Computer Nerds, Inc., is planning a project to develop a commercial software package for PC’s. They have come up with the following list of activities, times and precedence relationships.
Immediate Activity Time
Symbol Activity Description Predecessors (weeks)
P Perform market survey –– 3
D Design graphic icons P 4
F Develop flow chart P 2
S Design input/output screens D, F 6
U Code Module 1 F 5
V Code Module 2 F 3
W Code Module 3 U 7
X Code Module 4 U, V 5
T Merge modules & Test program S, W, X 8