In: Operations Management
Project Monitoring and Control Process Plan:
You have a Project Budget for building a five-bedroom house in
Ashburn, VA. Assume that your building project is two months behind
and has a $100,000.00 cost overrun. This should not be a surprise
to you because of the monitoring processes. Identify and discuss
some of the monitoring processes that could have alerted you of the
schedule and cost problems. What are some of the controlling steps
you would take to bring both the schedule and the cost back on
track? Be sure to justify your answers. . Your Project Monitoring
and Control Process Plan should be at least two pages including a
summarization and conclusion page. If necessary, include data from
the Project Budget and Project Schedule in the table shown below to
support your schedule and cost problems.
Unit 5 Project: | ||||
Activity Description | Start Date | End Date | Days to complete | Est $ |
Architectural Design | 5/1/2018 | 5/15/2018 | 14 | 50,000 |
Procurement of machinery | 5/15/2018 | 5/30/2018 | 15 | 60,000 |
Hiring Labor | 5/31/2018 | 6/10/2018 | 10 | 120,000 |
Work and Environmental Permits | 7/27/2018 | 8/6/2018 | 10 | 25,000 |
Site Security | 8/18/2018 | 4/30/2020 | 731 | 20,000 |
Concrete | 8/18/2018 | 8/31/2018 | 15 | 80,000 |
Lumber Procurement | 9/1/2018 | 9/11/2018 | 10 | 80,000 |
Material Storage | 9/1/2018 | 4/30/2020 | 637 | 10,000 |
Scaffolding Erection | 9/12/2018 | 9/17/2018 | 5 | 25,000 |
Framing | 9/15/2018 | 1/13/2019 | 120 | 130,000 |
Roofing | 1/14/2019 | 2/13/2019 | 30 | 40,000 |
Plumbing | 2/14/2019 | 3/17/2019 | 30 | 30,000 |
Electrical | 3/18/2019 | 4/17/2019 | 30 | 30,000 |
HVAC | 4/18/2019 | 6/2/2019 | 45 | 40,000 |
Windows and Doors | 6/3/2019 | 8/2/2019 | 60 | 20,000 |
Drywall | 8/3/2019 | 9/12/2019 | 40 | 45,000 |
Interior Design | 9/13/2019 | 10/23/2019 | 40 | 15,000 |
Paint and Wood Finishing | 10/24/2019 | 12/23/2019 | 60 | 40,000 |
Cabinetry | 12/24/2019 | 1/8/2020 | 15 | 40,000 |
Plumbing Fixtures | 12/24/2019 | 1/8/2020 | 15 | 20,000 |
Lighting Fixtures | 12/24/2019 | 1/8/2020 | 15 | 20,000 |
Flooring | 1/9/2020 | 1/30/2020 | 21 | 30,000 |
Interior Decorator and Decorations | 1/31/2020 | 2/20/2020 | 20 | 20,000 |
Exterior Rock | 2/21/2020 | 3/22/2020 | 30 | 50,000 |
Landscaping | 3/23/2020 | 4/15/2020 | 23 | 30,000 |
Cost of Construction | 1,040,000 | |||
Contingency (2%) | 4/16/2020 | 4/30/2020 | 14 | 19,800 |
Total | 1,059,800 |
The major concern at the inception of any project is timely completion within the budgetary allocation. This is however, impossible to achieve without constant monitoring and timely action against deviations if any. The importance of this was recognised by organisations which have project based activities and gave birth to a different organisational structure based on projects. A well prepared project monitoring and control process plan can go a long way in the final outcome and ensure the success of the project.
The monitoring plan is synonymous with the project plan itself and needs to work in close synchronicity with the project activities at each step. It needs to identify the project activity, the resources available, the steps involved and identification of risks involved. Next step would be to measure the progress of activity as per schedule and identify deviations if any in terms of time taken or resources allocated or any external factors which may impact timely completion of project or budgets. Once the deviations are identified there is a need to evaluate the causes for the deviations and then put in immediate control measures to minimize negative impact on project cost and completion. Corrective measures need to be speedily implemented and involve quick decision making as to how and where controls need to be implemented to be most effective. This may entail taking remedial action or at times the plan itself may have certain unrealistic targets and then the plan may itself need to be revised or simply amended for certain tasks. The trine of a realistic project plan, an effective step by step monitoring system to identify deviations earliest and a quick and decisive control process can guarantee completion of a project successfully.
The project monitoring and control samples are listed in the table below :
Unit 5 Project: |
P=project plan D= Deviation |
|||||
Activity Description |
Start Date |
End Date |
Days to complete |
Est $ |
Project monitoring |
Control Process |
Architectural Design |
5/1/2018 |
5/15/2018 |
14 |
50,000 |
Designing as required and does not require P changes |
If any D in cost or design modify allocations |
Procurement of machinery |
5/15/2018 |
5/30/2018 |
15 |
60,000 |
Ensure cost and setup as per P report D |
Verify sourcing is the most viable else try to reduce cost to create buffer |
Hiring Labor |
5/31/2018 |
6/10/2018 |
10 |
120,000 |
Ensure as required and daily desired output can be achieved |
If any D identify cause and explore more viable sourcing Consider overlapping activity 2,3,4 to create an additional 10 day buffer time |
Work and Environmental Permits |
7/27/2018 |
8/6/2018 |
10 |
25,000 |
Ensure all required permits are obtained |
Verify changes in policies which may be advantageous |
Site Security |
8/18/2018 |
4/30/2020 |
731 |
20,000 |
Ensure cross check to secure site no loopholes |
Ensure audit of security measures employed/deployed |
Concrete |
8/18/2018 |
8/31/2018 |
15 |
80,000 |
Best sourcing and quality required standards D if any |
D to be controlled by ensuring right quality and mix at best price change if needed |
Lumber Procurement |
9/1/2018 |
9/11/2018 |
10 |
80,000 |
ditto |
ditto |
Material Storage |
9/1/2018 |
4/30/2020 |
637 |
10,000 |
Should be secure and checks and surveillance installed any excess outflow can be verified here on daily basis |
Ensure P D are checked and identify changes in material requirements identify control measures cuts or rebudget |
Scaffolding Erection |
9/12/2018 |
9/17/2018 |
5 |
25,000 |
Ensure as per design And no D from required strength and on time |
Ditto |
Framing |
9/15/2018 |
1/13/2019 |
120 |
130,000 |
Ditto |
Ditto |
Roofing |
1/14/2019 |
2/13/2019 |
30 |
40,000 |
Ditto |
Ditto |
Plumbing |
2/14/2019 |
3/17/2019 |
30 |
30,000 |
Ditto |
Ditto |
Electrical |
3/18/2019 |
4/17/2019 |
30 |
30,000 |
Ditto |
Ditto |
HVAC |
4/18/2019 |
6/2/2019 |
45 |
40,000 |
Ditto |
Ditto |
Windows and Doors |
6/3/2019 |
8/2/2019 |
60 |
20,000 |
Ditto |
Ditto |
Drywall |
8/3/2019 |
9/12/2019 |
40 |
45,000 |
Ditto |
Ditto |
Interior Design |
9/13/2019 |
10/23/2019 |
40 |
15,000 |
Ditto |
Ditto |
Paint and Wood Finishing |
10/24/2019 |
12/23/2019 |
60 |
40,000 |
Ditto |
Ditto |
Cabinetry |
12/24/2019 |
1/8/2020 |
15 |
40,000 |
Ditto |
Ditto |
Plumbing Fixtures |
12/24/2019 |
1/8/2020 |
15 |
20,000 |
Ditto |
Ditto |
Lighting Fixtures |
12/24/2019 |
1/8/2020 |
15 |
20,000 |
Ditto |
Ditto |
Flooring |
1/9/2020 |
1/30/2020 |
21 |
30,000 |
Ditto |
Ditto |
Interior Decorator and Decorations |
1/31/2020 |
2/20/2020 |
20 |
20,000 |
Ditto |
Ditto |
Exterior Rock |
2/21/2020 |
3/22/2020 |
30 |
50,000 |
Ditto |
Ditto |
Landscaping |
3/23/2020 |
4/15/2020 |
23 |
30,000 |
Ditto |
Ditto |
Cost of Construction |
1,040,000 |
|||||
Contingency (2%) |
4/16/2020 |
4/30/2020 |
14 |
19,800 |
Increase to 4% if possible by above measures |
Ensure D control is quick and contingency requirement is not beyond 2% |
Total |
1,059,800 |
If a project is monitored at every step and activity it facilitates close monitoring to identify deviations immediately and control resultant damage through implementation of corrective measures at the earliest.