Question

In: Finance

NET PRESENT VALUE EXERCISE You are investing in a container ship to move your products across...

NET PRESENT VALUE EXERCISE

You are investing in a container ship to move your products across the Atlantic Ocean.   Building the ship will cost $2.5 billion, and after operating costs it is expected to bring in $350 million per year for the next 10 years, after which it will have no salvage value. What is the NPV of this project? Assume k = 14%

(Be sure to show your work)

YEAR

NET CASHFLOW

0

($2.5 B)

1

$350 M

2

$350 M

3

$350 M

4

$350 M

5

$350 M

6

$350 M

7

$350 M

8

$350 M

9

$350 M

10

$350 M

What do your results mean? Should you proceed with this project? How would country risk change your considerations?


** Please Answer, Time Sensitive**

Solutions

Expert Solution

Answer:

Initial Investment:

Initial Investment = $2.5 Billion = $2,500 million

Annual Operating Cash flow:

Annual operating income (amount after operating costs) per year for next 10 years = $350 million

Depreciation is an operating expense and hence is assumed that it has been deducted to arrive at operating income. To get annual operating cash flow we have to add it back.

Depreciation = (Cost of ship - Salvage value) /Useful life = (2500 - 0) / 10 = $250 million

Annual operating cash flow = Annual operating income + Depreciation = 350 + 250 = $600 million

PVA Factor:

PV factor for annuity of $1 for 10 years at discount rate of 14% = (1 - 1 / (1 + k) n) / k = (1 - 1 / (1 +14%) 10) / 14%

NPV:

NPV = Annual cash flow * PVA factor - Initial Investment

= 600 * (1 - 1 / (1 +14%) 10 ) / 14% - 2500

= 629.669387776 million

NPV (in nearest cents) = $629,669,387.78

NPV (in millions with two decimal points) = $629.67 millions

The results mean that the project should be accepted. You should proceed with the project since the NPV is positive at $629.67 million.

Country risks could be political risk, economic risks, exchange rate risk, Industry risks, Competitiveness risks etc.

Country risk may change considerations and:

1. We have to factor in political risk, economic risks, exchange rate risk, Industry risks, Competitiveness risks in annual cash flows and initial investment

2. We have to factor in such risks in project duration

3. We can also factor in such risks in discount rate.

We have to reevaluate the project with revised initial investment, annual cash flows, project duration and discount rate.


Related Solutions

Exercise 11-11 Comparison of Projects Using Net Present Value [LO11-2] Labeau Products, Ltd., of Perth, Australia,...
Exercise 11-11 Comparison of Projects Using Net Present Value [LO11-2] Labeau Products, Ltd., of Perth, Australia, has $28,000 to invest. The company is trying to decide between two alternative uses for the funds as follows:    Invest in Project X Invest in Project Y   Investment required $ 28,000    $ 28,000   Annual cash inflows $ 8,000      Single cash inflow at the end of 6 years $ 65,000   Life of the project 6 years 6 years    The company’s discount...
Exercise 13-14 Comparison of Projects Using Net Present Value [LO13-2] Labeau Products, Ltd., of Perth, Australia,...
Exercise 13-14 Comparison of Projects Using Net Present Value [LO13-2] Labeau Products, Ltd., of Perth, Australia, has $18,000 to invest. The company is trying to decide between two alternative uses for the funds as follows: Invest in Project X Invest in Project Y Investment required $ 18,000 $ 18,000 Annual cash inflows $ 7,000 Single cash inflow at the end of 6 years $ 41,000 Life of the project 6 years 6 years The company’s discount rate is 17%. Click...
In the following exercise, calculate the net present value (NPV) at a required return of 15...
In the following exercise, calculate the net present value (NPV) at a required return of 15 percent. Year                                          Cash Flow   0                                 -$1,000 (initial investment) 1                                               95 2                                                  55 Present value = (Future value) / (1+rate)^2 .
Net Present Value
NBA stars Kevin Durant and Chris Paul own a company that faces a 40% tax rate and uses a 14% discount rate. They just invested $677,000 in equipment for the banking app “Goalsetter” that would be depreciated on a straight-line basis to zero over the 6-year life of the project. The equipment will be salvaged for $182,000 at the end of the project. Kevin Durant and Chris Paul know that the project's operating cash flow will be $165,300 per year. What is the NPV of this project if it...
Net present Value
Company A wishes to invest in 4 projects X, W, Y & Z whose net benefits are given in the table below. Project Years   0 1 2 3 4 W (1000) 1200 0 0 0 X (1361.1) 500 500 500 500 Y (1000) 1200 1500 0 0 Z (2000) 1000 0 0 0 Using a discount rate of 10% appraise the 4 projects using the NPV criteria.
Net Present Value Method, An index computed by dividing the total present value of the net...
Net Present Value Method, An index computed by dividing the total present value of the net cash flow to be received from a proposed capital investment by the amount to be invested.Present Value Index, and Analysis for a service company Continental Railroad Company is evaluating three capital investment proposals by using the net present value method. Relevant data related to the proposals are summarized as follows: Maintenance Equipment Ramp Facilities Computer Network Amount to be invested $679,831 $436,634 $209,605 Annual...
The NPV (net present value) of Plan Alpha is $ (130,539) The NPV (net present value)...
The NPV (net present value) of Plan Alpha is $ (130,539) The NPV (net present value) of Plan Beta is $ 233,001 The IRR (internal rate of return) of Plan Alpha is $ 19.36 %. The IRR (internal rate of return) of Plan Beta is $ 21.25 %. Which​ plan, if​ any, should the company​ pursue? Based on the results​ above, the company should pursue Plan Beta because the NPV is positive and the IRR is greater than the​ company's...
Net present value Using a cost of capital of 11​%, calculate the net present value for...
Net present value Using a cost of capital of 11​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable, Initial investment ​(CF 0CF0​) negative 1 comma 143 comma 000−1,143,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 $81,000 2 $138,000 3 $193,000 4 $258,000 5 $311,000 6 $377,000 7 $270,000 8 $98,000 9 $45,000 10 $29,000 The net present value​ (NPV) of the project is _____​$ ​(Round to the nearest​...
Avalon Aviation Products is evaluating a new project. What is the net present value of this...
Avalon Aviation Products is evaluating a new project. What is the net present value of this project if the discount rate is 12% and the net cash flows are as per the following table? Year Cashflow 0 -$5334 1 $8301 2 $4682 3 $9112 4 $20025 5 $24873
Find Net Present Value.
Franklin Company is considering investing in two new vans that are expected to generate combined cash inflows of $32,000 per year. The vans’ combined purchase price is $99,000. The expected life and salvage value of each are seven years and $20,100, respectively. Franklin has an average cost of capital of 12 percent. (PV of $1 and PVA of $1) (Use appropriate factor(s) from the tables provided.)   Required Calculate the net present value of the investment opportunity. (Negative amount should be...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT