In: Electrical Engineering
select an energy alternative to coal.
1) Explain the system engineering tradeoffs based on estimated performance, cost, schedule, or other relevant factors.
2) Explain the decision process and analysis tools used in making your decision.
3)Identify and explain any federal acquisition regulations that affected your decision.
With an installed capacity greater than 137 GWs worldwide and
annual additions of about 40 GWs in recent years,solar photovoltaic
(PV) technology has become an increasingly important energy supply
option. A substantial decline in the cost of solar PV power plants
(80% reduction since 2008) has improved solar PV’s competitiveness,
reducing the needs for subsidies and enabling solar to compete with
other power generation options in some markets. While the majority
of
operating solar projects is in developed economies, the drop in
prices coupled with unreliable grid power and the high cost
of
diesel generators has driven fast-growing interest in solar PV
technology in emerging economies as well.
1. Optimum power plant design: A key project development
challenge is to design a PV power plant that is optimally balanced
in terms of cost and performance for a specific site.
2. Project implementation: Achieving project completion on time and
within budget with a power plant that operates efficiently and
reliably, and generates the expected energy and revenue, is another
key concern for developers. Key aspects of project
implementation include: permits and licensing, selection and
contracting of the Engineering, Procurement and Construction (EPC)
company, power plant construction, and operations and
maintenance
(O&M).
3. Commercial and financing aspects: PV regulatory frameworks and
specific types of incentives/support mechanisms for the development
of PV projects, such
as preferential tariffs and other direct and indirect financial
supports, have an important impact on the financial viability of
the project, as they affect the revenue stream. Power Purchase
Agreements (PPAs)
specify the terms under which the off-taker purchases the power
produced by the PV plant; this is the most important document to
obtain financing.
The key steps for developing a solar PV project are well
established, and yet there is no definitive detailed “road map” a
developer can follow. The approach taken in each project depends on
site-specific parameters and the developer’s priorities, risk
appetite, regulatory requirements, and the types of financing
support mechanisms (i.e., above market rates/subsidies or tax
credits) available in a given market. However, in all cases,
certain activities need to be completed that can broadly be
organized in the following five stages:
1. Concept development and site identification.
2. Prefeasibility study.
3. Feasibility study.
4. Permitting, financing and contracts.
5. Engineering, construction and commercial operation.
ENGINEERING, PROCUREMENT,
CONSTRUCTION AND COMMERCIAL
OPERATION
A single EPC contract is most commonly used for developing PV
plants. In this case, one contractor is responsible for the
complete project. The EPC contractor
is required to confirm the solar energy resource, develop the
detailed design of the PV plant, estimate its energy yield, procure
the equipment according to specifications
agreed upon with the developer, construct the PV plant, carry out
the acceptance tests, and transfer the plant for commercial
operation to its owner/operator.
The EPC contractor will prepare the necessary detail documentation
for the solar PV plant to be tendered and constructed. The
following documentation will be prepared:
• Detailed layout design.
• Detailed civil design (buildings, foundations, drainage,
access roads).
• Detailed electrical design.
• Revised energy yield.
• Construction plans.
• Project schedule.
• Interface matrix.
• Commissioning plans.
Key electrical systems must be designed in rigorous detail. This
will include equipment required for protection, earthing and
interconnection to the grid. The following
designs and specifications should be prepared:
• Overall single line diagrams.
• Medium voltage (MV) and low voltage (LV) switch
gear line diagrams.
• Protection systems.
• Interconnection systems and design.
• Auxiliary power requirements.
• Control systems.
Civil engineering items should be developed to a level suitable for
construction. These will include designs of array foundations and
buildings, as well as roads and infrastructure required for
implementation and operation. The design basis criteria should be
determined
in accordance with national standards and site specific constraints
such as geotechnical conditions.