In: Finance
The most likely outcomes for a particular project are estimated as follows:
Unit price: $ 70
Variable cost: $ 50
Fixed cost: $ 300,000
Expected sales: 40,000 units per year
However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.2 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is 30% and the required rate of return is 12%
. a. What is project NPV in the best-case scenario, that is, assuming all variables take on the best possible value? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)
b. What is project NPV in the worst-case scenario? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)
First lets find out the values of unit sales, sales price, variable cost and Fixed price in best and worst case scenario
Best case | Worst Case | ||
Sales | 40000 | 44000 | 36000 |
Unit price | 70 | 77 | 63 |
Variable cost | 50 | 45 | 55 |
Fixed Cost | 300000 | 270000 | 330000 |
In best case sales price and Unit price will increase by 10% and variable and fix will reduce by 10%
in worst case scenario Sales price and unit price will decrease by 10% and variable and fix will increase by 10%
Present value formula = cash flow/(1+discount rate)^(no of years)
Best case scenario
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |
Initial Investment | -2200000 | |||||||||||
Revenue | 3388000 | 3388000 | 3388000 | 3388000 | 3388000 | 3388000 | 3388000 | 3388000 | 3388000 | 3388000 | ||
Variable cost | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | ||
Fixed Cost | 270000 | 270000 | 270000 | 270000 | 270000 | 270000 | 270000 | 270000 | 270000 | 270000 | ||
Net income | 1138000 | 1138000 | 1138000 | 1138000 | 1138000 | 1138000 | 1138000 | 1138000 | 1138000 | 1138000 | ||
Depreciation amount | 220000 | 220000 | 220000 | 220000 | 220000 | 220000 | 220000 | 220000 | 220000 | 220000 | ||
Taxable Income | 918000 | 918000 | 918000 | 918000 | 918000 | 918000 | 918000 | 918000 | 918000 | 918000 | ||
after Tax income (0.7*Income after dep.) | 642600 | 642600 | 642600 | 642600 | 642600 | 642600 | 642600 | 642600 | 642600 | 642600 | ||
Add back dep. (Cash flow) | 862600 | 862600 | 862600 | 862600 | 862600 | 862600 | 862600 | 862600 | 862600 | 862600 | ||
Present value | -2200000 | 770178.571 | 687659.4 | 613981.6 | 548197.9 | 489462.4 | 437020 | 390196.4 | 348389.7 | 311062.2 | 277734.1 | |
NPV (Sum of present values) | 2673882 |
Worst case Scenario:
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |
Initial Investment | -2200000 | |||||||||||
Revenue | 2268000 | 2268000 | 2268000 | 2268000 | 2268000 | 2268000 | 2268000 | 2268000 | 2268000 | 2268000 | ||
Variable cost | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | 1980000 | ||
Fixed Cost | 330000 | 330000 | 330000 | 330000 | 330000 | 330000 | 330000 | 330000 | 330000 | 330000 | ||
Net income | -42000 | -42000 | -42000 | -42000 | -42000 | -42000 | -42000 | -42000 | -42000 | -42000 | ||
Depreciation amount | 220000 | 220000 | 220000 | 220000 | 220000 | 220000 | 220000 | 220000 | 220000 | 220000 | ||
Taxable Income | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
Add back dep. (Cash flow) | 178000 | 178000 | 178000 | 178000 | 178000 | 178000 | 178000 | 178000 | 178000 | 178000 | ||
Present value | -2200000 | 158928.571 | 141900.5 | 126696.9 | 113122.2 | 101002 | 90180.34 | 80518.16 | 71891.21 | 64188.58 | 57311.24 | |
NPV (Sum of present values) | -1194260 |