Question

In: Finance

The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70...

The most likely outcomes for a particular project are estimated as follows:

Unit price: $ 70

Variable cost: $ 50

Fixed cost: $ 300,000

Expected sales: 40,000 units per year

However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.2 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is 30% and the required rate of return is 12%

. a. What is project NPV in the best-case scenario, that is, assuming all variables take on the best possible value? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

b. What is project NPV in the worst-case scenario? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

Solutions

Expert Solution

First lets find out the values of unit sales, sales price, variable cost and Fixed price in best and worst case scenario

Best case Worst Case
Sales 40000 44000 36000
Unit price 70 77 63
Variable cost 50 45 55
Fixed Cost 300000 270000 330000

In best case sales price and Unit price will increase by 10% and variable and fix will reduce by 10%

in worst case scenario Sales price and unit price will decrease by 10% and variable and fix will increase by 10%

Present value formula = cash flow/(1+discount rate)^(no of years)

Best case scenario

Year 0 1 2 3 4 5 6 7 8 9 10
Initial Investment -2200000
Revenue 3388000 3388000 3388000 3388000 3388000 3388000 3388000 3388000 3388000 3388000
Variable cost 1980000 1980000 1980000 1980000 1980000 1980000 1980000 1980000 1980000 1980000
Fixed Cost 270000 270000 270000 270000 270000 270000 270000 270000 270000 270000
Net income 1138000 1138000 1138000 1138000 1138000 1138000 1138000 1138000 1138000 1138000
Depreciation amount 220000 220000 220000 220000 220000 220000 220000 220000 220000 220000
Taxable Income 918000 918000 918000 918000 918000 918000 918000 918000 918000 918000
after Tax income (0.7*Income after dep.) 642600 642600 642600 642600 642600 642600 642600 642600 642600 642600
Add back dep. (Cash flow) 862600 862600 862600 862600 862600 862600 862600 862600 862600 862600
Present value -2200000 770178.571 687659.4 613981.6 548197.9 489462.4 437020 390196.4 348389.7 311062.2 277734.1
NPV (Sum of present values) 2673882

Worst case Scenario:

Year 0 1 2 3 4 5 6 7 8 9 10
Initial Investment -2200000
Revenue 2268000 2268000 2268000 2268000 2268000 2268000 2268000 2268000 2268000 2268000
Variable cost 1980000 1980000 1980000 1980000 1980000 1980000 1980000 1980000 1980000 1980000
Fixed Cost 330000 330000 330000 330000 330000 330000 330000 330000 330000 330000
Net income -42000 -42000 -42000 -42000 -42000 -42000 -42000 -42000 -42000 -42000
Depreciation amount 220000 220000 220000 220000 220000 220000 220000 220000 220000 220000
Taxable Income 0 0 0 0 0 0 0 0 0 0
Add back dep. (Cash flow) 178000 178000 178000 178000 178000 178000 178000 178000 178000 178000
Present value -2200000 158928.571 141900.5 126696.9 113122.2 101002 90180.34 80518.16 71891.21 64188.58 57311.24
NPV (Sum of present values) -1194260

Related Solutions

The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70 Variable cost: $ 50 Fixed cost: $ 300,000 Expected sales: 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.2 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 420,000 Expected sales: 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 340,000 Expected sales: 35,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.4 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 410,000 Expected sales: 40,000 units per year Modern Artifacts can produce keepsakes that will be sold for $60 each. Nondepreciation fixed costs are $1,400 per year, and variable costs are $30 per unit. The initial investment of $5,000 will be depreciated straight-line over its useful life of 5 years to a final value of zero, and the...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 490,000 Expected sales: 48,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.3 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 420,000 Expected sales: 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 250,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 360,000 Expected sales: 35,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.6 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 380,000 Expected sales: 37,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.7 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 440,000 Expected sales: 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.1 million, which will be depreciated...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT