for project management, as to the problems with the bathtub period. Frank was the intermediary between Jerry and the general manager. Frank agreed with Jerry's approach to the problem and requested to be kept informed.

On September 15, Frank told Jerry that he wanted to “book” the management reserve of $125,000 as excess profit since it would influence his (Frank's) Christmas bonus. Frank and Jerry argued for a while, with Frank constantly saying, “Don't worry! You'll get your key people back. I'll see to that. But I want those uncommitted funds recorded as profit and the program closed out by November 1.”

Jerry was furious with Frank's lack of interest in maintaining the current organizational membership.

Case Study Questions:

Should Jerry go to the General Manager? Why or why not? Think back to what is expected of a project manager and the project charter.

Should the key people be supported on overhead? Why or why not?

If this were a cost-plus program, would you consider approaching the customer with your problem in hopes of relief? Why or why not?

If you were the customer of this cost-plus program, what would your response be for additional funds for the bathtub period, assuming cost overrun? Why or why not?

Would your previous answer change if the program had the money available as a result of being under budget? Why or why not?

How do you prevent this situation from recurring on all yearly follow-on contracts?

Solutions

Expert Solution

Yes, Jerry have to go to the General Manager. Jerry intimated his immediate division head for project management about the problems with the bathtub period as he was intermediary between Jerry and the general manager but the conflict arises between them. As Jerry needs to think in prior about the both perspective of the problem i.e. before intimation and after intimation. As the Jerry don’t have any fault so he needs to contact the General Manager as the solution to the problem was not found out. The project manager has the responsibility of the completion of the project on time, on demand and within allocated budget. If any short of problem arises then that has to be discussed with higher officials as it directly affects the project.

Yes, the key people be supported on overhead because it benefits the company over the period of time. Although the cost is more for retaining the employee for the bathtub period but it is not more than the benefits which the company gets after the completion of the project. The retention of good employee and getting back the well talented employees is harder to find.

If this were a cost-plus program, yes, I would consider approaching the customer with my problem in hopes of relief. The customers would invest on the project if they found out that the they get the handsome return on the investment. There is no harm in getting hopes from the customers as the risk are minimized here.

If you were the customer of this cost-plus program, my response be for additional funds for the bathtub period, assuming cost overrun was I would ensure the security of the investment. I may request for the detailed information about the project. I would be giving positive response if the information is clear and promising me.

Yes, my previous answer would be changed if the program had the money available as a result of being under budget because the risk associated with the project may be more. So, I may not get benefits which i would get over the period of time. In any case I would want to evaluate the potential payoff to the company before providing additional funds. However, I would be more forthcoming in providing funding if Park were generally fiscally responsible.

The risky situations may not be predicted in advanced. They are unpredicted. But with the help of proper risk management we may reduce it. However, we can inform to the Park of the 'projected' cash flow problem earlier in the project so that he could be better in allocating the funds for the bathtub period in the first place.


Related Solutions

The contract management process is comprised of three common phases. The 3 phases are the pre-award...
The contract management process is comprised of three common phases. The 3 phases are the pre-award phase, award phase and post-award phase. Of the three phases, is there one that is more important than the others?
Determine the exact simple interest on P 1,000,000 invested for the period from October 24, 1987 to January 7, 1990, if the rate of interest is 17%.
Simple InterestDetermine the exact simple interest on P 1,000,000 invested for the period from October 24, 1987 to January 7, 1990, if the rate of interest is 17%.
Question 3 On January 1, 2017, Sheffield Industries had stock outstanding as follows. 6% Cumulative preferred...
Question 3 On January 1, 2017, Sheffield Industries had stock outstanding as follows. 6% Cumulative preferred stock, $100 par value, issued and outstanding 9,700 shares $970,000 Common stock, $10 par value, issued and outstanding 203,000 shares 2,030,000 To acquire the net assets of three smaller companies, Sheffield authorized the issuance of an additional 163,200 common shares. The acquisitions took place as shown below. Date of Acquisition Shares Issued Company A April 1, 2017 49,200 Company B July 1, 2017 82,800...
In the 3-month period November 1, 2014, through January 31, 2015, Hess Corp. (HES) stock decreased...
In the 3-month period November 1, 2014, through January 31, 2015, Hess Corp. (HES) stock decreased from $80 to $64 per share, and Exxon Mobil (XOM) stock decreased from $96 to $80 per share. If you invested a total of $26,880 in these stocks at the beginning of November and sold them for $22,080 3 months later, how many shares of each stock did you buy? Hess Corp. (HES) stock  shares Exxon Mobil (XOM) stock
In the 3-month period November 1, 2014, through January 31, 2015, Hess Corp. (HES) stock decreased...
In the 3-month period November 1, 2014, through January 31, 2015, Hess Corp. (HES) stock decreased from $80 to $64 per share, and Exxon Mobil (XOM) stock decreased from $96 to $80 per share.† If you invested a total of $25,920 in these stocks at the beginning of November and sold them for $21,120 3 months later, how many shares of each stock did you buy?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT