In: Finance
Internal rate of return and modified internal rate of return.
Quark Industries has three potential projects, all with an initial cost of $1,600,000.
Given the discount rate and the future cash flow of each project in the following table,
Cash Flow Project M Project N Project O
Year 1 $400,000 $500,000 $900,000
Year 2 $400,000 $500,000 $700,000
Year 3 $400,000 $500,000 $500,000
Year 4 $400,000 $500,000 $300,000
Year 5 $400,000 $500,000 $100,000
Discount rate 9% 14% 17%
Computation of IRR using trial and error method:
Project M:
Let’s compute NPV of project M using discount rate of 7 %:
Year |
Cash Flow (CM) |
PV Factor Computation |
PV Factor @ 7 % (F) |
PV (CM x F) |
0 |
-$1,600,000 |
1/ (1+0.07) ^0 |
1 |
-$1,600,000 |
1 |
$400,000 |
1/ (1+0.07) ^1 |
0.934579439 |
$373,831.77570 |
2 |
$400,000 |
1/ (1+0.07) ^2 |
0.873438728 |
$349,375.49131 |
3 |
$400,000 |
1/ (1+0.07) ^3 |
0.816297877 |
$326,519.15076 |
4 |
$400,000 |
1/ (1+0.07) ^4 |
0.762895212 |
$305,158.08482 |
5 |
$400,000 |
1/ (1+0.07) ^5 |
0.712986179 |
$285,194.47179 |
NPV M1 |
$40,078.97438 |
As NPV is positive let’s compute NPV at discount rate of 8 %.
Year |
Cash Flow (CM) |
PV Factor Computation |
PV Factor @ 8 % (F) |
PV (CM x F) |
0 |
-$1,600,000 |
1/ (1+0.08) ^0 |
1 |
-$1,600,000 |
1 |
$400,000 |
1/ (1+0.08) ^1 |
0.925925926 |
$370,370.37037 |
2 |
$400,000 |
1/ (1+0.08) ^2 |
0.85733882 |
$342,935.52812 |
3 |
$400,000 |
1/ (1+0.08) ^3 |
0.793832241 |
$317,532.89641 |
4 |
$400,000 |
1/ (1+0.08) ^4 |
0.735029853 |
$294,011.94112 |
5 |
$400,000 |
1/ (1+0.08) ^5 |
0.680583197 |
$272,233.27881 |
NPV M2 |
-$2,915.985169 |
IRR M = R1 + [NPV M1 x (R2 – R1)/ (NPV M1 – NPV M2)]
= 7 % + [$40,078.97438 x (8 % - 7 %)]/ [$40,078.97438 – (-$2,915.985169)]
= 7 % + ($40,078.97438 x 1 %)/ ($40,078.97438 + $2,915.985169)
= 7 % + ($400.7897438 / $42,994.95955)
= 7 % + 0.009321784
= 7 % + 0.9321784 %
= 7.93 %
Project N:
Let’s compute NPV of project N using discount rate of 16 %:
Year |
Cash Flow (CN) |
PV Factor Computation |
PV Factor @ 16 % (F) |
PV (CN x F) |
0 |
-$1,600,000 |
1/ (1+0.16) ^0 |
1 |
-$1,600,000 |
1 |
$500,000 |
1/ (1+0.16) ^1 |
0.8620689655172 |
431034.48276 |
2 |
$500,000 |
1/ (1+0.16) ^2 |
0.7431629013080 |
371581.45065 |
3 |
$500,000 |
1/ (1+0.16) ^3 |
0.6406576735414 |
320328.83677 |
4 |
$500,000 |
1/ (1+0.16) ^4 |
0.5522910978805 |
276145.54894 |
5 |
$500,000 |
1/ (1+0.16) ^5 |
0.4761130154142 |
238056.50771 |
NPV N1 |
$37,146.82683 |
As NPV is positive let’s compute NPV at discount rate of 17 %.
Year |
Cash Flow (CN) |
PV Factor Computation |
PV Factor @ 17 % (F) |
PV (CN x F) |
0 |
-$1,600,000 |
1/ (1+0.17) ^0 |
1 |
-$1,600,000 |
1 |
$500,000 |
1/ (1+0.17) ^1 |
0.93457943925234 |
427,350.42735 |
2 |
$500,000 |
1/ (1+0.17) ^2 |
0.87343872827321 |
365,256.77551 |
3 |
$500,000 |
1/ (1+0.17) ^3 |
0.81629787689085 |
312,185.27822 |
4 |
$500,000 |
1/ (1+0.17) ^4 |
0.76289521204753 |
266,825.02412 |
5 |
$500,000 |
1/ (1+0.17) ^5 |
0.71298617948367 |
228,055.57617 |
NPV N2 |
-$326.91864 |
IRR N = R1 + [NPV N1 x (R2 – R1)/ (NPV N1 – NPV N2)]
= 16 % + [$37,146.82683 x (17 % - 16 %)]/ [$37,146.82683 – (-$326.91864)]
= 16% + ($37,146.82683 x 1 %)/ ($37,146.82683+ $326.91864)
= 16 % + ($371.4682683/ $37,473.74547)
= 16 % + 0.009912761
= 16% + 0.9912761%
= 16.93 %
Project O:
Let’s compute NPV of project O using discount rate of 24 %:
Year |
Cash Flow (CO) |
PV Factor Computation |
PV Factor @ 24 % (F) |
PV (CO x F) |
0 |
-$1,600,000 |
1/ (1+0.24) ^0 |
1 |
-$1,600,000.00 |
1 |
900,000 |
1/ (1+0.24) ^1 |
0.8064516129032 |
725,806.45161 |
2 |
700,000 |
1/ (1+0.24) ^2 |
0.6503642039542 |
455,254.94277 |
3 |
500,000 |
1/ (1+0.24) ^3 |
0.5244872612534 |
262,243.63063 |
4 |
300,000 |
1/ (1+0.24) ^4 |
0.4229735977850 |
126,892.07934 |
5 |
100,000 |
1/ (1+0.24) ^5 |
0.3411077401492 |
34,110.77401 |
NPV O1 |
$4,307.87836 |
As NPV is positive let’s compute NPV at discount rate of 25 %.
Year |
Cash Flow (CO) |
PV Factor Computation |
PV Factor @ 25 % (F) |
PV (CO x F) |
0 |
-$1,600,000 |
1/ (1+0.25) ^0 |
1 |
-$1,600,000 |
1 |
900,000 |
1/ (1+0.25) ^1 |
0.800000 |
720,000 |
2 |
700,000 |
1/ (1+0.25) ^2 |
0.640000 |
448,000 |
3 |
500,000 |
1/ (1+0.25) ^3 |
0.512000 |
256,000 |
4 |
300,000 |
1/ (1+0.25) ^4 |
0.409600 |
122,880 |
5 |
100,000 |
1/ (1+0.25) ^5 |
0.327680 |
32,768 |
NPV O2 |
-$20,352 |
IRR O = R1 + [NPV O1 x (R2 – R1)/ (NPV O1 – NPV O2)]
= 24 % + [$4,307.87836 x (25 % - 24 %)]/ [$4,307.87836– (-$20,352)]
= 24 % + ($4,307.87836 x 1 %)/ ($4,307.87836 + $20,352)
= 24 % + ($43.0787836/ $24659.87836)
= 24 % + 0.001746918
= 24 % + 0.1746918 %
= 24.17 %
Computation of MIRR:
MIRR = n√ (Future value of positive cash flow/Present value of negative cash flow) – 1
Project M:
Year |
Cash Flow (CM) |
Computation of FV Factor |
FV Factor @ 9 % (F) |
FV (CM x F) |
1 |
$400,000 |
(1+0.09) ^4 |
1.41158161 |
564632.644 |
2 |
$400,000 |
(1+0.09) ^3 |
1.295029 |
518011.600 |
3 |
$400,000 |
(1+0.09) ^2 |
1.1881 |
475240.000 |
4 |
$400,000 |
(1+0.09) ^1 |
1.09 |
436000.000 |
5 |
$400,000 |
(1+0.09) ^0 |
Related SolutionsInternal rate of return and modified internal rate of return. Lepton Industries has three potential projects,...Internal rate of return and modified internal rate of
return. Lepton Industries has three potential projects,
all with an initial cost of $1,700,000. Given the discount rate
and the future cash flows of each project, what are the IRRs and
MIRRs of the three projects for Lepton Industries?
Cash Flow
Project Q
Project R
Project S
Year 1
$400,000
$600,000
$900,000
Year 2
$400,000
$600,000
$700,000
Year 3
$400,000
$600,000
$500,000
Year 4
$400,000
$600,000
$300,000
Year 5
$400,000...
Net present value. Quark Industries has three potential projects, all with an initial cost of $1,800,000....Net present value. Quark Industries has three potential
projects, all with an initial cost of $1,800,000. The capital
budget for the year will allow Quark to accept only one of the
three projects. Given the discount rate and the future cash flow of
each project, determine which project Quark should accept.
Cash Flow Project M Project
N Project O
Year 1 $500,000 $600,000 $1,000,000
Year 2 $500,000 $600,000 $800,000
Year 3 $500,000 $600,000 $600,000
Year 4 $500,000 $600,000 $400,000
Year...
Net present value. Quark Industries has three potential projects, all with an initial cost of $1...Net present
value.
Quark Industries has three potential projects, all with an
initial cost of
$1 comma 900 comma 0001,900,000.
The capital budget for the year will allow Quark to accept only
one of the three projects. Given the discount rate and the future
cash flow of each project, determine which project Quark should
accept.
Cash Flow
Project M
Project N
Project O
Year 1
$500 comma 000500,000
$600 comma 000600,000
$1 comma 000 comma 0001,000,000
Year 2
$500...
Net present value. Quark Industries has three potential projects, all with an initial cost of $1,700,000....Net present value. Quark Industries has three potential
projects, all with an initial cost of $1,700,000. The capital
budget for the year will allow Quark to accept only one of the
three projects. Given the discount rate and the future cash flow of
each project, determine which project Quark should accept.
Cash Flow Project M Project N Project O
Year 1 $400,000 $600,000 $900,000
Year 2 $400,000 $600,000 $700,000
Year 3 $400,000 $600,000 $500,000
Year 4 $400,000 $600,000 $300,000 ...
the difference between the internal rate of return method and the modified internalthe difference between the internal rate of return
method and the modified internal
Tall Trees, Inc. is using the modified internal rate of return (MIRR) when evaluating projects. The...Tall Trees, Inc. is using the modified internal rate of return
(MIRR) when evaluating projects. The company is able to reinvest
cash flows received from the project at an annual rate of 12.04
percent. What is the MIRR of a project if the initial costs are
$1,680,000 and the project life is estimated as 7 years? The
project will produce the same after-tax cash inflows of 474,700 per
year at the end of the year. Round the answer to two...
Tall Trees, Inc. is using the modified internal rate of return (MIRR) when evaluating projects. The...Tall Trees, Inc. is using the modified internal rate of return
(MIRR) when evaluating projects. The company is able to reinvest
cash flows received from the project at an annual rate of 13.42
percent. What is the MIRR of a project if the initial costs are
$1,476,100 and the project life is estimated at 9 years? The
project will produce the same after-tax cash inflows of $627,700
per year at the end of the year.
Round the answer to two...
Tall Trees, Inc. is using the modified internal rate of return (MIRR) when evaluating projects. The...Tall Trees, Inc. is using the modified internal rate of return
(MIRR) when evaluating projects. The company is able to reinvest
cash flows received from the project at an annual rate of 12.40
percent. What is the MIRR of a project if the initial costs are
$1,386,400 and the project life is estimated as 9 years? The
project will produce the same after-tax cash inflows of 476,200 per
year at the end of the year.
Which of the following statements is not correct? a. The modified internal rate of return is...Which of the following statements is
not correct?
a. The modified internal rate of return is similar to the
realized compound yield method used with bonds.
b. The modified internal rate of return attempts to correct the
reinvestment rate assumption implicit with the internal rate of
return method.
c. The modified internal rate of return takes the outflows back
to the present time and the inflows to the terminus of the
project.
d. The modified internal rate of return solves...
Describe and explain the significance of each of the following: payback period, internal rate of return (IRR), modified internal rate of return (MIRR)
Describe and explain the significance of each of the following: payback period, internal rate of return (IRR), modified internal rate of return (MIRR), net present value (NPV), and profitability index (PI). Explain. Provide examples for better clarity.
Discuss the notions of conventional and nonconventional cash flows in capital budgeting. Which investment evaluation criteria would you use for unconventional cash flows and why? Provide a fictitious unconventional cash flow example and apply the payback period, NPV, IRR, MIRR, and PI...
ADVERTISEMENT
ADVERTISEMENT
Latest Questions
ADVERTISEMENT
|