Question

In: Finance

P10–14 Internal rate of return  For each of the projects shown in the following table, calculate the...

P10–14 Internal rate of return  For each of the projects shown in the following table, calculate the internal rate of return (IRR). Then indicate, for each project, the maximum cost of capital that the firm could have and still find the IRR acceptable. I DO NOT HAVE A FINANCIAL CALCULATOR OR I CANNOT USE EXCEL SPREADSHEETS; CAN YOU PLEASE BREAK IT DOWN ON HOW TO FIND THE IRR....THANKS IN ADVANCE

Project B

Project C

Initial investment (CF0)

−$490,000

−$20,000

Year (t)

Cash inflows (CFt)

1

   $150,000

     $7,500

2

     150,000

       7,500

3

     150,000

       7,500

4

     150,000

       7,500

5

       —

       7,500

  

Solutions

Expert Solution

Internal Rate of Return (IRR) for Project B

Step – 1, Firstly calculate NPV at a guessed discount Rate, Say 8% (R1)

Year

Annual Cash Flow ($)

Present Value factor at 8%

Present Value of Cash Flow ($)

1

1,50,000

0.925926

1,38,889

2

1,50,000

0.857339

1,28,601

3

1,50,000

0.793832

1,19,075

4

1,50,000

0.735030

1,10,254

TOTAL

496,819

Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment

= $496,819 - $490,000

= $6,819

Step – 2, NPV at 8% is positive, Calculate the NPV again at a higher discount rate, Say 9% (R2)

Year

Annual Cash Flow ($)

Present Value factor at 9%

Present Value of Cash Flow ($)

1

1,50,000

0.917431

1,37,615

2

1,50,000

0.841680

1,26,252

3

1,50,000

0.772183

1,15,828

4

1,50,000

0.708425

1,06,264

TOTAL

485,958

Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment

= $485,958 - $490,000

= -$4,042 (Negative NPV)

Therefore IRR = R1 + NPV1(R2-R1)

                                   NPV1-NPV2

= 0.08 + [$6,819 x (0.09 – 0.08)]

              $6,819 – (-$4,042)

= 0.08 + [$68.19 / $10,861]

= 0.08 + 0.0063

= 0.0863 or

= 8.63%

“Internal Rate of Return (IRR) for Project B = 8.63%”

Internal Rate of Return (IRR) for Project C

Step – 1, Firstly calculate NPV at a guessed discount Rate, Say 25% (R1)

Year

Annual Cash Flow ($)

Present Value factor at 25%

Present Value of Cash Flow ($)

1

7,500

0.800000

6,000

2

7,500

0.640000

4,800

3

7,500

0.512000

3,840

4

7,500

0.409600

3,072

5

7,500

0.327680

2,458

TOTAL

20,170

Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment

= $20,170 - $20,000

= $170

Step – 2, NPV at 25% is positive, Calculate the NPV again at a higher discount rate, Say 26% (R2)

Year

Annual Cash Flow ($)

Present Value factor at 26%

Present Value of Cash Flow ($)

1

7,500

0.793651

5,952

2

7,500

0.629882

4,724

3

7,500

0.499906

3,749

4

7,500

0.396751

2,976

5

7,500

0.314882

2,362

TOTAL

19,763

Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment

= $19,763 - $20,000

= -$237 (Negative NPV)

Therefore IRR = R1 + NPV1(R2-R1)

                                   NPV1-NPV2

= 0.25 + [$170 x (0.26 – 0.25)]

              $170 – (-$237)

= 0.25 + [$1.70 / $407]

= 0.25 + 0.0042

= 0.2542 or

= 25.42%

“Internal Rate of Return (IRR) for Project C = 25.42%”

NOTE    

The Formula for calculating the Present Value Factor is [1/(1 + r)n], Where “r” is the Discount/Interest Rate and “n” is the number of years.


Related Solutions

 For the project shown in the following​ table, LOADING... ​, calculate the internal rate of return...
 For the project shown in the following​ table, LOADING... ​, calculate the internal rate of return ​(IRR). Then​ indicate, for the​ project, the maximum cost of capital that the firm could have and still find the IRR acceptable. Initial investment ​(CF 0CF0​) ​$160 comma 000160,000 Copy to Clipboard + Open in Excel + Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 ​$45 comma 00045,000 2 ​$50 comma 00050,000 3 ​$45 comma 00045,000 4 ​$30 comma 00030,000 5 ​$35 comma 00035,000...
Calculate the internal rate of return on the following projects: Initial outlay of $50,000 with an...
Calculate the internal rate of return on the following projects: Initial outlay of $50,000 with an after-tax cash flow of $10,000 per year for eight years. Initial outlay of $600,000 with an after-tax cash flow of $120,000 per year for ten years. Initial outlay of $25,000 with an after-tax cash flow $11,500 per year for three years.
Calculate the Internal Rate of Return of each of the following potential investments and recommend whether...
Calculate the Internal Rate of Return of each of the following potential investments and recommend whether or not to include them in the upcoming capital budget given that the firm’s cost of capital is 14.5%. New Software: Initial Cost                        $25,000 Training Cost                    $12,000 Annual Cost Savings         $10,500 Useful Life                        6 Years Machine A or Machine B Note: The key word here is “or”. One or the other machine must be bought. So, the analysis should be based on the incremental...
Calculate the Internal Rate of Return of each of the following potential investments and recommend whether...
Calculate the Internal Rate of Return of each of the following potential investments and recommend whether or not to include them in the upcoming capital budget given that the firm’s cost of capital is 14.5%. New Software: Initial Cost                         $25,000 Training Cost                    $12,000 Annual Cost Savings        $10,500 Useful Life                        6 Years Machine A or Machine B Note: The key word here is “or”. One or the other machine must be bought. So, the analysis should be based on the incremental...
Billabong Tech uses the internal rate of return​ (IRR) to select projects. Calculate the IRR for...
Billabong Tech uses the internal rate of return​ (IRR) to select projects. Calculate the IRR for each of the following projects and recommend the best project based on this measure. Project​ T-Shirt requires an initial investment of ​$12,500 and generates cash inflows of ​$7,500 per year for 3 years. Project Board Shorts requires an initial investment of ​$18,333 and produces cash inflows of ​$10,000 per year for 4 years
Billabong Tech uses the internal rate of return​ (IRR) to select projects. Calculate the IRR for...
Billabong Tech uses the internal rate of return​ (IRR) to select projects. Calculate the IRR for each of the following projects and recommend the best project based on this measure. Project​ T-Shirt requires an initial investment of ​$16, 000 and generates cash inflows of ​$6,000 per year for 6 years. Project Board Shorts requires an initial investment of ​$30,667 and produces cash inflows of ​$11,000 per year for 7 years
Internal rate of return and modified internal rate of return. Quark Industries has three potential​ projects,...
Internal rate of return and modified internal rate of return. Quark Industries has three potential​ projects, all with an initial cost of ​$1,600,000. Given the discount rate and the future cash flow of each project in the following​ table,  Cash Flow   Project M Project N Project O   Year 1   $400,000   $500,000 $900,000   Year 2   ​$400,000   ​$500,000   $700,000   Year 3   $400,000 $500,000 $500,000   Year 4   $400,000 $500,000 $300,000   Year 5 $400,000   $500,000 $100,000 Discount rate 9​% 14%   17%
Internal rate of return and modified internal rate of return. Lepton Industries has three potential​ projects,...
Internal rate of return and modified internal rate of return. Lepton Industries has three potential​ projects, all with an initial cost of ​$1,700,000. Given the discount rate and the future cash flows of each​ project, what are the IRRs and MIRRs of the three projects for Lepton​ Industries?   Cash Flow Project Q Project R Project S   Year 1 ​ $400,000 ​$600,000 ​$900,000   Year 2 ​$400,000 ​$600,000 ​$700,000   Year 3 ​$400,000 ​$600,000 ​$500,000   Year 4 ​$400,000 ​$600,000 ​$300,000   Year 5 ​$400,000...
\\ Compute the internal rate of return for the cash flows of the following two projects....
\\ Compute the internal rate of return for the cash flows of the following two projects. (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)      Year Project A Project B   0 –$ 6,300 –$ 3,900     1 2,400 1,400     2 3,200 2,500     3 2,000 1,600       
For the following projects, compute the net present value, internal rate of return, and the profitability...
For the following projects, compute the net present value, internal rate of return, and the profitability index. Assume the required rate of return is 17% compounded annually. Project Initial Investment Cashflow at time 1 Cashflow at time 2 A 116,000 69,000 89,000 B 1,530 4,100 100 C 260,000 134,000 160,000 D 910 350 3,400 Assume no capital constrain exists and that the projects are not mutually exclusive. What is the net present value of Project A? What is the internal...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT