Question

In: Finance

The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...

The most likely outcomes for a particular project are estimated as follows:

Unit price:

$

60

Variable cost:

$

40

Fixed cost:

$

250,000

Expected sales:

30,000

units per year

However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is 40% and the required rate of return is 10%.

a. What is project NPV in the best-case scenario, that is, assuming all variables take on the best possible value? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

b. What is project NPV in the worst-case scenario? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

Solutions

Expert Solution

Tax rate 40%
Base Case Best Case Worst Case
Units               30,000               33,000        27,000
Sale price                       60                       66                54
Variable cost                       40                       36                44
Sale          1,800,000          2,178,000 1,458,000
Less: Operating Cost          1,200,000          1,188,000 1,188,000
Contribution             600,000             990,000      270,000
Less: Fixed Cost             250,000             225,000      275,000
Less: Depreciation 1200000/10             120,000             120,000      120,000
Profit before tax             230,000             645,000    (125,000)
Tax               92,000             258,000       (50,000)
Profit After Tax             138,000             387,000      (75,000)
Add Depreciation             120,000             120,000      120,000
Cash Profit After tax             258,000             507,000        45,000
Years Best case cash flow Worst case cash flows PV factor @ 10% PV-Best PV-Worst
0        (1,200,000)        (1,200,000)          1.000        (1,200,000)        (1,200,000)
1             507,000               45,000          0.909             460,909               40,909
2             507,000               45,000          0.826             419,008               37,190
3             507,000               45,000          0.751             380,917               33,809
4             507,000               45,000          0.683             346,288               30,736
5             507,000               45,000          0.621             314,807               27,941
6             507,000               45,000          0.564             286,188               25,401
7             507,000               45,000          0.513             260,171               23,092
8             507,000               45,000          0.467             236,519               20,993
9             507,000               45,000          0.424             215,017               19,084
10             507,000               45,000          0.386             195,470               17,349
NPV          1,915,296            (923,494)

Related Solutions

The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 420,000 Expected sales: 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 420,000 Expected sales: 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 340,000 Expected sales: 35,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.4 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 410,000 Expected sales: 40,000 units per year Modern Artifacts can produce keepsakes that will be sold for $60 each. Nondepreciation fixed costs are $1,400 per year, and variable costs are $30 per unit. The initial investment of $5,000 will be depreciated straight-line over its useful life of 5 years to a final value of zero, and the...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 490,000 Expected sales: 48,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.3 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 360,000 Expected sales: 35,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.6 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 380,000 Expected sales: 37,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.7 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 440,000 Expected sales: 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 440,000 Expected sales: 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 40...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 40 Variable cost: $ 20 Fixed cost: $ 350,000 Expected sales: 34,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT