Question

In: Finance

Internal rate of return and modified internal rate of return. Quark Industries has three potential​ projects,...

Internal rate of return and modified internal rate of return.

Quark Industries has three potential​ projects, all with an initial cost of ​$1,600,000.

Given the discount rate and the future cash flow of each project in the following​ table,

 Cash Flow   Project M Project N Project O

  Year 1   $400,000   $500,000 $900,000

  Year 2   ​$400,000   ​$500,000   $700,000

  Year 3   $400,000 $500,000 $500,000

  Year 4   $400,000 $500,000 $300,000

  Year 5 $400,000   $500,000 $100,000

Discount rate 9​% 14%   17%

Solutions

Expert Solution

Computation of IRR using trial and error method:

Project M:

Let’s compute NPV of project M using discount rate of 7 %:

Year

Cash Flow (CM)

PV Factor Computation

PV Factor @ 7 % (F)

PV (CM x F)

0

-$1,600,000

1/ (1+0.07) ^0

1

-$1,600,000

1

$400,000

1/ (1+0.07) ^1

0.934579439

$373,831.77570

2

$400,000

1/ (1+0.07) ^2

0.873438728

$349,375.49131

3

$400,000

1/ (1+0.07) ^3

0.816297877

$326,519.15076

4

$400,000

1/ (1+0.07) ^4

0.762895212

$305,158.08482

5

$400,000

1/ (1+0.07) ^5

0.712986179

$285,194.47179

NPV M1

$40,078.97438

As NPV is positive let’s compute NPV at discount rate of 8 %.

Year

Cash Flow (CM)

PV Factor Computation

PV Factor @ 8 % (F)

PV (CM x F)

0

-$1,600,000

1/ (1+0.08) ^0

1

-$1,600,000

1

$400,000

1/ (1+0.08) ^1

0.925925926

$370,370.37037

2

$400,000

1/ (1+0.08) ^2

0.85733882

$342,935.52812

3

$400,000

1/ (1+0.08) ^3

0.793832241

$317,532.89641

4

$400,000

1/ (1+0.08) ^4

0.735029853

$294,011.94112

5

$400,000

1/ (1+0.08) ^5

0.680583197

$272,233.27881

NPV M2

-$2,915.985169

IRR M = R1 + [NPV M1 x (R2 – R1)/ (NPV M1 – NPV M2)]

     = 7 % + [$40,078.97438 x (8 % - 7 %)]/ [$40,078.97438 – (-$2,915.985169)]

     = 7 % + ($40,078.97438 x 1 %)/ ($40,078.97438 + $2,915.985169)

    = 7 % + ($400.7897438 / $42,994.95955)

     = 7 % + 0.009321784

      = 7 % + 0.9321784 %

      = 7.93 %

Project N:

Let’s compute NPV of project N using discount rate of 16 %:

Year

Cash Flow (CN)

PV Factor Computation

PV Factor @ 16 % (F)

PV (CN x F)

0

-$1,600,000

1/ (1+0.16) ^0

1

-$1,600,000

1

$500,000

1/ (1+0.16) ^1

0.8620689655172

431034.48276

2

$500,000

1/ (1+0.16) ^2

0.7431629013080

371581.45065

3

$500,000

1/ (1+0.16) ^3

0.6406576735414

320328.83677

4

$500,000

1/ (1+0.16) ^4

0.5522910978805

276145.54894

5

$500,000

1/ (1+0.16) ^5

0.4761130154142

238056.50771

NPV N1

$37,146.82683

As NPV is positive let’s compute NPV at discount rate of 17 %.

Year

Cash Flow (CN)

PV Factor Computation

PV Factor @ 17 % (F)

PV (CN x F)

0

-$1,600,000

1/ (1+0.17) ^0

1

-$1,600,000

1

$500,000

1/ (1+0.17) ^1

0.93457943925234

427,350.42735

2

$500,000

1/ (1+0.17) ^2

0.87343872827321

365,256.77551

3

$500,000

1/ (1+0.17) ^3

0.81629787689085

312,185.27822

4

$500,000

1/ (1+0.17) ^4

0.76289521204753

266,825.02412

5

$500,000

1/ (1+0.17) ^5

0.71298617948367

228,055.57617

NPV N2

-$326.91864

IRR N = R1 + [NPV N1 x (R2 – R1)/ (NPV N1 – NPV N2)]

     = 16 % + [$37,146.82683 x (17 % - 16 %)]/ [$37,146.82683 – (-$326.91864)]

     = 16% + ($37,146.82683 x 1 %)/ ($37,146.82683+ $326.91864)

    = 16 % + ($371.4682683/ $37,473.74547)

      = 16 % + 0.009912761

      = 16% + 0.9912761%

      = 16.93 %

Project O:

Let’s compute NPV of project O using discount rate of 24 %:

Year

Cash Flow (CO)

PV Factor Computation

PV Factor @ 24 % (F)

PV (CO x F)

0

-$1,600,000

1/ (1+0.24) ^0

1

-$1,600,000.00

1

900,000

1/ (1+0.24) ^1

0.8064516129032

725,806.45161

2

700,000

1/ (1+0.24) ^2

0.6503642039542

455,254.94277

3

500,000

1/ (1+0.24) ^3

0.5244872612534

262,243.63063

4

300,000

1/ (1+0.24) ^4

0.4229735977850

126,892.07934

5

100,000

1/ (1+0.24) ^5

0.3411077401492

34,110.77401

NPV O1

$4,307.87836

As NPV is positive let’s compute NPV at discount rate of 25 %.

Year

Cash Flow (CO)

PV Factor Computation

PV Factor @ 25 % (F)

PV (CO x F)

0

-$1,600,000

1/ (1+0.25) ^0

1

-$1,600,000

1

900,000

1/ (1+0.25) ^1

0.800000

720,000

2

700,000

1/ (1+0.25) ^2

0.640000

448,000

3

500,000

1/ (1+0.25) ^3

0.512000

256,000

4

300,000

1/ (1+0.25) ^4

0.409600

122,880

5

100,000

1/ (1+0.25) ^5

0.327680

32,768

NPV O2

-$20,352

IRR O = R1 + [NPV O1 x (R2 – R1)/ (NPV O1 – NPV O2)]

     = 24 % + [$4,307.87836 x (25 % - 24 %)]/ [$4,307.87836– (-$20,352)]

     = 24 % + ($4,307.87836 x 1 %)/ ($4,307.87836 + $20,352)

    = 24 % + ($43.0787836/ $24659.87836)

      = 24 % + 0.001746918

      = 24 % + 0.1746918 %

      = 24.17 %

Computation of MIRR:

MIRR = n√ (Future value of positive cash flow/Present value of negative cash flow) – 1

Project M:           

Year

Cash Flow

(CM)

Computation of FV Factor

FV Factor @ 9 % (F)

FV

(CM x F)

1

$400,000

(1+0.09) ^4

1.41158161

564632.644

2

$400,000

(1+0.09) ^3

1.295029

518011.600

3

$400,000

(1+0.09) ^2

1.1881

475240.000

4

$400,000

(1+0.09) ^1

1.09

436000.000

5

$400,000

(1+0.09) ^0

Related Solutions

Internal rate of return and modified internal rate of return. Lepton Industries has three potential​ projects,...
Internal rate of return and modified internal rate of return. Lepton Industries has three potential​ projects, all with an initial cost of ​$1,700,000. Given the discount rate and the future cash flows of each​ project, what are the IRRs and MIRRs of the three projects for Lepton​ Industries?   Cash Flow Project Q Project R Project S   Year 1 ​ $400,000 ​$600,000 ​$900,000   Year 2 ​$400,000 ​$600,000 ​$700,000   Year 3 ​$400,000 ​$600,000 ​$500,000   Year 4 ​$400,000 ​$600,000 ​$300,000   Year 5 ​$400,000...
Net present value. Quark Industries has three potential​ projects, all with an initial cost of $1,800,000....
Net present value. Quark Industries has three potential​ projects, all with an initial cost of $1,800,000. The capital budget for the year will allow Quark to accept only one of the three projects. Given the discount rate and the future cash flow of each​ project, determine which project Quark should accept. Cash Flow   Project M   Project N   Project O Year 1 $500,000   $600,000   $1,000,000 Year 2 $500,000   $600,000   $800,000 Year 3 $500,000   $600,000   $600,000 Year 4 $500,000   $600,000   $400,000 Year...
Net present value. Quark Industries has three potential​ projects, all with an initial cost of ​$1...
Net present value. Quark Industries has three potential​ projects, all with an initial cost of ​$1 comma 900 comma 0001,900,000. The capital budget for the year will allow Quark to accept only one of the three projects. Given the discount rate and the future cash flow of each​ project, determine which project Quark should accept.   Cash Flow Project M Project N Project O   Year 1 ​ $500 comma 000500,000 ​$600 comma 000600,000 ​$1 comma 000 comma 0001,000,000   Year 2 ​$500...
Net present value. Quark Industries has three potential​ projects, all with an initial cost of ​$1,700,000....
Net present value. Quark Industries has three potential​ projects, all with an initial cost of ​$1,700,000. The capital budget for the year will allow Quark to accept only one of the three projects. Given the discount rate and the future cash flow of each​ project, determine which project Quark should accept. Cash Flow Project M Project N Project O    Year 1 ​ $400,000 ​$600,000 ​$900,000    Year 2 ​$400,000 ​$600,000 ​$700,000    Year 3 ​$400,000 ​$600,000 ​$500,000    Year 4 ​$400,000 ​$600,000 ​$300,000   ...
Tall Trees, Inc. is using the modified internal rate of return (MIRR) when evaluating projects. The...
Tall Trees, Inc. is using the modified internal rate of return (MIRR) when evaluating projects. The company is able to reinvest cash flows received from the project at an annual rate of 12.04 percent. What is the MIRR of a project if the initial costs are $1,680,000 and the project life is estimated as 7 years? The project will produce the same after-tax cash inflows of 474,700 per year at the end of the year. Round the answer to two...
Tall Trees, Inc. is using the modified internal rate of return (MIRR) when evaluating projects. The...
Tall Trees, Inc. is using the modified internal rate of return (MIRR) when evaluating projects. The company is able to reinvest cash flows received from the project at an annual rate of 13.42 percent. What is the MIRR of a project if the initial costs are $1,476,100 and the project life is estimated at 9 years? The project will produce the same after-tax cash inflows of $627,700 per year at the end of the year. Round the answer to two...
Tall Trees, Inc. is using the modified internal rate of return (MIRR) when evaluating projects. The...
Tall Trees, Inc. is using the modified internal rate of return (MIRR) when evaluating projects. The company is able to reinvest cash flows received from the project at an annual rate of 12.40 percent. What is the MIRR of a project if the initial costs are $1,386,400 and the project life is estimated as 9 years? The project will produce the same after-tax cash inflows of 476,200 per year at the end of the year.
Which of the following statements is not correct? a. The modified internal rate of return is...
Which of the following statements is not correct? a. The modified internal rate of return is similar to the realized compound yield method used with bonds. b. The modified internal rate of return attempts to correct the reinvestment rate assumption implicit with the internal rate of return method. c. The modified internal rate of return takes the outflows back to the present time and the inflows to the terminus of the project. d. The modified internal rate of return solves...
Describe and explain the significance of each of the following: payback period, internal rate of return (IRR), modified internal rate of return (MIRR)
  Describe and explain the significance of each of the following: payback period, internal rate of return (IRR), modified internal rate of return (MIRR), net present value (NPV), and profitability index (PI). Explain. Provide examples for better clarity. Discuss the notions of conventional and nonconventional cash flows in capital budgeting. Which investment evaluation criteria would you use for unconventional cash flows and why? Provide a fictitious unconventional cash flow example and apply the payback period, NPV, IRR, MIRR, and PI...
Describe the modified internal rate of return (MIRR) as a method for deciding the desirability of...
Describe the modified internal rate of return (MIRR) as a method for deciding the desirability of a capital budgeting project. What are MIRR's strengths and weaknesses?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT