Question

In: Electrical Engineering

I'm working on a project where I need to design a transmission line tap for a...

I'm working on a project where I need to design a transmission line tap for a station generator. The parameters include sizing three switches for the tap where at least one is a loop break switch. From where to start? What kind of calculations are needed to size the switches? What are those switches?

Solutions

Expert Solution

7. Calculate Operating Conditions of the Motors
If the motors are operating at 12 kV, this represents 12 kV/13.8 kV = 0.87 per-unit voltage. At unity power factor, the load is given as three-quarters or 0.75 p.u.

Thus, expressed in per unit, the combined motor current is obtained by using the equation:
Iper unit = per-unit power/per-unit voltage = 0.75/0.87 = 0.862 ?0° p.u.

8. Calculate the Generator Terminal Voltage
The voltage at the generator terminals is:

VG = Vmotor + the voltage drop through transformers and transmission line
VG = 0.87?0° + 0.862 ?0°(j0.101 + j0.313 + j0.101)
VG = 0.87 + j0.444 = 0.977 ?27.03° p.u.
In order to obtain the actual voltage, multiply the per-unit voltage by the base voltage at the generator. Thus,

VG = (0.977 ?27.03°) (13.8 kV) = 13.48 ?27.03° kV

Single line diagram
This technical article explains how to calculate and draw a single line diagram of the three-phase, 60-Hz system power system with generators, motors, transformers and lines. The following components comprise a simplified version of a power system, listed in sequential physical order from the generator location to the load:

Two steam-electric generators, each at 13.2 kV
Two step-up transformers, 13.2/66 kV
Sending-end, high-voltage bus at 66 kV
One long transmission line at 66 kV
Receiving-end bus at 66 kV
A second 66 kV transmission line with a center-tap bus
Step-down transformer at receiving-end bus, 66/12 kV, supplying four 12 kV motors in parallel and
A step-down transformer, 66/7.2 kV, off the center-tap bus, supplying a 7.2 kV motor

Calculation Procedure
1. Identify the Appropriate Symbols

2. Draw the Required System
The system described in the problem is shown in Figure 2. The oil circuit breakers are added at the appropriate points for proper isolation of equipment.

Related Calculations
It is the general procedure to use single line diagrams for representing three-phase systems. When analysis is done using symmetrical components, different diagrams may be drawn that will represent the electric circuitry for positive, negative, and zero-sequence components.

Additionally, it is often necessary to identify the grounding connection, or whether the device is wye- or delta-connected.
This type of notation is shown in Figure 3.


Per-unit method of solving of 3-phase problems
For the system shown in Figure 4, draw the electric circuit or reactance diagram, with all reactances marked in per-unit (p.u.) values, and find the generator terminal voltage assuming both motors operating at 12 kV, three-quarters load, and unity power factor.
Generator Transformers
(each) Motor A Motor B Transmission
Line
13.8kV 25,000 kVA 15,000 kVA 10,000 kVA –
25,000 kVA 3-phase 13.2/69 kV 13.0 kV 13.0 kV –
X” = 15 percent XL = 15 percent X” = 15 percent X” = 15 percent X = 65 ?

Calculation Procedure in 8 steps
1. Establish Base Voltage through the System
By observation of the magnitude of the components in the system, a base value of apparent power S is chosen. It should be of the general magnitude of the components, and the choice is arbitrary. In this problem, 25,000 kVA is chosen as the base S, and simultaneously, at the generator end 13.8 kV is selected as a base voltage Vbase.

The base voltage of the transmission line is then determined by the turns ratio of the connecting transformer:
(13.8 kV)(69 kV / 13.2 kV) = 72.136 kV
The base voltage of the motors is determined likewise but with the 72.136 kV value, thus:
(72.136 kV)(13.2 kV / 69 kV) = 13.8 kV

The selected base S value remains constant throughout the system, but the base voltage is 13.8 kV at the generator and at the motors, and 72.136 kV on the transmission line.


2. Calculate the Generator Reactance
No calculation is necessary for correcting the value of the generator reactance because it is given as 0.15 p.u. (15 percent), based on 25,000 kVA and 13.8 kV. If a different S base were used in this problem, then a correction would be necessary as shown for the transmission line, electric motors, and power transformers.


3. Calculate the Transformer Reactance
It is necessary to make a correction when the transformer nameplate reactance is used because the calculated operation is at a different voltage, 13.8 kV / 72.136 kV instead of 13.2 kV / 69 kV.

Use the equation for correction: per-unit reactance:
(nameplate per-unit reactance) (base kVA/nameplate kVA) (nameplate kV/base kV)2 =
(0.11) (25,000/25,000) (13.2/13.8)2 = 0.101 p.u.

This applies to each transformer.


4. Calculate the Transmission-Line Reactance
Use the equation:

Xper unit = (ohms reactance)(base kVA)/(1000)(base kV)2 =
Xper unit = (65) (25,000)/(1000)(72.1)2 = 0.313 p.u.

5. Calculate the Reactance of the Motors
Corrections need to be made in the nameplate ratings of both motors because of differences of ratings in kVA and kV as compared with those selected for calculations in this problem. Use the correcting equation from Step 3, above.

For motor A:
X”A = (0.15 p.u.) (25,000 kVA / 15,000 kVA) (13.0 kV / 13.8 kV)2 = 0.222 p.u.
For motor B:
X”B = (0.15 p.u.)(25,000 kVA /10,000 kVA)(13.0 kV / 13.8 kV)2 = 0.333 p.u.


6. Draw the Reactance Diagram
The completed reactance diagram is shown in Figure 5:


Related Solutions

I'm working in Java and am working on a project where I need to find an...
I'm working in Java and am working on a project where I need to find an average. The catch is that for some of the values there is no data because they will be entered at a later date. I have variables assigned so that for each entry if there is an input I'll have it say _____available = 1, otherwise the variable will equal 0. I'll use an example to make this more clear. Let's say I am trying...
I'm working on setting up a final project for Statistics and I wanted to make sure...
I'm working on setting up a final project for Statistics and I wanted to make sure I am choosing the right test for my hypotheses. Are my test choices correct? Hypotheses I hypothesize that the difference in the respondent’s physical effort at work, and how difficult it is for the respondent to take time off, has an impact on the respondent’s general health. Statistical Test Used: ANOVA I hypothesize that black men with less than college education are less likely...
i have a project where i would like to make organic chicken to look green. I'm...
i have a project where i would like to make organic chicken to look green. I'm looking for a technology that can do that. Also I'm searching for high level milestones for the project. Any ideas to help me out for the project?
I'm working on a project on bungee jump. Including air resistance, Using Principle of Dynamics, I...
I'm working on a project on bungee jump. Including air resistance, Using Principle of Dynamics, I need to analyse the Bungee Jump (Using work and Energy of the spring cord, uniform acceleration formula, etc) I'm looking for maximum height of the bounce, energy, forces of horizontal and vertical axis, velocity, acceleration and time etc Please Include free body diagrams, calculations, assumptions, conclusion too. Thank you.
How do I write this method correctly? What Ihave is a Java project assignment where I'm...
How do I write this method correctly? What Ihave is a Java project assignment where I'm supposed to create a Roshambo game. One of the classes that the project is supposed to have is a class called "RoshamboApp that let the user play 1 of 2 AI opponents, a "Bart" class, and a "Lisa" class. The instructions say "Create a class names RoshamboApp that allows player1 to play Bart or Lisa as shown in the console output. Rock should beat...
I am working on a project where I have to create my own organization (stem cell...
I am working on a project where I have to create my own organization (stem cell research) I need to go further in depth about the program or organization in terms of describing the program implementation and the project evaluation...
i need a scenario for factorial design
i need a scenario for factorial design
I need a Literature Reviews With References About ( CNC Shield ) Integrated manufacturing project Design...
I need a Literature Reviews With References About ( CNC Shield ) Integrated manufacturing project Design and Fabrication of Mini CNC Machine
Hi, i'm working on the lab report for Iodometric determination of Cu in Brass and i...
Hi, i'm working on the lab report for Iodometric determination of Cu in Brass and i need help with these questions. I greatly appreciate your help. Info: This experiment has two parts: standardization of the thiosulfate solution, and assay of the copper. In the standardization of the thiosulfate solution, a known amount of iodine is created from KIO3 and excess iodide, then titrated with the thiosulfate. In the copper assay, iodine is formed from the reaction between copper and excess...
I need a reply for this comment: "In a perfect world if I was working for...
I need a reply for this comment: "In a perfect world if I was working for a local hospital or doctors office, I believe that the hospital/office would need to make and keep their employees happy. This can be with incentives and good benefits. However, a main reason that I would keep a position is the leadership of co-workers, management, and the doctors. This would make work pleasant and would flow into employees working better with customers and patients. The...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT